Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Ongoing

Yash Empire

Survey No.466,525,526,527

Commercial67 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/10099

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/CAA07231/210620

Yash Empire — residential developmentGandhinagar · representative residential imagery

Paperwork score

Material gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusOngoing
Quarterly filings8 / 17
Recorded complaints1
ExtensionsNone recorded
Promoter projects1 completed

Project at a glance

Developer
Riddhi Infra Build Tech Llp
Project type
Commercial
Total units
67
Project cost
₹14.22 Cr
Carpet area
4,234.7 sq m
Price band
₹7L – ₹0L
Carpet area per unit
22.13-135.4 sq m
Status
Ongoing
Filing extras — blocks, inventory lines, dates
  • Commercial — 67 units · carpet 4,234.71 sq m
  • Block Building 1
  • Declared start 2020-02-21 · completion 2024-09-30
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.1583° N, 72.6348° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

67

Total units

5

Booked (7%)

62

Unsold (93%)

7% booked · 93% unsold

Tower Building 167 units

5 booked (7%) · 62 available (93%)

Flat-level inventory (67 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
1Building 141.51UNBOOKED
2Building 141.84UNBOOKED
3Building 141.84UNBOOKED
4Building 149.25UNBOOKED
5Building 138.7UNBOOKED
6Building 134.64UNBOOKED
7Building 134.45UNBOOKED
8Building 147.43BOOKED
9Building 147.89BOOKED
10Building 147.78BOOKED
11Building 138.71UNBOOKED
12Building 141.33UNBOOKED
101Building 1100.2UNBOOKED
102Building 139.91UNBOOKED
103Building 139.78UNBOOKED
104Building 132.19UNBOOKED
105Building 125.17UNBOOKED
106Building 124.94UNBOOKED
107Building 138.08UNBOOKED
108Building 138.54UNBOOKED
109Building 138.54UNBOOKED
110Building 1129.51UNBOOKED
201Building 1100.2UNBOOKED
202Building 139.91UNBOOKED
203Building 139.78UNBOOKED
204Building 132.19UNBOOKED
205Building 125.17UNBOOKED
206Building 124.94UNBOOKED
207Building 138.08UNBOOKED
208Building 138.54UNBOOKED
209Building 138.54UNBOOKED
210Building 1129.51UNBOOKED
301Building 197.05UNBOOKED
302Building 1123.13UNBOOKED
303Building 133.63UNBOOKED
304Building 133.63UNBOOKED
305Building 133.63UNBOOKED
306Building 1135.4UNBOOKED
307Building 1103.91UNBOOKED
401Building 197.05UNBOOKED
402Building 1123.13UNBOOKED
403Building 130.75UNBOOKED
404Building 130.75UNBOOKED
405Building 130.75UNBOOKED
406Building 1135.4UNBOOKED
407Building 1103.91UNBOOKED
501Building 197.05UNBOOKED
502Building 1123.13UNBOOKED
503Building 127.88UNBOOKED
504Building 127.88UNBOOKED
505Building 127.88UNBOOKED
506Building 1135.4UNBOOKED
507Building 1103.91UNBOOKED
601Building 197.05UNBOOKED
602Building 1123.13UNBOOKED
603Building 125UNBOOKED
604Building 125UNBOOKED
605Building 125UNBOOKED
606Building 1135.4UNBOOKED
607Building 1103.91UNBOOKED
701Building 197.05UNBOOKED
702Building 1123.13UNBOOKED
703Building 122.13BOOKED
704Building 122.13BOOKED
705Building 122.13UNBOOKED
706Building 1135.4UNBOOKED
707Building 1103.91UNBOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 41.65%
0%25%50%75%100%202020212022November 2020 — 12.75% builtFebruary 2021 — 15.94% builtMay 2021 — 19.12% builtAugust 2021 — 19.12% builtNovember 2021 — 23.91% builtFebruary 2022 — 36.02% builtMay 2022 — 39.21% builtAugust 2022 — 41.65% built

8 quarterly returns · November 2020 (12.75%) to August 2022 (41.65%)

12.75%

Initial progress · November 2020

41.65%

Final progress · August 2022

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2020

    Registration

  2. 2021

    Annual Compliance · BCR

  3. 2023

    Annual Compliance

  4. 2024

    Complaint

  5. 2025

    Challan

  6. Undated

    Challan · Annual Compliance

  7. 2026

    Snapshot reviewed

Full application ledger (9 rows)
  1. Registration — 2020-06-21 21:47:02.000000
  2. Complaint — 2024-04-25 16:10:12 · GJ/CMP/NCQR/Gandhinagar/230224/0079 (CLOSED)
  3. Challan — undated · GJ/CMP/NCQR/Gandhinagar/230224/0079 (status not published)
  4. Challan — 2025-09-29 13:22:21 · GJ/CMP/NCQR/Gandhinagar/230224/0079 (status not published)
  5. Annual Compliance — 2021-12-31 17:47:55
  6. Annual Compliance — 2023-11-17 21:14:28
  7. Annual Compliance — 2023-11-17 21:14:28
  8. Annual Compliance — undated
  9. BCR — 2021-03-26 12:53:07.000000

Quarterly filing history

2020

Q-1

2021

Q-2 · Q-3 · Q-4 · Q-5

2022

Q-6 · Q-7 · Q-8

—

Q-9 · Q-10 · Q-11 · Q-12 · Q-13 · Q-14 · X-1 · X-2 · Q-E

8 submitted · 9 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/CAA07231/210620 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Kudasan
TP scheme
( KUDASAN-KOBA )
Final / sub plot
-
Authority
Gandhinagar Urban Development Authority
Covered area
703 sq m
Open area
854 sq m
Land cost
₹3.77 Cr
Estimated cost
₹10.45 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/200603/009084
Covered parking
80 · 1695 sq m
Parking for sale
10

Escrow account

Bank
STATE BANK OF INDIA
Branch
Plot No 17,Cinemax Complex,Suman City ,Sector 11,Gandhinagar
IFSC
SBIN0032214
Account
XXXX-0212
Closing
₹0 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
ARPIT SHAH
Site visit
2022-06-28
Form-1 PDF
Open file
  • Block Building 149%
Phase actual dates (1 block)
  • Block Building 1: excavation — → slab —

Filing PDFs

Project team on record

  • Vasant Soni · engineer
  • ARPIT SHAH · architect
How is the paperwork score calculated?57 / 100
  • Delivery standing

    24 / 40

  • Filing discipline

    12 / 25

  • Promoter track record

    10 / 20

  • Complaints and extensions

    11 / 15

  • Delivery 2024-09-30 elapsed 1 yr ago, progress 41.65% -> 24/40
  • QPR filings 8/17 -> 12/25
  • Promoter completed projects 1 -> 10/20
  • Red flags 1 complaint + 0 extensions -> 11/15

Confidence Medium: declared completion date elapsed 1 year ago with work still declared incomplete; QPR filing rate 47.1% is below 90%; 1 complaint entry on the ledger.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/CAA07231/210620

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.