Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Ongoing

Siddharth Heights 1

SURVEY NO 822/2 NEAR SIDDHARTH HEIGHTS

ResidentialGroup Housing80 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/10323

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA07322/140820

Siddharth Heights 1 — residential developmentGandhinagar · representative residential imagery

Paperwork score

Material gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusOngoing
Quarterly filings12 / 12
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Siddharth Developers
Project type
Residential / Group Housing
Total units
80
Project cost
₹14.23 Cr
Carpet area
5,297.9 sq m
Price band
₹16L – ₹0L
Carpet area per unit
61.15-71.64 sq m
Status
Ongoing
Filing extras — blocks, inventory lines, dates
  • Residential/Group Housing — 80 units · carpet 5,297.92 sq m
  • Block A
  • Block B
  • Declared start 2020-07-01 · completion 2023-07-01
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.2214° N, 72.6155° E

Filed plot outline · 7 corners
Open in Google Maps

Units & inventory

80

Total units

61

Booked (76%)

19

Unsold (24%)

76% booked · 24% unsold

Tower A32 units

29 booked (91%) · 3 available (9%)

Tower B48 units

32 booked (67%) · 16 available (33%)

Flat-level inventory (80 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
101A71.64BOOKED
102A71.64BOOKED
103A71.64BOOKED
104A71.64BOOKED
201A71.64BOOKED
202A71.64BOOKED
203A71.64BOOKED
204A71.64BOOKED
301A71.64BOOKED
302A71.64BOOKED
303A71.64UNBOOKED
304A71.64BOOKED
401A71.64BOOKED
402A71.64BOOKED
403A71.64BOOKED
404A71.64BOOKED
501A71.64BOOKED
502A71.64BOOKED
503A71.64BOOKED
504A71.64BOOKED
601A71.64BOOKED
602A71.64BOOKED
603A71.64BOOKED
604A71.64BOOKED
701A71.64BOOKED
702A71.64UNBOOKED
703A71.64BOOKED
704A71.64BOOKED
801A71.64BOOKED
802A71.64UNBOOKED
803A71.64BOOKED
804A71.64BOOKED
101B64.42UNBOOKED
102B64.42UNBOOKED
103B61.15BOOKED
104B62.27UNBOOKED
105B62.27UNBOOKED
106B61.15UNBOOKED
201B64.42UNBOOKED
202B64.42BOOKED
203B61.15BOOKED
204B62.27BOOKED
205B62.27UNBOOKED
206B61.15UNBOOKED
301B64.42BOOKED
302B64.42BOOKED
303B61.15BOOKED
304B62.27BOOKED
305B62.27BOOKED
306B61.15BOOKED
401B64.42BOOKED
402B64.42BOOKED
403B61.15BOOKED
404B62.27BOOKED
405B62.27BOOKED
406B61.15UNBOOKED
501B64.42BOOKED
502B64.42BOOKED
503B61.15BOOKED
504B62.27BOOKED
505B62.27BOOKED
506B61.15BOOKED
601B64.42BOOKED
602B64.42BOOKED
603B61.15BOOKED
604B62.27BOOKED
605B62.27BOOKED
606B61.15UNBOOKED
701B64.42BOOKED
702B64.42BOOKED
703B61.15BOOKED
704B62.27BOOKED
705B62.27UNBOOKED
706B61.15UNBOOKED
801B64.42UNBOOKED
802B64.42BOOKED
803B61.15BOOKED
804B62.27UNBOOKED
805B62.27UNBOOKED
806B61.15UNBOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 98.24%
0%25%50%75%100%202120222023January 2021 — 39.52% builtApril 2021 — 43.99% builtJuly 2021 — 45.71% builtOctober 2021 — 48.45% builtJanuary 2022 — 52.06% builtApril 2022 — 66.51% builtJuly 2022 — 72.04% builtOctober 2022 — 95.06% builtJanuary 2023 — 95.59% builtApril 2023 — 97.53% builtJuly 2023 — 98.24% builtAugust 2023 — 98.24% built

12 quarterly returns · January 2021 (39.52%) to August 2023 (98.24%)

39.52%

Initial progress · January 2021

98.24%

Final progress · August 2023

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2020

    Registration

  2. 2021

    Annual Compliance

  3. 2023

    Annual Compliance

  4. Undated

    Annual Compliance

  5. 2026

    Snapshot reviewed

Full application ledger (4 rows)
  1. Registration — 2020-08-14 10:50:32.000000
  2. Annual Compliance — 2021-12-13 18:02:44
  3. Annual Compliance — 2023-11-17 21:14:55
  4. Annual Compliance — undated

Quarterly filing history

2020

Q-1

2021

Q-2 · Q-3 · Q-4 · Q-5

2022

Q-6 · Q-7 · Q-8 · Q-9

2023

Q-10 · Q-11 · Q-E

12 submitted · 0 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA07322/140820 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Vavol
Final / sub plot
-
Authority
Gandhinagar Urban Development Authority
Covered area
873.05 sq m
Open area
1125.95 sq m
Land cost
₹1.07 Cr
Estimated cost
₹13.16 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/200717/009282
Covered parking
40 · 859.98 sq m
Parking for sale
80

Escrow account

Bank
Kotak Mahindra Bank
Branch
GH ROAD GANDHINAGAR
IFSC
KKBK0000879
Account
XXXX-3600
Deposited
₹1.16 Cr
Withdrawn
₹0.89 Cr
Closing
₹0.34 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
JAY SUTHAR
Site visit
2023-05-19
Form-1 PDF
Open file
  • Block A100%
  • Block B100%
Phase actual dates (2 blocks)
  • Block A: excavation — → slab —
  • Block B: excavation — → slab —

Filing PDFs

Project team on record

  • RONAK S GAJJAR · engineer
  • JAY SUTHAR · architect
How is the paperwork score calculated?52 / 100
  • Delivery standing

    12 / 40

  • Filing discipline

    25 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2023-07-01 elapsed 3 yr ago, progress 98.24% -> 12/40
  • QPR filings 12/12 -> 25/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: declared completion date elapsed 3 years ago with work still declared incomplete; no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA07322/140820

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.