Akshar Tirth
R.S. No. 63/1/P+63/2/P+63/3/P, F.P. No. 62+63+64
Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA07449/110920
Paperwork score
Some gaps
A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.
Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.
Project at a glance
- Developer
- Akshar Infrastructure
- Project type
- Residential / Group Housing
- Total units
- 142
- Project cost
- ₹24.51 Cr
- Carpet area
- 8,888.7 sq m
- Price band
- ₹3L – ₹0L
- Carpet area per unit
- 58.67-77.12 sq m
- Status
- Ongoing
Filing extras — blocks, inventory lines, dates
- Residential/Group Housing — 142 units · carpet 8,888.72 sq m
- Block BLOCK A+B
- Block BLOCK C+D
- Block BLOCK E
- Declared start 2020-06-14 · completion 2025-06-09
- Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised
Location
23.2713° N, 72.6661° E
Units & inventory
142
Total units
142
Booked (100%)
0
Unsold (0%)
100% booked · 0% unsold
56 booked (100%) · 0 available (0%)
56 booked (100%) · 0 available (0%)
30 booked (100%) · 0 available (0%)
Flat-level inventory (142 units)
| Flat | Block | Carpet m² | Status |
|---|---|---|---|
| A-3 | BLOCK A+B | 58.67 | BOOKED |
| A-4 | BLOCK A+B | 58.67 | BOOKED |
| A-101 | BLOCK A+B | 58.67 | BOOKED |
| A-102 | BLOCK A+B | 58.67 | BOOKED |
| A-103 | BLOCK A+B | 58.67 | BOOKED |
| A-104 | BLOCK A+B | 58.67 | BOOKED |
| A-201 | BLOCK A+B | 58.67 | BOOKED |
| A-202 | BLOCK A+B | 58.67 | BOOKED |
| A-203 | BLOCK A+B | 58.67 | BOOKED |
| A-204 | BLOCK A+B | 58.67 | BOOKED |
| A-301 | BLOCK A+B | 58.67 | BOOKED |
| A-302 | BLOCK A+B | 58.67 | BOOKED |
| A-303 | BLOCK A+B | 58.67 | BOOKED |
| A-304 | BLOCK A+B | 58.67 | BOOKED |
| A-401 | BLOCK A+B | 58.67 | BOOKED |
| A-402 | BLOCK A+B | 58.67 | BOOKED |
| A-403 | BLOCK A+B | 58.67 | BOOKED |
| A-404 | BLOCK A+B | 58.67 | BOOKED |
| A-501 | BLOCK A+B | 58.67 | BOOKED |
| A-502 | BLOCK A+B | 58.67 | BOOKED |
| A-503 | BLOCK A+B | 58.67 | BOOKED |
| A-504 | BLOCK A+B | 58.67 | BOOKED |
| A-601 | BLOCK A+B | 58.67 | BOOKED |
| A-602 | BLOCK A+B | 58.67 | BOOKED |
| A-603 | BLOCK A+B | 58.67 | BOOKED |
| A-604 | BLOCK A+B | 58.67 | BOOKED |
| A-702 | BLOCK A+B | 59.18 | BOOKED |
| A-703 | BLOCK A+B | 59.18 | BOOKED |
| B-1 | BLOCK A+B | 58.67 | BOOKED |
| B-2 | BLOCK A+B | 58.67 | BOOKED |
| B-101 | BLOCK A+B | 58.67 | BOOKED |
| B-102 | BLOCK A+B | 58.67 | BOOKED |
| B-103 | BLOCK A+B | 58.67 | BOOKED |
| B-104 | BLOCK A+B | 58.67 | BOOKED |
| B-201 | BLOCK A+B | 58.67 | BOOKED |
| B-202 | BLOCK A+B | 58.67 | BOOKED |
| B-203 | BLOCK A+B | 58.67 | BOOKED |
| B-204 | BLOCK A+B | 58.67 | BOOKED |
| B-301 | BLOCK A+B | 58.67 | BOOKED |
| B-302 | BLOCK A+B | 58.67 | BOOKED |
| B-303 | BLOCK A+B | 58.67 | BOOKED |
| B-304 | BLOCK A+B | 58.67 | BOOKED |
| B-401 | BLOCK A+B | 58.67 | BOOKED |
| B-402 | BLOCK A+B | 58.67 | BOOKED |
| B-403 | BLOCK A+B | 58.67 | BOOKED |
| B-404 | BLOCK A+B | 58.67 | BOOKED |
| B-501 | BLOCK A+B | 58.67 | BOOKED |
| B-502 | BLOCK A+B | 58.67 | BOOKED |
| B-503 | BLOCK A+B | 58.67 | BOOKED |
| B-504 | BLOCK A+B | 58.67 | BOOKED |
| B-601 | BLOCK A+B | 58.67 | BOOKED |
| B-602 | BLOCK A+B | 58.67 | BOOKED |
| B-603 | BLOCK A+B | 58.67 | BOOKED |
| B-604 | BLOCK A+B | 58.67 | BOOKED |
| B-702 | BLOCK A+B | 59.18 | BOOKED |
| B-703 | BLOCK A+B | 59.18 | BOOKED |
| C-3 | BLOCK C+D | 58.67 | BOOKED |
| C-4 | BLOCK C+D | 58.67 | BOOKED |
| C-101 | BLOCK C+D | 58.67 | BOOKED |
| C-102 | BLOCK C+D | 58.67 | BOOKED |
| C-103 | BLOCK C+D | 58.67 | BOOKED |
| C-104 | BLOCK C+D | 58.67 | BOOKED |
| C-201 | BLOCK C+D | 58.67 | BOOKED |
| C-202 | BLOCK C+D | 58.67 | BOOKED |
| C-203 | BLOCK C+D | 58.67 | BOOKED |
| C-204 | BLOCK C+D | 58.67 | BOOKED |
| C-301 | BLOCK C+D | 58.67 | BOOKED |
| C-302 | BLOCK C+D | 58.67 | BOOKED |
| C-303 | BLOCK C+D | 58.67 | BOOKED |
| C-304 | BLOCK C+D | 58.67 | BOOKED |
| C-401 | BLOCK C+D | 58.67 | BOOKED |
| C-402 | BLOCK C+D | 58.67 | BOOKED |
| C-403 | BLOCK C+D | 58.67 | BOOKED |
| C-404 | BLOCK C+D | 58.67 | BOOKED |
| C-501 | BLOCK C+D | 58.67 | BOOKED |
| C-502 | BLOCK C+D | 58.67 | BOOKED |
| C-503 | BLOCK C+D | 58.67 | BOOKED |
| C-504 | BLOCK C+D | 58.67 | BOOKED |
| C-601 | BLOCK C+D | 58.67 | BOOKED |
| C-602 | BLOCK C+D | 58.67 | BOOKED |
| C-603 | BLOCK C+D | 58.67 | BOOKED |
| C-604 | BLOCK C+D | 58.67 | BOOKED |
| C-702 | BLOCK C+D | 59.18 | BOOKED |
| C-703 | BLOCK C+D | 59.18 | BOOKED |
| D-1 | BLOCK C+D | 58.67 | BOOKED |
| D-2 | BLOCK C+D | 58.67 | BOOKED |
| D-101 | BLOCK C+D | 58.67 | BOOKED |
| D-102 | BLOCK C+D | 58.67 | BOOKED |
| D-103 | BLOCK C+D | 58.67 | BOOKED |
| D-104 | BLOCK C+D | 58.67 | BOOKED |
| D-201 | BLOCK C+D | 58.67 | BOOKED |
| D-202 | BLOCK C+D | 58.67 | BOOKED |
| D-203 | BLOCK C+D | 58.67 | BOOKED |
| D-204 | BLOCK C+D | 58.67 | BOOKED |
| D-301 | BLOCK C+D | 58.67 | BOOKED |
| D-302 | BLOCK C+D | 58.67 | BOOKED |
| D-303 | BLOCK C+D | 58.67 | BOOKED |
| D-304 | BLOCK C+D | 58.67 | BOOKED |
| D-401 | BLOCK C+D | 58.67 | BOOKED |
| D-402 | BLOCK C+D | 58.67 | BOOKED |
| D-403 | BLOCK C+D | 58.67 | BOOKED |
| D-404 | BLOCK C+D | 58.67 | BOOKED |
| D-501 | BLOCK C+D | 58.67 | BOOKED |
| D-502 | BLOCK C+D | 58.67 | BOOKED |
| D-503 | BLOCK C+D | 58.67 | BOOKED |
| D-504 | BLOCK C+D | 58.67 | BOOKED |
| D-601 | BLOCK C+D | 58.67 | BOOKED |
| D-602 | BLOCK C+D | 58.67 | BOOKED |
| D-603 | BLOCK C+D | 58.67 | BOOKED |
| D-604 | BLOCK C+D | 58.67 | BOOKED |
| D-702 | BLOCK C+D | 59.18 | BOOKED |
| D-703 | BLOCK C+D | 59.18 | BOOKED |
| E-1 | BLOCK E | 77.12 | BOOKED |
| E-2 | BLOCK E | 77.12 | BOOKED |
| E-101 | BLOCK E | 77.12 | BOOKED |
| E-102 | BLOCK E | 77.12 | BOOKED |
| E-103 | BLOCK E | 77.12 | BOOKED |
| E-104 | BLOCK E | 77.12 | BOOKED |
| E-201 | BLOCK E | 77.12 | BOOKED |
| E-202 | BLOCK E | 77.12 | BOOKED |
| E-203 | BLOCK E | 77.12 | BOOKED |
| E-204 | BLOCK E | 77.12 | BOOKED |
| E-301 | BLOCK E | 77.12 | BOOKED |
| E-302 | BLOCK E | 77.12 | BOOKED |
| E-303 | BLOCK E | 77.12 | BOOKED |
| E-304 | BLOCK E | 77.12 | BOOKED |
| E-401 | BLOCK E | 77.12 | BOOKED |
| E-402 | BLOCK E | 77.12 | BOOKED |
| E-403 | BLOCK E | 77.12 | BOOKED |
| E-404 | BLOCK E | 77.12 | BOOKED |
| E-501 | BLOCK E | 77.12 | BOOKED |
| E-502 | BLOCK E | 77.12 | BOOKED |
| E-503 | BLOCK E | 77.12 | BOOKED |
| E-504 | BLOCK E | 77.12 | BOOKED |
| E-601 | BLOCK E | 77.12 | BOOKED |
| E-602 | BLOCK E | 77.12 | BOOKED |
| E-603 | BLOCK E | 77.12 | BOOKED |
| E-604 | BLOCK E | 77.12 | BOOKED |
| E-701 | BLOCK E | 77.12 | BOOKED |
| E-702 | BLOCK E | 77.12 | BOOKED |
| E-703 | BLOCK E | 77.12 | BOOKED |
| E-704 | BLOCK E | 77.12 | BOOKED |
Booking status as filed — confirm availability with the builder.
Construction progress
Reported completion: 87.25%13 quarterly returns · February 2021 (21.78%) to July 2025 (87.25%)
21.78%
Initial progress · February 2021
87.25%
Final progress · July 2025
Builder-declared quarterly returns — not an independent inspection.
RERA activity timeline
2020
Registration
2023
Annual Compliance
2024
Annual Compliance
2025
Annual Compliance
2026
Snapshot reviewed
Full application ledger (6 rows)
- Registration — 2020-09-11 15:44:30.000000
- Annual Compliance — 2023-11-17 21:15:21
- Annual Compliance — 2023-11-17 21:15:21
- Annual Compliance — 2023-11-17 21:15:21
- Annual Compliance — 2024-10-27 20:00:36
- Annual Compliance — 2025-10-30 12:37:23
Quarterly filing history
2021
Q-1 · Q-2 · Q-3 · Q-4
2022
Q-5 · Q-6 · Q-7 · Q-8
2023
Q-9 · Q-10 · Q-11
—
Q-12 · Q-14 · Q-15 · Q-16 · Q-17 · Q-18
2024
Q-13 · Q-E
13 submitted · 6 missing
Documents on file
42 documentsMissing from this record: Registration certificate.
Registration (0)Registration certificate
- None on this record.
Land & title (4)Title · EC · Clearance
4 of 4 open directly
Approvals (6)Plans · CC · NOCs
- Commencement certificate
- Sanctioned plan
- Approved layout plan
- Approved building plan
- Area development plan
- NOCs from authorities
6 of 6 open directly
Builder finances (22)Accounts · ITR · Audit reports
- Auditor's report (1 of 3)
- Auditor's report (2 of 3)
- Auditor's report (3 of 3)
- Director's report (1 of 3)
- Director's report (2 of 3)
- Director's report (3 of 3)
- Income-tax return (1 of 3)
- Income-tax return (2 of 3)
- Income-tax return (3 of 3)
- PAN card
- auditedBalSheetDoc1
- auditedBalSheetDoc2_
- auditedBalSheetDoc3
- auditedProfitLossSheetDoc1
- auditedProfitLossSheetDoc2
- auditedProfitLossSheetDoc3
- auditedReportDoc1
- auditedReportDoc2
- auditedReportDoc3
- cashFlowStmtFileDoc1
- cashFlowStmtFileDoc2
- cashFlowStmtFileDoc3
22 of 22 open directly
Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.
View documents on GujRERASearch PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA07449/110920 → Documents tab
Filing depth
Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.
Land & money
- Village (moje)
- Pethapur
- TP scheme
- (Pethapur)
- Final / sub plot
- -
- Authority
- Gandhinagar Urban Development Authority
- Covered area
- 1631 sq m
- Open area
- 2849 sq m
- Land cost
- ₹5.65 Cr
- Estimated cost
- ₹30.16 Cr
- BU permission
- Registration cert
- Portal file
- Ack no.
- PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/200811/009456
- Covered parking
- 124 · 4012 sq m
- Parking for sale
- 11
Escrow account
- Bank
- IDFC Bank
- Branch
- Ground Floor,Plot No ,Sector 16,GH Road,Gandhinagar
- IFSC
- IDFB0042343
- Account
- XXXX-5322
- Deposited
- ₹0.78 Cr
- Withdrawn
- ₹1.1 Cr
- Closing
- ₹0 Cr
- Status
- APPROVED
Inspection phases (Form-1)
- Architect
- ARPIT PRIYAVADAN MEENA SHAH
- Firm
- Grey Leaf
- Site visit
- 2024-04-03
- Form-1 PDF
- Open file
- Block BLOCK A+B85%
- Block BLOCK C+D85%
- Block BLOCK E85%
Phase actual dates (3 blocks)
- Block BLOCK E: excavation → slab
- Block BLOCK A+B: excavation → slab
- Block BLOCK C+D: excavation → slab
Filing PDFs
- REG_PROCESS · 2020-08-06 — Form-1 · Form-2
- Q-1 · 2021-01-07 — Form-1 · Form-2
- Q-2 · 2021-04-07 — Form-1 · Form-2
- Q-3 · 2021-07-07 — Form-1 · Form-2
- Q-4 · 2021-10-06 — Form-1 · Form-2
- Q-5 · 2022-01-07 — Form-1 · Form-2
- Q-6 · 2022-04-06 — Form-1 · Form-2
- Q-7 · 2022-07-07 — Form-1 · Form-2
- Q-8 · 2022-10-07 — Form-1 · Form-2
- Q-9 · 2023-01-07 — Form-1 · Form-2
- Q-10 · 2023-04-06 — Form-1 · Form-2
- Q-11 · 2023-07-07 — Form-1 · Form-2
- Q-13 · 2024-03-06 — Form-1 · Form-2
- Q-E · 2024-04-20 — Form-1 · Form-2
- Form-5 · 2020-21 · SUBMITTED — Audit file
- Form-5 · 2021-22 · SUBMITTED — Audit file
- Form-5 · 2022-23 · SUBMITTED — Audit file
- Form-5 · 2023-24 · SUBMITTED — Audit file
- Form-5 · 2024-25 · SUBMITTED — Audit file
Project team on record
- Vasant Soni-Torsion Engineers & Consultants · engineer
- Arpit Shah-Grey Leaf · architect
How is the paperwork score calculated?66 / 100
Delivery standing
24 / 40
Filing discipline
17 / 25
Promoter track record
10 / 20
Complaints and extensions
15 / 15
- Delivery 2025-06-09 elapsed 1 yr ago, progress 87.25% -> 24/40
- QPR filings 13/19 -> 17/25
- Promoter completed projects 1 -> 10/20
- Red flags 0 complaints + 0 extensions -> 15/15
Confidence Medium: declared completion date elapsed 1 year ago with work still declared incomplete; QPR filing rate 68.4% is below 90%.
Verify this yourself
If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:
PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA07449/110920
Open this project on GujRERARun the manual check →Sources
Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.
- MoHUA - Real Estate Regulatory Authorities of States / UTsThe national index of every state/UT RERA portal. Fallback when a state link moves.
- GujRERA - Gujarat Real Estate Regulatory AuthorityGujarat project / agent / complaint search and registrations.