Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Ongoing

Sahjanand Srushti

F.P. No.439/8

Mixed Development76 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/10622

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA07592/EX1/300623

Sahjanand Srushti — residential developmentGandhinagar · representative residential imagery

Paperwork score

Material gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusOngoing
Quarterly filings11 / 13
Recorded complaints1
Extensions1
Promoter projects1 completed

Project at a glance

Developer
Shreeji Construction
Project type
Mixed Development
Total units
76
Project cost
₹11.2 Cr
Carpet area
3,856.1 sq m
Price band
₹5L – ₹0L
Carpet area per unit
16.84-58.97 sq m
Status
Ongoing
Filing extras — blocks, inventory lines, dates
  • Mixed Development — 76 units · carpet 3,856.08 sq m
  • Block A+B
  • Declared start 2020-08-01 · completion 2024-03-31
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.1920° N, 72.6052° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

76

Total units

65

Booked (86%)

11

Unsold (14%)

86% booked · 14% unsold

Tower A+B76 units

65 booked (86%) · 11 available (14%)

Flat-level inventory (76 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
01A+B28.36UNBOOKED
02A+B26.03BOOKED
03A+B29.06UNBOOKED
04A+B28.36BOOKED
05A+B28.36BOOKED
06A+B26.03BOOKED
07A+B23.15UNBOOKED
08A+B23.15BOOKED
101A+B28.36BOOKED
102A+B18.93BOOKED
103A+B21.13BOOKED
104A+B20.62UNBOOKED
105A+B20.62UNBOOKED
106A+B18.93UNBOOKED
107A+B16.84UNBOOKED
108A+B23.15UNBOOKED
A-101A+B57.89UNBOOKED
A-102A+B57.89BOOKED
B-101A+B57.89BOOKED
A-201A+B57.89BOOKED
A-202A+B57.89BOOKED
A-203A+B57.89BOOKED
A-204A+B57.89BOOKED
A-301A+B57.89BOOKED
A-302A+B57.89BOOKED
A-303A+B57.89BOOKED
A-304A+B57.89BOOKED
A-401A+B57.89BOOKED
A-402A+B57.89BOOKED
A-403A+B57.89BOOKED
A-404A+B57.89BOOKED
A-501A+B57.89BOOKED
A-502A+B57.89BOOKED
A-503A+B57.89BOOKED
A-504A+B57.89BOOKED
A-601A+B57.89BOOKED
A-602A+B57.89BOOKED
A-603A+B57.89BOOKED
A-604A+B57.89BOOKED
A-701A+B57.89BOOKED
A-702A+B57.89BOOKED
A-703A+B57.89BOOKED
A-704A+B57.89BOOKED
A-801A+B57.89BOOKED
A-802A+B57.89BOOKED
A-803A+B57.89UNBOOKED
A-804A+B57.89UNBOOKED
A-901A+B57.89BOOKED
A-902A+B57.89BOOKED
A-903A+B57.89BOOKED
A-904A+B57.89BOOKED
A-1001A+B57.89BOOKED
A-1002A+B57.89BOOKED
A-1003A+B57.89BOOKED
A-1004A+B57.89BOOKED
A-1102A+B58.97BOOKED
A-1103A+B58.41BOOKED
B-201A+B57.89BOOKED
B-202A+B57.89BOOKED
B-301A+B57.89BOOKED
B-302A+B57.89BOOKED
B-401A+B57.89BOOKED
B-402A+B57.89BOOKED
B-501A+B57.89BOOKED
B-502A+B57.89BOOKED
B-601A+B57.89BOOKED
B-602A+B57.89BOOKED
B-701A+B57.89BOOKED
B-702A+B57.89BOOKED
B-801A+B57.89BOOKED
B-802A+B57.89BOOKED
B-901A+B57.89BOOKED
B-902A+B57.89BOOKED
B-1001A+B57.89BOOKED
B-1002A+B57.89BOOKED
B-1102A+B57.89BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 89.38%
0%25%50%75%100%2021202220232024March 2021 — 39.52% builtJune 2021 — 44.31% builtSeptember 2021 — 57.27% builtDecember 2021 — 62.69% builtMarch 2022 — 69.91% builtJune 2022 — 70.71% builtSeptember 2022 — 71.51% builtDecember 2022 — 78.47% builtSeptember 2023 — 97.27% builtDecember 2023 — 86.65% builtApril 2024 — 89.38% built

11 quarterly returns · March 2021 (39.52%) to April 2024 (89.38%)

39.52%

Initial progress · March 2021

89.38%

Final progress · April 2024

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2020

    Registration

  2. 2022

    Annual Compliance

  3. 2023

    Extension · Annual Compliance

  4. 2024

    Complaint · Challan · Annual Compliance

  5. 2026

    Snapshot reviewed

Full application ledger (8 rows)
  1. Registration — 2020-10-23 15:41:10.000000
  2. Extension — 2023-06-30 17:04:10
  3. Complaint — 2024-09-18 17:03:43 · CMP0106202400822 (CLOSED)
  4. Challan — 2024-10-22 17:09:43 · CMP0106202400822 (status not published)
  5. Annual Compliance — 2022-02-18 20:22:14
  6. Annual Compliance — 2023-11-17 21:15:36
  7. Annual Compliance — 2023-11-17 21:15:36
  8. Annual Compliance — 2024-11-25 15:08:59

Quarterly filing history

2021

Q-1 · Q-2 · Q-3 · Q-4

2022

Q-5 · Q-6 · Q-7

2023

Q-8 · X-2

—

Q-9 · X-1

2024

X-3 · Q-E

11 submitted · 2 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA07592/EX1/300623 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Sargasan
Authority
Gandhinagar Urban Development Authority
Covered area
1688.14 sq m
Open area
238.86 sq m
Land cost
₹3.28 Cr
Estimated cost
₹7.92 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/200924/009629
Covered parking
76 · 1165.53 sq m
Parking for sale
0

Escrow account

Bank
IDFC Bank
Branch
GANDHINAGAR BRANCH
IFSC
IDFB0042343
Account
XXXX-3615
Status
APPROVED

Inspection phases (Form-1)

Architect
ARPIT PRIYAVADAN MEENA SHAH
Firm
GREY LEAF
Site visit
2024-12-16
Form-1 PDF
Open file
  • Block A+B87.5%
Phase actual dates (1 block)
  • Block A+B: excavation → slab

Filing PDFs

Project team on record

  • UMANG PATEL · engineer
  • MR. ARPIT SHAH (GREY LEAF) · architect
How is the paperwork score calculated?50 / 100
  • Delivery standing

    12 / 40

  • Filing discipline

    21 / 25

  • Promoter track record

    10 / 20

  • Complaints and extensions

    7 / 15

  • Delivery 2024-03-31 elapsed 2 yr ago, progress 89.38% -> 12/40
  • QPR filings 11/13 -> 21/25
  • Promoter completed projects 1 -> 10/20
  • Red flags 1 complaint + 1 extension -> 7/15

Confidence Medium: declared completion date elapsed 2 years ago with work still declared incomplete; QPR filing rate 84.6% is below 90%; 1 complaint entry on the ledger; 1 extension request on the ledger.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA07592/EX1/300623

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.