Delivered

Sharnam-56

F.P.No.72/1+2, Survey No.108/1 & 108/2, T.P.S. No.241(Nana Chiloda), Moje : Chiloda(Naroda), Ta : Gandhinagar, Dist : Gandhinagar, Sharnam-56, 108/1/2, Opp Shreeji Avenue, Someshwar Mahadev Road,

Mixed Development61 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/10629

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/MAA07534/071020

Sharnam-56 — residential developmentGandhinagar · representative residential imagery

Paperwork score

Complete record

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings9 / 9
Recorded complaints0
ExtensionsNone recorded
Promoter projects1 completed

Project at a glance

Developer
Saanvi Developers
Project type
Mixed Development
Total units
61
Project cost
₹11.71 Cr
Carpet area
3,862.9 sq m
Price band
₹18L – ₹0L
Carpet area per unit
29.72-66.64 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Mixed Development — 61 units · carpet 3,862.87 sq m
  • Block A
  • Block B
  • Declared start 2019-10-17 · completion 2022-12-31
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.1106° N, 72.6647° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

61

Total units

50

Booked (82%)

11

Unsold (18%)

82% booked · 18% unsold

Tower A33 units

28 booked (85%) · 5 available (15%)

Tower B28 units

22 booked (79%) · 6 available (21%)

Flat-level inventory (61 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
A-101A66.64BOOKED
A-102A66.64BOOKED
A-103A66.64BOOKED
A-104A66.64BOOKED
A-201A66.64BOOKED
A-202A66.64BOOKED
A-203A66.64BOOKED
A-204A66.64BOOKED
A-301A66.64BOOKED
A-302A66.64BOOKED
A-303A66.64BOOKED
A-304A66.64BOOKED
A-401A66.64BOOKED
A-402A66.64BOOKED
A-403A66.64BOOKED
A-404A66.64BOOKED
A-501A66.64BOOKED
A-502A66.64BOOKED
A-503A66.64BOOKED
A-504A66.64BOOKED
A-601A66.64UNBOOKED
A-602A66.64BOOKED
A-603A66.64BOOKED
A-604A66.64BOOKED
A-701A66.64BOOKED
A-702A66.64UNBOOKED
A-703A66.64UNBOOKED
A-704A66.64BOOKED
Shop-1A31.43UNBOOKED
Shop-2A29.72BOOKED
Shop-3A32.75BOOKED
Shop-4A32.2UNBOOKED
Shop-5A34.05BOOKED
B-101B65.6BOOKED
B-102B65.6BOOKED
B-103B65.6UNBOOKED
B-104B65.6BOOKED
B-201B65.6BOOKED
B-202B65.6BOOKED
B-203B65.6UNBOOKED
B-204B65.6BOOKED
B-301B65.6BOOKED
B-302B65.6BOOKED
B-303B65.6BOOKED
B-304B65.6BOOKED
B-401B65.6BOOKED
B-402B65.6BOOKED
B-403B65.6BOOKED
B-404B65.6UNBOOKED
B-501B65.6BOOKED
B-502B65.6UNBOOKED
B-503B65.6UNBOOKED
B-504B65.6BOOKED
B-601B65.6BOOKED
B-602B65.6BOOKED
B-603B65.6BOOKED
B-604B65.6BOOKED
B-701B65.6UNBOOKED
B-702B65.6BOOKED
B-703B65.6BOOKED
B-704B65.6BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%202120222023March 2021 — 52.35% builtJune 2021 — 56.9% builtSeptember 2021 — 59.71% builtDecember 2021 — 69.21% builtMarch 2022 — 73.02% builtJune 2022 — 85.09% builtSeptember 2022 — 100% builtDecember 2022 — 100% builtJanuary 2023 — 100% built

9 quarterly returns · March 2021 (52.35%) to January 2023 (100%)

52.35%

Initial progress · March 2021

100%

Final progress · January 2023

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2020

    Registration

  2. 2021

    Annual Compliance

  3. 2023

    Annual Compliance

  4. 2026

    Snapshot reviewed

Full application ledger (5 rows)
  1. Registration — 2020-10-07 16:28:32.000000
  2. Annual Compliance — 2021-01-31 02:22:12
  3. Annual Compliance — 2023-11-17 21:15:36
  4. Annual Compliance — 2023-11-17 21:15:37
  5. Annual Compliance — 2023-11-17 21:15:37

Quarterly filing history

2021

Q-1 · Q-2 · Q-3 · Q-4

2022

Q-5 · Q-6 · Q-7 · Q-8 · Q-E

9 submitted · 0 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/MAA07534/071020 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Nana Chiloda
TP scheme
Nana chiloda
Authority
Ahmedabad Urban Development Authority
Covered area
1302.86 sq m
Open area
336.14 sq m
Land cost
₹0.85 Cr
Estimated cost
₹8.5 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/200919/009607
Covered parking
50 · 1215.41 sq m
Parking for sale
2

Escrow account

Bank
HDFC
Branch
CHANDKHEDA BRANCH
IFSC
HDFC0004894
Account
XXXX-1555
Deposited
₹0.77 Cr
Withdrawn
₹0.76 Cr
Closing
₹0.01 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
SAVAN P PANCHAL
Site visit
2022-11-30
Form-1 PDF
Open file
  • Block A100%
  • Block B100%
Phase actual dates (2 blocks)
  • Block B: excavation — → slab —
  • Block A: excavation — → slab —

Filing PDFs

Project team on record

  • VIREN DILIPBHAI PAREKH · engineer
  • SAVAN PRAVINKUMAR PANCHAL · architect
How is the paperwork score calculated?90 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    25 / 25

  • Promoter track record

    10 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2022-12-31 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 9/9 -> 25/25
  • Promoter completed projects 1 -> 10/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/MAA07534/071020

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.