Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Delivered

Pushkar Residency

SURVEY NO 475/1 FP 130 TP NO 409/B MOUJE ZUNDAL

ResidentialGroup Housing80 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/10644

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA07535/091020

Pushkar Residency — residential developmentGandhinagar · representative residential imagery

Paperwork score

Complete record

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings11 / 11
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Pushkar Developers
Project type
Residential / Group Housing
Total units
80
Project cost
₹23.52 Cr
Carpet area
5,237.8 sq m
Price band
₹25L – ₹0L
Carpet area per unit
59.92-70.71 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Residential/Group Housing — 80 units · carpet 5,237.83 sq m
  • Block BLOCK A
  • Block BLOCK B
  • Declared start 2020-07-28 · completion 2023-08-28
  • Professionals on record: 0 architect(s), 0 engineer(s) · land not itemised

Location

23.1357° N, 72.5725° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

80

Total units

80

Booked (100%)

0

Unsold (0%)

100% booked · 0% unsold

Tower BLOCK A40 units

40 booked (100%) · 0 available (0%)

Tower BLOCK B40 units

40 booked (100%) · 0 available (0%)

Flat-level inventory (80 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
101BLOCK A70.71BOOKED
102BLOCK A70.71BOOKED
103BLOCK A70.71BOOKED
104BLOCK A70.71BOOKED
201BLOCK A70.71BOOKED
202BLOCK A70.71BOOKED
203BLOCK A70.71BOOKED
204BLOCK A70.71BOOKED
301BLOCK A70.71BOOKED
302BLOCK A70.71BOOKED
303BLOCK A70.71BOOKED
304BLOCK A70.71BOOKED
401BLOCK A70.71BOOKED
402BLOCK A70.71BOOKED
403BLOCK A70.71BOOKED
404BLOCK A70.71BOOKED
501BLOCK A70.71BOOKED
502BLOCK A70.71BOOKED
503BLOCK A70.71BOOKED
504BLOCK A70.71BOOKED
601BLOCK A70.71BOOKED
602BLOCK A70.71BOOKED
603BLOCK A70.71BOOKED
604BLOCK A70.71BOOKED
701BLOCK A70.71BOOKED
702BLOCK A70.71BOOKED
703BLOCK A70.71BOOKED
704BLOCK A70.71BOOKED
801BLOCK A70.71BOOKED
802BLOCK A70.71BOOKED
803BLOCK A70.71BOOKED
804BLOCK A70.71BOOKED
901BLOCK A70.71BOOKED
902BLOCK A70.71BOOKED
903BLOCK A70.71BOOKED
904BLOCK A70.71BOOKED
1001BLOCK A70.71BOOKED
1002BLOCK A70.36BOOKED
1003BLOCK A70.36BOOKED
1004BLOCK A70.36BOOKED
101BLOCK B60.3BOOKED
102BLOCK B60.3BOOKED
103BLOCK B60.3BOOKED
104BLOCK B60.3BOOKED
201BLOCK B60.3BOOKED
202BLOCK B60.3BOOKED
203BLOCK B60.3BOOKED
204BLOCK B60.3BOOKED
301BLOCK B60.3BOOKED
302BLOCK B60.3BOOKED
303BLOCK B60.3BOOKED
304BLOCK B60.3BOOKED
401BLOCK B60.3BOOKED
402BLOCK B60.3BOOKED
403BLOCK B60.3BOOKED
404BLOCK B60.3BOOKED
501BLOCK B60.3BOOKED
502BLOCK B60.3BOOKED
503BLOCK B60.3BOOKED
504BLOCK B60.3BOOKED
601BLOCK B60.3BOOKED
602BLOCK B60.3BOOKED
603BLOCK B60.3BOOKED
604BLOCK B60.3BOOKED
701BLOCK B60.3BOOKED
702BLOCK B60.3BOOKED
703BLOCK B60.3BOOKED
704BLOCK B60.3BOOKED
801BLOCK B60.3BOOKED
802BLOCK B60.3BOOKED
803BLOCK B60.3BOOKED
804BLOCK B60.3BOOKED
901BLOCK B60.3BOOKED
902BLOCK B60.3BOOKED
903BLOCK B60.3BOOKED
904BLOCK B60.3BOOKED
1001BLOCK B59.92BOOKED
1002BLOCK B59.92BOOKED
1003BLOCK B59.92BOOKED
1004BLOCK B59.92BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%202120222023March 2021 — 25.5% builtJune 2021 — 34.27% builtSeptember 2021 — 40.38% builtDecember 2021 — 43.56% builtMarch 2022 — 51% builtJune 2022 — 63.02% builtSeptember 2022 — 63.02% builtDecember 2022 — 98.64% builtMarch 2023 — 98.64% builtJune 2023 — 100% builtSeptember 2023 — 100% built

11 quarterly returns · March 2021 (25.5%) to September 2023 (100%)

25.5%

Initial progress · March 2021

100%

Final progress · September 2023

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2020

    Registration

  2. 2021

    BCR

  3. 2023

    Annual Compliance

  4. 2026

    Snapshot reviewed

Full application ledger (5 rows)
  1. Registration — 2020-10-09 11:26:05.000000
  2. Annual Compliance — 2023-11-17 21:15:38
  3. Annual Compliance — 2023-11-17 21:15:38
  4. Annual Compliance — 2023-11-17 21:15:38
  5. BCR — 2021-07-31 14:43:20.000000

Quarterly filing history

2021

Q-1 · Q-2 · Q-3 · Q-4

2022

Q-5 · Q-6 · Q-7 · Q-8

2023

Q-9 · Q-10 · Q-E

11 submitted · 0 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA07535/091020 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Zundal
TP scheme
Zundal
Authority
Ahmedabad Urban Development Authority
Covered area
726.3 sq m
Open area
1458.7 sq m
Land cost
₹3.92 Cr
Estimated cost
₹19.6 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/AHMEDABAD TPO/200916/009580
Parking for sale
0

Escrow account

Bank
DCB bank Ltd
Branch
CG ROAD , AHMEDABAD
IFSC
DCBL0000036
Account
XXXX-0222
Deposited
₹0.65 Cr
Withdrawn
₹0.65 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
DHAVAL N MEWADA
Site visit
2023-08-28
Form-1 PDF
Open file
  • Block BLOCK A100%
  • Block BLOCK B100%
Phase actual dates (2 blocks)
  • Block BLOCK A: excavation — → slab —
  • Block BLOCK B: excavation — → slab —

Filing PDFs

How is the paperwork score calculated?80 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    25 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2023-08-28 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 11/11 -> 25/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA07535/091020

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.