Ongoing

Saral Skyline

Block No.461, TP No.3, FP No.32,

Mixed Development93 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/10649

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA07573/201020

Saral Skyline — residential developmentGandhinagar · representative residential imagery

Paperwork score

Some gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusOngoing
Quarterly filings16 / 16
Recorded complaints0
ExtensionsNone recorded
Promoter projects1 completed

Project at a glance

Developer
Shubh Ashish Developers
Project type
Mixed Development
Total units
93
Project cost
₹34.5 Cr
Carpet area
8,817.4 sq m
Price band
₹12L – ₹0L
Carpet area per unit
22.02-147.13 sq m
Status
Ongoing
Filing extras — blocks, inventory lines, dates
  • Mixed Development — 93 units · carpet 8,817.38 sq m
  • Block A
  • Declared start 2020-07-01 · completion 2024-12-31
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.1664° N, 72.6371° E

Filed plot outline · 6 corners
Open in Google Maps

Units & inventory

93

Total units

67

Booked (72%)

26

Unsold (28%)

72% booked · 28% unsold

Tower A93 units

67 booked (72%) · 26 available (28%)

Flat-level inventory (93 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
1A114.31UNBOOKED
2A83.52UNBOOKED
3A77.07UNBOOKED
4A35.4BOOKED
5A37.78BOOKED
6A28.94BOOKED
7A41.03UNBOOKED
8A45.05BOOKED
9A41.66BOOKED
10A45.25UNBOOKED
11A73.24BOOKED
101A147.13UNBOOKED
102A50.01UNBOOKED
103A51.93UNBOOKED
104A22.02UNBOOKED
105A46.93UNBOOKED
106A33.38BOOKED
107A36.05BOOKED
108A33.67BOOKED
109A36.81BOOKED
110A73UNBOOKED
201A115.52BOOKED
202A115.52BOOKED
203A106.12BOOKED
204A106.12BOOKED
205A105.85UNBOOKED
206A89.47BOOKED
301A115.52UNBOOKED
302A115.52BOOKED
303A106.12BOOKED
304A106.12BOOKED
305A105.85BOOKED
306A89.47BOOKED
401A115.52BOOKED
402A115.52BOOKED
403A106.12BOOKED
404A106.12BOOKED
405A105.85BOOKED
406A89.47BOOKED
501A115.52UNBOOKED
502A115.52BOOKED
503A106.12BOOKED
504A106.12BOOKED
505A105.85UNBOOKED
506A89.47BOOKED
601A115.52BOOKED
602A115.52BOOKED
603A106.12BOOKED
604A106.12BOOKED
605A105.85UNBOOKED
606A89.47BOOKED
701A115.52BOOKED
702A115.52BOOKED
703A106.12BOOKED
704A106.12BOOKED
705A105.85UNBOOKED
706A89.47BOOKED
801A115.52BOOKED
802A115.52BOOKED
803A106.12BOOKED
804A106.12BOOKED
805A105.85UNBOOKED
806A89.47BOOKED
901A115.52BOOKED
902A115.52BOOKED
903A106.12BOOKED
904A106.12BOOKED
905A105.85UNBOOKED
906A89.47UNBOOKED
1001A115.52BOOKED
1002A115.52BOOKED
1003A106.12BOOKED
1004A106.12UNBOOKED
1005A105.85UNBOOKED
1006A89.47BOOKED
1101A115.52BOOKED
1102A115.52BOOKED
1103A106.12BOOKED
1104A106.12BOOKED
1105A105.85UNBOOKED
1106A89.47BOOKED
1201A115.52BOOKED
1202A115.52BOOKED
1203A106.12BOOKED
1204A106.12BOOKED
1205A105.85UNBOOKED
1206A89.47BOOKED
1301A115.52BOOKED
1302A115.52BOOKED
1303A106.12BOOKED
1304A106.12UNBOOKED
1305A105.85UNBOOKED
1306A89.47BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 87.25%
0%25%50%75%100%20212022202320242025March 2021 — 15.94% builtJune 2021 — 25.5% builtSeptember 2021 — 25.5% builtDecember 2021 — 31.5% builtMarch 2022 — 36.12% builtJune 2022 — 40.91% builtSeptember 2022 — 43.56% builtDecember 2022 — 52.86% builtMarch 2023 — 61.36% builtJune 2023 — 68.18% builtSeptember 2023 — 71.26% builtJanuary 2024 — 75.03% builtApril 2024 — 87.25% builtJuly 2024 — 87.25% builtOctober 2024 — 87.25% builtJanuary 2025 — 87.25% built

16 quarterly returns · March 2021 (15.94%) to January 2025 (87.25%)

15.94%

Initial progress · March 2021

87.25%

Final progress · January 2025

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2020

    Registration

  2. 2021

    Annual Compliance · BCR

  3. 2023

    Annual Compliance

  4. 2024

    Annual Compliance

  5. Undated

    Annual Compliance

  6. 2026

    Snapshot reviewed

Full application ledger (7 rows)
  1. Registration — 2020-10-20 15:15:26.000000
  2. Annual Compliance — 2021-12-21 15:20:10
  3. Annual Compliance — 2023-11-17 21:15:39
  4. Annual Compliance — 2023-11-17 21:15:39
  5. Annual Compliance — 2024-09-30 15:29:47
  6. Annual Compliance — undated
  7. BCR — 2021-01-19 18:01:09.000000

Quarterly filing history

2021

Q-1 · Q-2 · Q-3 · Q-4

2022

Q-5 · Q-6 · Q-7

2023

Q-8 · Q-9 · Q-10 · Q-11

2024

Q-12 · Q-13 · Q-14 · Q-15 · Q-E

16 submitted · 0 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA07573/201020 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Kudasan
TP scheme
KOBA-KUDASAN
Authority
Gandhinagar Urban Development Authority
Covered area
1022.47 sq m
Open area
1609.53 sq m
Land cost
₹6.79 Cr
Estimated cost
₹27.71 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/200916/009583
Covered parking
2 · 2911.4 sq m
Parking for sale
1

Escrow account

Bank
Axis Bank
Branch
KUDASAN
IFSC
UTIB0002646
Account
XXXX-4360
Deposited
₹1.25 Cr
Withdrawn
₹1.65 Cr
Closing
₹0.05 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
VISHWJITSINH DILIPSINH HADA
Firm
THE GRID ARCHITECTS
Site visit
2024-12-26
Form-1 PDF
Open file
  • Block A85%
Phase actual dates (1 block)
  • Block A: excavation → slab

Filing PDFs

Project team on record

  • Amee Associates · engineer
  • Vishwjitsinh D. Hada · architect
How is the paperwork score calculated?74 / 100
  • Delivery standing

    24 / 40

  • Filing discipline

    25 / 25

  • Promoter track record

    10 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2024-12-31 elapsed 1 yr ago, progress 87.25% -> 24/40
  • QPR filings 16/16 -> 25/25
  • Promoter completed projects 1 -> 10/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: declared completion date elapsed 1 year ago with work still declared incomplete.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA07573/201020

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.