Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Delivered

Tirupati Tirth

BLOCK NO. 363 FP 349/1 TP-410

Mixed Development67 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/10702

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/MAA07601/261020

Tirupati Tirth — residential developmentGandhinagar · representative residential imagery

Paperwork score

Complete record

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings15 / 16
Recorded complaints0
ExtensionsNone recorded
Promoter projects1 completed

Project at a glance

Developer
Shreeji Procon
Project type
Mixed Development
Total units
67
Project cost
₹17.32 Cr
Carpet area
4,379.8 sq m
Price band
₹6L – ₹0L
Carpet area per unit
9.63-73.19 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Mixed Development — 67 units · carpet 4,379.8 sq m
  • Block 1
  • Declared start 2020-07-22 · completion 2024-12-31
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.1182° N, 72.6238° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

67

Total units

52

Booked (78%)

15

Unsold (22%)

78% booked · 22% unsold

Tower 167 units

52 booked (78%) · 15 available (22%)

Flat-level inventory (67 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
SHOP-1125.44UNBOOKED
SHOP-2160.06BOOKED
SHOP-3129.28UNBOOKED
SHOP-4121.85BOOKED
SHOP-5126.66BOOKED
SHOP-6126.66BOOKED
SHOP-719.63BOOKED
SHOP-8120.5BOOKED
SHOP-9121.71BOOKED
SHOP-10134.36BOOKED
OFFICE-101160.07UNBOOKED
OFFICE-102142.82UNBOOKED
OFFICE-103148.5UNBOOKED
FLAT-101173.19UNBOOKED
FLAT-102173.19BOOKED
FLAT NO -201173.19BOOKED
FLAT NO -202173.19BOOKED
FLAT NO -203173.19BOOKED
FLAT NO -204173.19BOOKED
FLAT NO -301173.19BOOKED
FLAT NO -302173.19BOOKED
FLAT NO -303173.19BOOKED
FLAT NO -304173.19BOOKED
FLAT NO -401173.19BOOKED
FLAT NO -402173.19BOOKED
FLAT NO -403173.19BOOKED
FLAT NO -404173.19BOOKED
FLAT NO -501173.19BOOKED
FLAT NO -502173.19BOOKED
FLAT NO -503173.19BOOKED
FLAT NO -504173.19BOOKED
FLAT NO -601173.19BOOKED
FLAT NO -602173.19BOOKED
FLAT NO -603173.19BOOKED
FLAT NO -604173.19BOOKED
FLAT NO -701173.19UNBOOKED
FLAT NO -702173.19UNBOOKED
FLAT NO -703173.19BOOKED
FLAT NO -704173.19BOOKED
FLAT NO -801173.19UNBOOKED
FLAT NO -802173.19UNBOOKED
FLAT NO -803173.19BOOKED
FLAT NO -804173.19BOOKED
FLAT NO -901173.19BOOKED
FLAT NO -902173.19BOOKED
FLAT NO -903173.19BOOKED
FLAT NO -904173.19BOOKED
FLAT NO -1001173.19BOOKED
FLAT NO -1002173.19BOOKED
FLAT NO -1003173.19UNBOOKED
FLAT NO -1004173.19BOOKED
FLAT NO -1101173.19UNBOOKED
FLAT NO -1102173.19BOOKED
FLAT NO -1103173.19BOOKED
FLAT NO -1104173.19UNBOOKED
FLAT NO -1201173.19UNBOOKED
FLAT NO -1202173.19BOOKED
FLAT NO -1203173.19BOOKED
FLAT NO -1204173.19BOOKED
FLAT NO -1301173.19BOOKED
FLAT NO -1302173.19BOOKED
FLAT NO -1303173.19BOOKED
FLAT NO -1304173.19UNBOOKED
FLAT NO -1401173.19BOOKED
FLAT NO -1402173.19BOOKED
FLAT NO -1403173.19BOOKED
FLAT NO -1404173.19BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%20212022202320242025March 2021 — 23.36% builtJune 2021 — 27.34% builtSeptember 2021 — 27.72% builtDecember 2021 — 34.48% builtMarch 2022 — 42.7% builtJune 2022 — 52.63% builtSeptember 2022 — 57.65% builtDecember 2022 — 63.58% builtMarch 2023 — 71.77% builtJune 2023 — 76.37% builtSeptember 2023 — 85.43% builtDecember 2023 — 96.59% builtApril 2024 — 99.23% builtJuly 2024 — 100% builtJanuary 2025 — 100% built

15 quarterly returns · March 2021 (23.36%) to January 2025 (100%)

23.36%

Initial progress · March 2021

100%

Final progress · January 2025

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2020

    Registration

  2. 2021

    Annual Compliance

  3. 2023

    Annual Compliance

  4. 2024

    Annual Compliance

  5. 2025

    Annual Compliance

  6. 2026

    Snapshot reviewed

Full application ledger (6 rows)
  1. Registration — 2020-10-26 10:47:58.000000
  2. Annual Compliance — 2021-12-30 18:10:41
  3. Annual Compliance — 2023-11-17 21:15:45
  4. Annual Compliance — 2023-11-17 21:15:45
  5. Annual Compliance — 2024-10-22 14:41:36
  6. Annual Compliance — 2025-10-27 13:42:52

Quarterly filing history

2021

Q-1 · Q-2 · Q-3 · Q-4

2022

Q-5 · Q-6 · Q-7 · Q-8

2023

Q-9 · Q-10 · Q-11 · Q-12

2024

Q-13 · Q-14 · Q-E

—

Q-15

15 submitted · 1 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/MAA07601/261020 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Sughad
TP scheme
Amiyapur-Zundal-Sughad
Authority
Ahmedabad Urban Development Authority
Covered area
484 sq m
Open area
1337 sq m
Land cost
₹2.46 Cr
Estimated cost
₹14.86 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/AHMEDABAD TPO/201001/009647
Covered parking
121 · 1518.06 sq m
Parking for sale
25

Escrow account

Bank
HDFC
Branch
RAYSAN
IFSC
HDFC0005065
Account
XXXX-4583
Deposited
₹1.22 Cr
Withdrawn
₹1.22 Cr
Closing
₹0.82 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
URVASHI LALITKUMAR TULI
Firm
SPACECITIZ DESIGN STUDIO
Site visit
2024-08-08
Form-1 PDF
Open file
  • Block 1100%
Phase actual dates (1 block)
  • Block 1: excavation → slab

Filing PDFs

Project team on record

  • CHINTAN HIMANSHUBHAI MEHTA · engineer
  • URVASHI TULI · architect
How is the paperwork score calculated?88 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    23 / 25

  • Promoter track record

    10 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2024-12-31 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 15/16 -> 23/25
  • Promoter completed projects 1 -> 10/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/MAA07601/261020

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.