Delivered

Manorath Lifestyle

Manorath Lifestyle

Mixed Development77 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/10786

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA07665/101120

Manorath Lifestyle — residential developmentGandhinagar · representative residential imagery

Paperwork score

Some gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings11 / 17
Recorded complaints1
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Manorath Infra
Project type
Mixed Development
Total units
77
Project cost
₹21.51 Cr
Carpet area
5,795 sq m
Price band
₹5L – ₹0L
Carpet area per unit
12.12-95.1 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Mixed Development — 77 units · carpet 5,795.02 sq m
  • Block BLOCK A
  • Block BLOCK B
  • Declared start 2020-09-19 · completion 2025-03-31
  • Professionals on record: 0 architect(s), 0 engineer(s) · land not itemised

Location

23.1727° N, 72.6419° E

Filed plot outline · 10 corners
Open in Google Maps

Units & inventory

77

Total units

77

Booked (100%)

0

Unsold (0%)

100% booked · 0% unsold

Tower BLOCK A41 units

41 booked (100%) · 0 available (0%)

Tower BLOCK B36 units

36 booked (100%) · 0 available (0%)

Flat-level inventory (77 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
1BLOCK A23.08BOOKED
2BLOCK A23.65BOOKED
3BLOCK A29.54BOOKED
4BLOCK A31.96BOOKED
5BLOCK A12.12BOOKED
6BLOCK A31.96BOOKED
7BLOCK A29.54BOOKED
8BLOCK A23.65BOOKED
9BLOCK A23.08BOOKED
A-101BLOCK A95.1BOOKED
A-201BLOCK A95.1BOOKED
A-301BLOCK A95.1BOOKED
A-401BLOCK A95.1BOOKED
A-501BLOCK A95.1BOOKED
A-601BLOCK A95.1BOOKED
A-701BLOCK A95.1BOOKED
A-801BLOCK A95.1BOOKED
A-102BLOCK A95.1BOOKED
A-202BLOCK A95.1BOOKED
A-302BLOCK A95.1BOOKED
A-402BLOCK A95.1BOOKED
A-502BLOCK A95.1BOOKED
A-602BLOCK A95.1BOOKED
A-702BLOCK A95.1BOOKED
A-802BLOCK A95.1BOOKED
A-103BLOCK A95.1BOOKED
A-203BLOCK A95.1BOOKED
A-303BLOCK A95.1BOOKED
A-403BLOCK A95.1BOOKED
A-503BLOCK A95.1BOOKED
A-603BLOCK A95.1BOOKED
A-703BLOCK A95.1BOOKED
A-803BLOCK A95.1BOOKED
A-104BLOCK A95.1BOOKED
A-204BLOCK A95.1BOOKED
A-304BLOCK A95.1BOOKED
A-404BLOCK A95.1BOOKED
A-504BLOCK A95.1BOOKED
A-604BLOCK A95.1BOOKED
A-704BLOCK A95.1BOOKED
A-804BLOCK A95.1BOOKED
B-101BLOCK B70.09BOOKED
B-201BLOCK B70.09BOOKED
B-301BLOCK B70.09BOOKED
B-401BLOCK B70.09BOOKED
B-501BLOCK B70.09BOOKED
B-601BLOCK B70.09BOOKED
B-701BLOCK B70.09BOOKED
B-801BLOCK B70.09BOOKED
B-901BLOCK B70.09BOOKED
B-102BLOCK B70.09BOOKED
B-202BLOCK B70.09BOOKED
B-302BLOCK B70.09BOOKED
B-402BLOCK B70.09BOOKED
B-502BLOCK B70.09BOOKED
B-602BLOCK B70.09BOOKED
B-702BLOCK B70.09BOOKED
B-802BLOCK B70.09BOOKED
B-902BLOCK B70.09BOOKED
B-103BLOCK B70.09BOOKED
B-203BLOCK B70.09BOOKED
B-303BLOCK B70.09BOOKED
B-403BLOCK B70.09BOOKED
B-503BLOCK B70.09BOOKED
B-603BLOCK B70.09BOOKED
B-703BLOCK B70.09BOOKED
B-803BLOCK B70.09BOOKED
B-903BLOCK B70.09BOOKED
B-104BLOCK B70.09BOOKED
B-204BLOCK B70.09BOOKED
B-304BLOCK B70.09BOOKED
B-404BLOCK B70.09BOOKED
B-504BLOCK B70.09BOOKED
B-604BLOCK B70.09BOOKED
B-704BLOCK B70.09BOOKED
B-804BLOCK B70.09BOOKED
B-904BLOCK B70.09BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%2021202220232025April 2021 — 19.12% builtJuly 2021 — 22.95% builtOctober 2021 — 26.4% builtJanuary 2022 — 39.84% builtApril 2022 — 41.38% builtJuly 2022 — 47.13% builtOctober 2022 — 58.37% builtJanuary 2023 — 66.77% builtApril 2023 — 89.14% builtJuly 2023 — 100% builtApril 2025 — 100% built

11 quarterly returns · April 2021 (19.12%) to April 2025 (100%)

19.12%

Initial progress · April 2021

100%

Final progress · April 2025

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2020

    Registration

  2. 2021

    Annual Compliance

  3. 2023

    Annual Compliance

  4. 2024

    Complaint

  5. Undated

    Annual Compliance

  6. 2026

    Snapshot reviewed

Full application ledger (7 rows)
  1. Registration — 2020-11-10 14:41:30.000000
  2. Complaint — 2024-06-12 12:51:09 · CMP1301202400341 (CLOSED)
  3. Annual Compliance — 2021-12-31 13:33:29
  4. Annual Compliance — 2023-11-17 21:15:57
  5. Annual Compliance — 2023-11-17 21:15:57
  6. Annual Compliance — undated
  7. Annual Compliance — undated

Quarterly filing history

2021

Q-1 · Q-2 · Q-3 · Q-4

2022

Q-5 · Q-6 · Q-7 · Q-8

2023

Q-9 · Q-10 · Q-E

—

Q-11 · Q-12 · Q-13 · Q-14 · Q-15 · Q-16

11 submitted · 6 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA07665/101120 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Randesan
TP scheme
Randesan- Kudasan
Final / sub plot
-
Authority
Gandhinagar Urban Development Authority
Covered area
881.73 sq m
Open area
2048.27 sq m
Land cost
₹4.5 Cr
Estimated cost
₹16.51 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/201015/009722
Parking for sale
0

Escrow account

Bank
HDFC
Branch
CHANDKHEDA
IFSC
HDFC0004894
Account
XXXX-3158
Deposited
₹1.72 Cr
Withdrawn
₹2.52 Cr
Closing
₹0.39 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
NIYATI MISTRY
Site visit
2023-01-30
Form-1 PDF
Open file
  • Block BLOCK A100%
  • Block BLOCK B100%
Phase actual dates (2 blocks)
  • Block BLOCK A: excavation — → slab —
  • Block BLOCK B: excavation — → slab —

Filing PDFs

How is the paperwork score calculated?67 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    16 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    11 / 15

  • Delivery 2025-03-31 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 11/17 -> 16/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 1 complaint + 0 extensions -> 11/15

Confidence Medium: QPR filing rate 64.7% is below 90%; no completed project on the promoter record; 1 complaint entry on the ledger.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA07665/101120

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.