Delivered

Shikshapatri Sky Line

SHIKSHAPATRI SKY LINE, B/H SHIKSHAPATRI SWASTIK,

Mixed Development68 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/11094

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA08036/100221

Shikshapatri Sky Line — residential developmentGandhinagar · representative residential imagery

Paperwork score

Some gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings17 / 19
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Shikshapatri Infracon
Project type
Mixed Development
Total units
68
Project cost
₹25 Cr
Carpet area
6,041.8 sq m
Price band
₹9L – ₹0L
Carpet area per unit
14.34-117.24 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Mixed Development — 68 units · carpet 6,041.81 sq m
  • Block UNIT-01
  • Declared start 2020-11-04 · completion 2025-12-31
  • Professionals on record: 0 architect(s), 0 engineer(s) · land not itemised

Location

23.1906° N, 72.6041° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

68

Total units

63

Booked (93%)

5

Unsold (7%)

93% booked · 7% unsold

Tower UNIT-0168 units

63 booked (93%) · 5 available (7%)

Flat-level inventory (68 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
SHOP-01UNIT-0152.33BOOKED
SHOP-02UNIT-0152.33BOOKED
SHOP-03UNIT-0154.01BOOKED
SHOP-04UNIT-0144.6BOOKED
SHOP-05UNIT-0152.75BOOKED
SHOP-06UNIT-0114.34BOOKED
SHOP-07UNIT-0114.34BOOKED
SHOP-08UNIT-0152.75BOOKED
SHOP-09UNIT-0144.6BOOKED
SHOP-10UNIT-0154.7BOOKED
SHOP-11UNIT-0141.28BOOKED
SHOP-12UNIT-0141.28BOOKED
SHOP-13UNIT-0141.28BOOKED
SHOP-14UNIT-0141.28BOOKED
SHOP-15UNIT-0141.28UNBOOKED
SHOP-16UNIT-0141.28UNBOOKED
SHOP-17UNIT-0149.38UNBOOKED
SHOP-18UNIT-0145.52UNBOOKED
A-101UNIT-01104.75BOOKED
A-102UNIT-01104.75BOOKED
A-201UNIT-01104.75BOOKED
A-202UNIT-01104.75BOOKED
A-301UNIT-01104.75BOOKED
A-302UNIT-01104.75BOOKED
A-401UNIT-01104.75BOOKED
A-402UNIT-01104.75BOOKED
A-501UNIT-01104.75BOOKED
A-502UNIT-01104.75BOOKED
A-601UNIT-01104.75BOOKED
A-602UNIT-01104.75BOOKED
A-701UNIT-01104.75BOOKED
A-702UNIT-01104.75BOOKED
A-801UNIT-01104.75BOOKED
A-802UNIT-01104.75BOOKED
A-901UNIT-01104.75BOOKED
A-902UNIT-01104.75BOOKED
A-1001UNIT-01104.75BOOKED
A-1002UNIT-01104.75BOOKED
A-1101UNIT-01104.75BOOKED
A-1102UNIT-01104.75BOOKED
A-1201UNIT-01104.75UNBOOKED
A-1202UNIT-01104.75BOOKED
A-1302UNIT-01117.24BOOKED
B-101UNIT-01104.75BOOKED
B-102UNIT-01104.75BOOKED
B-201UNIT-01104.75BOOKED
B-202UNIT-01104.75BOOKED
B-301UNIT-01104.75BOOKED
B-302UNIT-01104.75BOOKED
B-401UNIT-01104.75BOOKED
B-402UNIT-01104.75BOOKED
B-501UNIT-01104.75BOOKED
B-502UNIT-01104.75BOOKED
B-601UNIT-01104.75BOOKED
B-602UNIT-01104.75BOOKED
B-701UNIT-01104.75BOOKED
B-702UNIT-01104.75BOOKED
B-801UNIT-01104.75BOOKED
B-802UNIT-01104.75BOOKED
B-901UNIT-01104.75BOOKED
B-902UNIT-01104.75BOOKED
B-1001UNIT-01104.75BOOKED
B-1002UNIT-01104.75BOOKED
B-1101UNIT-01104.75BOOKED
B-1102UNIT-01104.75BOOKED
B-1201UNIT-01104.75BOOKED
B-1202UNIT-01104.75BOOKED
B-1302UNIT-01117.24BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%20212022202320242026July 2021 — 38.25% builtOctober 2021 — 41.97% builtJanuary 2022 — 50.47% builtApril 2022 — 57.64% builtJuly 2022 — 61.89% builtOctober 2022 — 75.97% builtJanuary 2023 — 81.36% builtApril 2023 — 100% builtJuly 2023 — 100% builtOctober 2023 — 100% builtJanuary 2024 — 87.25% builtApril 2024 — 87.25% builtJuly 2024 — 87.25% builtOctober 2024 — 87.25% builtJanuary 2026 — 100% built

15 quarterly returns · July 2021 (38.25%) to January 2026 (100%)

38.25%

Initial progress · July 2021

100%

Final progress · January 2026

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2021

    Registration · Annual Compliance

  2. 2023

    Annual Compliance

  3. 2024

    Annual Compliance

  4. 2025

    Annual Compliance

  5. Undated

    Annual Compliance

  6. 2026

    Snapshot reviewed

Full application ledger (7 rows)
  1. Registration — 2021-02-10 16:50:32.000000
  2. Annual Compliance — 2021-12-27 18:42:38
  3. Annual Compliance — 2023-11-17 21:16:39
  4. Annual Compliance — 2023-11-17 21:16:39
  5. Annual Compliance — 2024-10-29 15:47:18
  6. Annual Compliance — 2025-12-10 20:09:47
  7. Annual Compliance — undated

Quarterly filing history

2021

Q-1 · Q-2 · Q-3

2022

Q-4 · Q-5 · Q-6

2023

Q-7 · Q-8 · Q-9 · Q-10

2024

Q-11 · Q-12 · Q-13 · Q-14

2025

Q-15 · Q-16 · Q-E

—

Q-17 · Q-18

17 submitted · 2 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA08036/100221 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Authority
Others
Covered area
1446.04 sq m
Open area
1549.96 sq m
Land cost
₹4.42 Cr
Estimated cost
₹20.58 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/201221/010023
Covered parking
48 · 2039 sq m
Parking for sale
20

Escrow account

Bank
Axis Bank
Branch
SARGASAN CROSS ROAD
IFSC
UTIB0004377
Account
XXXX-9510
Deposited
₹0.33 Cr
Withdrawn
₹0.33 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
ARPIT PRIYAVADAN MEENA SHAH
Firm
ARPIT PRIYAVADAN MEENA SHAH
Site visit
2025-04-10
Form-1 PDF
Open file
  • Block UNIT-01100%
Phase actual dates (1 block)
  • Block UNIT-01: excavation → slab

Filing PDFs

How is the paperwork score calculated?77 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    22 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2025-12-31 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 17/19 -> 22/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: QPR filing rate 89.5% is below 90%; no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA08036/100221

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.