Ongoing

Radhe Homes

SURVEY NO 1079, 1080/1, 1080/2 BEHIND DHANVIR HANUMAN TEMPLE

ResidentialGroup Housing81 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/11141

Filing PR/GJ/GANDHINAGAR/MANSA/Others/RAA08166/EX1/220724/301224

Radhe Homes — residential developmentGandhinagar · representative residential imagery

Paperwork score

Material gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusOngoing
Quarterly filings12 / 16
Recorded complaints3
Extensions1
Promoter projectsNone completed on record

Project at a glance

Developer
Radhe Developers
Project type
Residential / Group Housing
Total units
81
Project cost
₹8.56 Cr
Carpet area
5,267.3 sq m
Price band
₹4L – ₹0L
Carpet area per unit
54.34-69.02 sq m
Status
Ongoing
Filing extras — blocks, inventory lines, dates
  • Residential/Group Housing — 81 units · carpet 5,267.32 sq m
  • Block A
  • Block B
  • Block C
  • Block D
  • Block E
  • Block F
  • Block G
  • Block H
  • Block I
  • Block J
  • Declared start 2020-07-24 · completion 2024-12-30
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.4284° N, 72.6468° E

Filed plot outline · 4 corners
Open in Google Maps

Units & inventory

81

Total units

76

Booked (94%)

5

Unsold (6%)

94% booked · 6% unsold

Tower A10 units

8 booked (80%) · 2 available (20%)

Tower B10 units

10 booked (100%) · 0 available (0%)

Tower C12 units

11 booked (92%) · 1 available (8%)

Tower D12 units

12 booked (100%) · 0 available (0%)

Tower E15 units

14 booked (93%) · 1 available (7%)

Tower F15 units

14 booked (93%) · 1 available (7%)

Tower G3 units

3 booked (100%) · 0 available (0%)

Tower H2 units

2 booked (100%) · 0 available (0%)

Tower I1 units

1 booked (100%) · 0 available (0%)

Tower J1 units

1 booked (100%) · 0 available (0%)

Flat-level inventory (81 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
1A54.35BOOKED
3A54.35BOOKED
50A54.35BOOKED
52A54.35UNBOOKED
54A54.35BOOKED
56A54.35BOOKED
58A54.35UNBOOKED
60A54.35BOOKED
62A54.35BOOKED
64A54.35BOOKED
2B54.35BOOKED
4B54.35BOOKED
49B54.35BOOKED
51B54.35BOOKED
53B54.35BOOKED
55B54.35BOOKED
57B54.35BOOKED
59B54.35BOOKED
61B54.35BOOKED
63B54.35BOOKED
5C69.01BOOKED
7C69.01UNBOOKED
9C69.01BOOKED
11C69.01BOOKED
67C69.01BOOKED
69C69.01BOOKED
71C69.01BOOKED
73C69.01BOOKED
75C69.01BOOKED
77C69.01BOOKED
79C69.01BOOKED
81C69.01BOOKED
6D69.01BOOKED
8D69.01BOOKED
10D69.01BOOKED
12D69.01BOOKED
66D69.01BOOKED
68D69.01BOOKED
70D69.01BOOKED
72D69.01BOOKED
74D69.01BOOKED
76D69.01BOOKED
78D69.01BOOKED
80D69.01BOOKED
12AE69.01BOOKED
15E69.01UNBOOKED
17E69.01BOOKED
21E69.01BOOKED
23E69.01BOOKED
25E69.01BOOKED
27E69.01BOOKED
29E69.01BOOKED
31E69.01BOOKED
35E69.01BOOKED
37E69.01BOOKED
39E69.01BOOKED
41E69.01BOOKED
43E69.01BOOKED
45E69.01BOOKED
14F69.01BOOKED
16F69.01BOOKED
18F69.01BOOKED
22F69.01BOOKED
24F69.01BOOKED
26F69.01BOOKED
28F69.01BOOKED
30F69.01BOOKED
32F69.01BOOKED
36F69.01BOOKED
38F69.01UNBOOKED
40F69.01BOOKED
42F69.01BOOKED
44F69.01BOOKED
46F69.01BOOKED
19G69.02BOOKED
33G69.02BOOKED
47G69.02BOOKED
20H69.02BOOKED
34H69.02BOOKED
48I54.34BOOKED
65J54.34BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 77.08%
0%25%50%75%100%20212022202320242025August 2021 — 12.37% builtNovember 2021 — 19.06% builtFebruary 2022 — 21.92% builtMay 2022 — 31.92% builtAugust 2022 — 35.69% builtNovember 2022 — 40.1% builtFebruary 2023 — 52.36% builtMay 2023 — 57.66% builtAugust 2023 — 63.98% builtNovember 2023 — 74.42% builtOctober 2024 — 77.08% builtJanuary 2025 — 77.08% built

12 quarterly returns · August 2021 (12.37%) to January 2025 (77.08%)

12.37%

Initial progress · August 2021

77.08%

Final progress · January 2025

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2021

    Registration

  2. 2023

    Annual Compliance

  3. 2024

    Extension · Complaint · Annual Compliance

  4. 2025

    Complaint · Challan · Annual Compliance

  5. 2026

    Snapshot reviewed

Full application ledger (11 rows)
  1. Registration — 2021-03-09 12:27:24.000000
  2. Extension — 2024-07-22 13:29:36
  3. Complaint — 2024-08-30 18:04:58 · CMP0106202400836 (CLOSED)
  4. Complaint — 2025-07-05 13:49:42 · CMP1309202401444 (CLOSED)
  5. Complaint — 2025-08-04 15:12:34 · CMP0407202500848 (CLOSED)
  6. Challan — 2025-08-28 14:45:23 · CMP0407202500848 (status not published)
  7. Annual Compliance — 2023-11-17 21:16:47
  8. Annual Compliance — 2023-11-17 21:16:47
  9. Annual Compliance — 2023-11-17 21:16:47
  10. Annual Compliance — 2024-10-25 18:13:04
  11. Annual Compliance — 2025-12-05 18:33:44

Quarterly filing history

2021

Q-1 · Q-2

2022

Q-3 · Q-4 · Q-5 · Q-6

2023

Q-7 · Q-8 · Q-9 · Q-10

—

X-1 · X-2 · X-3 · BWA-1

2024

X-4

2025

Q-E

12 submitted · 4 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/MANSA/Others/RAA08166/EX1/220724/301224 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Authority
Others
Covered area
3713.23 sq m
Open area
9236.77 sq m
Land cost
₹3.66 Cr
Estimated cost
₹4.9 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/MANSA/GANDHINAGAR TPO/210125/010182
Parking for sale
0

Escrow account

Bank
Mehsana Urban Co-Operative Bank Ltd.
Branch
MANSA
IFSC
MSNU0000011
Account
XXXX-1050
Deposited
₹0.77 Cr
Withdrawn
₹0.77 Cr
Closing
₹0 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
MAULIKKUMAR GOVINDSINH CHAVDA
Firm
MGC ARCHITECTS AND ASSOCIATES
Site visit
2025-08-28
Form-1 PDF
Open file
  • Block A75%
  • Block B75%
  • Block C75%
  • Block D75%
  • Block E75%
  • Block F75%
  • Block G75%
  • Block H75%
  • Block I75%
  • Block J75%
Phase actual dates (10 blocks)
  • Block B: excavation → slab
  • Block C: excavation → slab
  • Block D: excavation → slab
  • Block E: excavation → slab
  • Block F: excavation → slab
  • Block G: excavation → slab
  • Block H: excavation → slab
  • Block I: excavation → slab
  • Block J: excavation → slab
  • Block A: excavation → slab

Filing PDFs

Project team on record

  • AMRUTBHAI HARGOVANDAS PATEL · engineer
  • MAULIKBHAI G CHAVADA · architect
How is the paperwork score calculated?47 / 100
  • Delivery standing

    24 / 40

  • Filing discipline

    19 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    4 / 15

  • Delivery 2024-12-30 elapsed 1 yr ago, progress 77.08% -> 24/40
  • QPR filings 12/16 -> 19/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 3 complaints + 1 extension -> 4/15

Confidence Medium: declared completion date elapsed 1 year ago with work still declared incomplete; QPR filing rate 75.0% is below 90%; no completed project on the promoter record; 3 complaint entries on the ledger; 1 extension request on the ledger.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/MANSA/Others/RAA08166/EX1/220724/301224

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.