Skip to content
Compare
Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Delivered

Shubh City Heights

SHUBH CITY HEIGHTS, OPP. HARIDEV AATREYA,

Mixed Development88 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/11201

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA07919/160121

Shubh City Heights — residential developmentGandhinagar · representative residential imagery

Paperwork score

Some gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings10 / 11
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Shubh Infra Space
Project type
Mixed Development
Total units
88
Project cost
₹15.67 Cr
Carpet area
4,577.9 sq m
Price band
₹18L – ₹0L
Carpet area per unit
22.22-58.37 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Mixed Development — 88 units · carpet 4,577.89 sq m
  • Block A+B
  • Declared start 2020-11-13 · completion 2023-12-31
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.1930° N, 72.6039° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

88

Total units

58

Booked (66%)

30

Unsold (34%)

66% booked · 34% unsold

Tower A+B88 units

58 booked (66%) · 30 available (34%)

Flat-level inventory (88 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
A-101A+B58.37BOOKED
A-102A+B58.37BOOKED
A-103A+B58.37BOOKED
A-104A+B58.37BOOKED
A-201A+B58.37UNBOOKED
A-202A+B58.37UNBOOKED
A-203A+B58.37BOOKED
A-204A+B58.37BOOKED
A-301A+B58.37UNBOOKED
A-302A+B58.37UNBOOKED
A-303A+B58.37BOOKED
A-304A+B58.37BOOKED
A-401A+B58.37BOOKED
A-402A+B58.37BOOKED
A-403A+B58.37BOOKED
A-404A+B58.37BOOKED
A-501A+B58.37UNBOOKED
A-502A+B58.37UNBOOKED
A-503A+B58.37BOOKED
A-504A+B58.37BOOKED
A-601A+B58.37BOOKED
A-602A+B58.37UNBOOKED
A-603A+B58.37BOOKED
A-604A+B58.37BOOKED
A-701A+B58.37UNBOOKED
A-702A+B58.37UNBOOKED
A-703A+B58.37BOOKED
A-704A+B58.37BOOKED
A-801A+B58.37UNBOOKED
A-802A+B58.37UNBOOKED
A-803A+B58.37BOOKED
A-804A+B58.37BOOKED
A-901A+B58.37UNBOOKED
A-902A+B58.37BOOKED
A-903A+B58.37UNBOOKED
A-904A+B58.37UNBOOKED
B-101A+B58.37BOOKED
B-102A+B58.37BOOKED
B-103A+B58.37BOOKED
B-104A+B58.37BOOKED
B-201A+B58.37BOOKED
B-202A+B58.37BOOKED
B-203A+B58.37BOOKED
B-204A+B58.37BOOKED
B-301A+B58.37BOOKED
B-302A+B58.37UNBOOKED
B-303A+B58.37BOOKED
B-304A+B58.37BOOKED
B-401A+B58.37UNBOOKED
B-402A+B58.37UNBOOKED
B-403A+B58.37BOOKED
B-404A+B58.37BOOKED
B-501A+B58.37BOOKED
B-502A+B58.37UNBOOKED
B-503A+B58.37BOOKED
B-504A+B58.37BOOKED
B-601A+B58.37BOOKED
B-602A+B58.37BOOKED
B-603A+B58.37BOOKED
B-604A+B58.37BOOKED
B-701A+B58.37BOOKED
B-702A+B58.37UNBOOKED
B-703A+B58.37BOOKED
B-704A+B58.37BOOKED
B-801A+B58.37BOOKED
B-802A+B58.37BOOKED
B-803A+B58.37BOOKED
B-804A+B58.37BOOKED
B-901A+B58.37BOOKED
B-902A+B58.37BOOKED
B-903A+B58.37BOOKED
B-904A+B58.37BOOKED
SHOP GF - 1A+B22.29UNBOOKED
SHOP GF - 2A+B22.29UNBOOKED
SHOP GF - 3A+B22.22UNBOOKED
SHOP GF - 4A+B22.22BOOKED
SHOP GF - 5A+B22.29BOOKED
SHOP GF - 6A+B22.29BOOKED
SHOP GF - 7A+B22.29UNBOOKED
SHOP GF - 8A+B22.29UNBOOKED
SHOP GF - 9A+B22.22UNBOOKED
SHOP GF - 10A+B24.09UNBOOKED
SHOP GF - 11A+B24.09UNBOOKED
SHOP GF - 12A+B24.01UNBOOKED
SHOP GF - 13A+B35.86BOOKED
SHOP GF - 14A+B22.22UNBOOKED
SHOP GF - 15A+B22.29UNBOOKED
SHOP GF - 16A+B22.29BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%2021202220232024June 2021 — 17.53% builtSeptember 2021 — 23.91% builtDecember 2021 — 30.28% builtMarch 2022 — 41.44% builtJune 2022 — 46.22% builtSeptember 2022 — 49.41% builtDecember 2022 — 49.67% builtMarch 2023 — 50.73% builtJune 2023 — 77.03% builtJanuary 2024 — 100% built

10 quarterly returns · June 2021 (17.53%) to January 2024 (100%)

17.53%

Initial progress · June 2021

100%

Final progress · January 2024

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2021

    Registration

  2. 2023

    Annual Compliance

  3. Undated

    Annual Compliance

  4. 2026

    Snapshot reviewed

Full application ledger (5 rows)
  1. Registration — 2021-01-16 12:12:45.000000
  2. Annual Compliance — 2023-11-17 21:16:55
  3. Annual Compliance — 2023-11-17 21:16:55
  4. Annual Compliance — 2023-11-17 21:16:55
  5. Annual Compliance — undated

Quarterly filing history

2021

Q-1 · Q-2 · Q-3

2022

Q-4 · Q-5 · Q-6 · Q-7

2023

Q-8 · Q-9 · Q-E

—

Q-10

10 submitted · 1 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA07919/160121 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Authority
Others
Covered area
749.41 sq m
Open area
1192.59 sq m
Land cost
₹2.25 Cr
Estimated cost
₹13.42 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/201228/010115
Covered parking
1 · 861.74 sq m
Parking for sale
1

Escrow account

Bank
Axis Bank
Branch
SARGASAN
IFSC
UTIB0004377
Account
XXXX-0587
Deposited
₹0.62 Cr
Withdrawn
₹0.68 Cr
Closing
₹0 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
SAVAN SAXENA
Site visit
2023-06-30
Form-1 PDF
Open file
  • Block A+B100%
Phase actual dates (1 block)
  • Block A+B: excavation — → slab —

Filing PDFs

Project team on record

  • KETAV P JOSHI · engineer
  • SAVAN S SAXENA · architect
How is the paperwork score calculated?78 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    23 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2023-12-31 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 10/11 -> 23/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA07919/160121

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.