Delivered

Shivam Residency

FP 66 NEAR DIYA GREEN PARTY PLOT

Mixed Development69 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/11337

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA08023/080221

Shivam Residency — residential developmentGandhinagar · representative residential imagery

Paperwork score

Some gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings10 / 16
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Om Developers
Project type
Mixed Development
Total units
69
Project cost
₹10.3 Cr
Carpet area
4,568.3 sq m
Price band
₹5L – ₹0L
Carpet area per unit
15.81-103.15 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Mixed Development — 69 units · carpet 4,568.34 sq m
  • Block A
  • Block B
  • Declared start 2020-10-26 · completion 2025-03-31
  • Professionals on record: 0 architect(s), 0 engineer(s) · land not itemised

Location

23.2203° N, 72.6131° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

69

Total units

67

Booked (97%)

2

Unsold (3%)

97% booked · 3% unsold

Tower A34 units

32 booked (94%) · 2 available (6%)

Tower B35 units

35 booked (100%) · 0 available (0%)

Flat-level inventory (69 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
101A64.96BOOKED
102A64.96BOOKED
103A64.96BOOKED
104A64.96BOOKED
201A64.96BOOKED
202A64.96BOOKED
203A64.96BOOKED
204A64.96BOOKED
301A64.96BOOKED
302A64.96BOOKED
303A64.96BOOKED
304A64.96BOOKED
401A64.96BOOKED
402A64.96BOOKED
403A64.96BOOKED
404A64.96BOOKED
501A64.96BOOKED
502A64.96BOOKED
503A64.96BOOKED
504A64.96BOOKED
601A64.96BOOKED
602A64.96BOOKED
603A64.96BOOKED
604A64.96BOOKED
701A78.72BOOKED
702A78.72BOOKED
1A29.95BOOKED
2A30.49BOOKED
3A27.41BOOKED
4A22.38BOOKED
5A30.22BOOKED
6A28.52UNBOOKED
7A38BOOKED
8A38UNBOOKED
101B86.15BOOKED
102B86.15BOOKED
103B86.15BOOKED
104B86.15BOOKED
201B86.15BOOKED
202B86.15BOOKED
203B86.15BOOKED
204B86.15BOOKED
301B86.15BOOKED
302B86.15BOOKED
303B86.15BOOKED
304B86.15BOOKED
401B86.15BOOKED
402B86.15BOOKED
403B86.15BOOKED
404B86.15BOOKED
501B86.15BOOKED
502B86.15BOOKED
503B86.15BOOKED
504B86.15BOOKED
601B86.15BOOKED
602B86.15BOOKED
603B86.15BOOKED
604B86.15BOOKED
701B103.15BOOKED
702B103.15BOOKED
9B42.13BOOKED
10B40.79BOOKED
11B36.42BOOKED
12B40.55BOOKED
13B44.31BOOKED
14B15.81BOOKED
15B23.64BOOKED
16B32.45BOOKED
17B56.89BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%2021202220232025July 2021 — 50.07% builtOctober 2021 — 60.4% builtJanuary 2022 — 68.66% builtApril 2022 — 75.27% builtJuly 2022 — 82.22% builtOctober 2022 — 89.76% builtJanuary 2023 — 98.4% builtApril 2023 — 98.53% builtJuly 2023 — 100% builtApril 2025 — 100% built

10 quarterly returns · July 2021 (50.07%) to April 2025 (100%)

50.07%

Initial progress · July 2021

100%

Final progress · April 2025

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2021

    Registration · Annual Compliance

  2. 2023

    Annual Compliance

  3. Undated

    Annual Compliance

  4. 2026

    Snapshot reviewed

Full application ledger (6 rows)
  1. Registration — 2021-02-08 16:37:30.000000
  2. Annual Compliance — 2021-12-31 13:34:18
  3. Annual Compliance — 2023-11-17 21:17:09
  4. Annual Compliance — 2023-11-17 21:17:09
  5. Annual Compliance — undated
  6. Annual Compliance — undated

Quarterly filing history

2021

Q-1 · Q-2 · Q-3

2022

Q-4 · Q-5 · Q-6 · Q-7

2023

Q-8 · Q-9 · Q-E

—

Q-10 · Q-11 · Q-12 · Q-13 · Q-14 · Q-15

10 submitted · 6 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA08023/080221 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Authority
Others
Covered area
998.01 sq m
Open area
1320.99 sq m
Land cost
₹1.08 Cr
Estimated cost
₹9.22 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/210111/010228
Covered parking
2 · 1234.64 sq m
Parking for sale
1

Escrow account

Bank
IDFC Bank
Branch
GANDHINAGAR BRANCH
IFSC
IDFB0042343
Account
XXXX-5899
Deposited
₹0.31 Cr
Closing
₹0.4 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
HIREN PRAJAPATI
Site visit
2023-01-31
Form-1 PDF
Open file
  • Block A100%
  • Block B100%
Phase actual dates (2 blocks)
  • Block A: excavation — → slab —
  • Block B: excavation — → slab —

Filing PDFs

How is the paperwork score calculated?71 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    16 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2025-03-31 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 10/16 -> 16/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: QPR filing rate 62.5% is below 90%; no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA08023/080221

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.