Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Ongoing

Madhuram Enclave

Madhuram Enclave, Nr Palash Prime

Mixed Development79 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/11376

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/MAA08148/EX1/140623

Madhuram Enclave — residential developmentGandhinagar · representative residential imagery

Paperwork score

Material gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusOngoing
Quarterly filings8 / 10
Recorded complaints1
Extensions1
Promoter projects1 completed

Project at a glance

Developer
S P Construction
Project type
Mixed Development
Total units
79
Project cost
₹16.99 Cr
Carpet area
4,366.2 sq m
Price band
₹10L – ₹0L
Carpet area per unit
19.46-58.71 sq m
Status
Ongoing
Filing extras — blocks, inventory lines, dates
  • Mixed Development — 79 units · carpet 4,366.25 sq m
  • Block A
  • Declared start 2020-12-17 · completion 2023-07-31
  • Professionals on record: 0 architect(s), 0 engineer(s) · land not itemised

Location

23.1273° N, 72.5802° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

79

Total units

79

Booked (100%)

0

Unsold (0%)

100% booked · 0% unsold

Tower A79 units

79 booked (100%) · 0 available (0%)

Flat-level inventory (79 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
1A33.92BOOKED
2A33.92BOOKED
3A19.52BOOKED
4A19.46BOOKED
5A19.52BOOKED
6A26.6BOOKED
7A26.57BOOKED
8A21.69BOOKED
101A58.71BOOKED
102A58.6BOOKED
103A58.68BOOKED
104A58.68BOOKED
105A58.6BOOKED
106A58.71BOOKED
201A58.71BOOKED
202A58.6BOOKED
203A58.68BOOKED
204A58.68BOOKED
205A58.6BOOKED
206A58.71BOOKED
301A58.71BOOKED
302A58.6BOOKED
303A58.68BOOKED
304A58.68BOOKED
305A58.6BOOKED
306A58.71BOOKED
401A58.71BOOKED
402A58.6BOOKED
403A58.68BOOKED
404A58.68BOOKED
405A58.6BOOKED
406A58.71BOOKED
501A58.71BOOKED
502A58.6BOOKED
503A58.68BOOKED
504A58.68BOOKED
505A58.6BOOKED
506A58.71BOOKED
601A58.71BOOKED
602A58.6BOOKED
603A58.68BOOKED
604A58.68BOOKED
605A58.6BOOKED
606A58.71BOOKED
701A58.71BOOKED
702A58.6BOOKED
703A58.68BOOKED
704A58.68BOOKED
705A58.6BOOKED
706A58.71BOOKED
801A58.71BOOKED
802A58.6BOOKED
803A58.68BOOKED
804A58.68BOOKED
805A58.6BOOKED
806A58.71BOOKED
901A58.71BOOKED
902A58.6BOOKED
903A58.68BOOKED
904A58.68BOOKED
905A58.6BOOKED
906A58.71BOOKED
1001A58.71BOOKED
1002A58.6BOOKED
1003A58.68BOOKED
1004A58.68BOOKED
1005A58.6BOOKED
1006A58.71BOOKED
1101A58.71BOOKED
1102A58.6BOOKED
1103A58.68BOOKED
1104A58.68BOOKED
1105A58.6BOOKED
1106A58.71BOOKED
1202A58.6BOOKED
1203A58.68BOOKED
1204A58.68BOOKED
1205A58.6BOOKED
1206A58.71BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 78.75%
0%25%50%75%100%202120222023August 2021 — 27.41% builtNovember 2021 — 29.32% builtFebruary 2022 — 38.78% builtMay 2022 — 39.84% builtAugust 2022 — 43.78% builtNovember 2022 — 52.17% builtFebruary 2023 — 65.98% builtAugust 2023 — 78.75% built

8 quarterly returns · August 2021 (27.41%) to August 2023 (78.75%)

27.41%

Initial progress · August 2021

78.75%

Final progress · August 2023

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2021

    Registration · BCR

  2. 2023

    Extension · Annual Compliance

  3. 2024

    Complaint · Challan · Annual Compliance

  4. 2026

    Snapshot reviewed

Full application ledger (9 rows)
  1. Registration — 2021-03-04 15:00:44.000000
  2. Extension — 2023-06-14 15:50:52
  3. Complaint — 2024-09-18 16:38:00 · CMP3004202400596 (CLOSED)
  4. Challan — 2024-09-19 20:23:09 · CMP3004202400596 (status not published)
  5. Annual Compliance — 2023-11-17 21:17:13
  6. Annual Compliance — 2023-11-17 21:17:14
  7. Annual Compliance — 2023-11-17 21:17:14
  8. Annual Compliance — 2024-11-14 12:27:28
  9. BCR — 2021-10-07 11:11:13.000000

Quarterly filing history

2021

Q-1 · Q-2

2022

Q-3 · Q-4 · Q-5 · Q-6

2023

Q-7

—

X-1 · X-2

2024

Q-E

8 submitted · 2 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/MAA08148/EX1/140623 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Authority
AUDA
Covered area
660.5 sq m
Open area
1156 sq m
Land cost
₹2.24 Cr
Estimated cost
₹11 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/AUDA/210130/010278
Covered parking
71 · 1401.42 sq m
Parking for sale
13

Escrow account

Bank
DCB bank Ltd
Branch
C G ROAD
IFSC
DCBL0000036
Account
XXXX-0231
Deposited
₹13.11 Cr
Withdrawn
₹13.11 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
DHAVAL NATUBHAI MEWADA
Firm
DHAVAL NATUBHAI MEWADA
Site visit
2024-11-11
Form-1 PDF
Open file
  • Block A75%
Phase actual dates (1 block)
  • Block A: excavation → slab —

Filing PDFs

How is the paperwork score calculated?49 / 100
  • Delivery standing

    12 / 40

  • Filing discipline

    20 / 25

  • Promoter track record

    10 / 20

  • Complaints and extensions

    7 / 15

  • Delivery 2023-07-31 elapsed 3 yr ago, progress 78.75% -> 12/40
  • QPR filings 8/10 -> 20/25
  • Promoter completed projects 1 -> 10/20
  • Red flags 1 complaint + 1 extension -> 7/15

Confidence Medium: declared completion date elapsed 3 years ago with work still declared incomplete; QPR filing rate 80.0% is below 90%; 1 complaint entry on the ledger; 1 extension request on the ledger.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/MAA08148/EX1/140623

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.