Skip to content
Compare
Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Ongoing

Shri Suraj Residency

SHRI SURAJ RESIDENCY

ResidentialGroup Housing56 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/11674

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA08355/220421

Shri Suraj Residency — residential developmentGandhinagar · representative residential imagery

Paperwork score

Some gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusOngoing
Quarterly filings19 / 20
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Jignesh Patel Prop Of Suraj Infratech
Project type
Residential / Group Housing
Total units
56
Project cost
₹9.42 Cr
Carpet area
2,811.2 sq m
Price band
₹19L – ₹0L
Carpet area per unit
50.19-50.21 sq m
Status
Ongoing
Filing extras — blocks, inventory lines, dates
  • Residential/Group Housing — 56 units · carpet 2,811.2 sq m
  • Block A+B
  • Declared start 2020-01-01 · completion 2027-04-30
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.2205° N, 72.6200° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

56

Total units

42

Booked (75%)

14

Unsold (25%)

75% booked · 25% unsold

Tower A+B56 units

42 booked (75%) · 14 available (25%)

Flat-level inventory (56 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
A-101A+B50.21BOOKED
A-102A+B50.19BOOKED
A-103A+B50.19BOOKED
A-104A+B50.21BOOKED
A-201A+B50.21BOOKED
A-202A+B50.19BOOKED
A-203A+B50.19UNBOOKED
A-204A+B50.21UNBOOKED
A-301A+B50.21BOOKED
A-302A+B50.19BOOKED
A-303A+B50.19BOOKED
A-304A+B50.21BOOKED
A-401A+B50.21BOOKED
A-402A+B50.19BOOKED
A-403A+B50.19BOOKED
A-404A+B50.21UNBOOKED
A-501A+B50.21BOOKED
A-502A+B50.19BOOKED
A-503A+B50.19BOOKED
A-504A+B50.21UNBOOKED
A-601A+B50.21BOOKED
A-602A+B50.19BOOKED
A-603A+B50.19BOOKED
A-604A+B50.21BOOKED
A-701A+B50.21BOOKED
A-702A+B50.19UNBOOKED
A-703A+B50.19BOOKED
A-704A+B50.21UNBOOKED
B-101A+B50.21UNBOOKED
B-102A+B50.19UNBOOKED
B-103A+B50.19UNBOOKED
B-104A+B50.21UNBOOKED
B-201A+B50.21BOOKED
B-202A+B50.19BOOKED
B-203A+B50.19BOOKED
B-204A+B50.21BOOKED
B-301A+B50.21BOOKED
B-302A+B50.19BOOKED
B-303A+B50.19BOOKED
B-304A+B50.21BOOKED
B-401A+B50.21BOOKED
B-402A+B50.19BOOKED
B-403A+B50.19BOOKED
B-404A+B50.21BOOKED
B-501A+B50.21BOOKED
B-502A+B50.19UNBOOKED
B-503A+B50.19UNBOOKED
B-504A+B50.21BOOKED
B-601A+B50.21BOOKED
B-602A+B50.19BOOKED
B-603A+B50.19BOOKED
B-604A+B50.21BOOKED
B-701A+B50.21BOOKED
B-702A+B50.19UNBOOKED
B-703A+B50.19UNBOOKED
B-704A+B50.21BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 87%
0%25%50%75%100%202120222023202420252026September 2021 — 16.26% builtDecember 2021 — 16.89% builtMarch 2022 — 24.7% builtJune 2022 — 28.69% builtSeptember 2022 — 28.69% builtDecember 2022 — 30.28% builtMarch 2023 — 28.69% builtJune 2023 — 31.88% builtSeptember 2023 — 31.88% builtDecember 2023 — 100% builtApril 2024 — 100% builtJuly 2024 — 100% builtOctober 2024 — 100% builtOctober 2025 — 87% builtJanuary 2026 — 87% builtApril 2026 — 87% built

16 quarterly returns · September 2021 (16.26%) to April 2026 (87%)

16.26%

Initial progress · September 2021

87%

Final progress · April 2026

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2021

    Registration

  2. 2023

    Annual Compliance

  3. 2024

    Annual Compliance

  4. 2025

    Annual Compliance

  5. Undated

    Annual Compliance

  6. 2026

    Snapshot reviewed

Full application ledger (7 rows)
  1. Registration — 2021-04-22 15:05:22.000000
  2. Annual Compliance — 2023-11-17 21:17:54
  3. Annual Compliance — 2023-11-17 21:17:54
  4. Annual Compliance — 2024-09-30 14:44:45
  5. Annual Compliance — 2025-10-30 08:31:39
  6. Annual Compliance — undated
  7. Annual Compliance — undated

Quarterly filing history

2021

Q-1 · Q-2

2022

Q-3 · Q-4 · Q-5 · Q-6

2023

Q-7 · Q-8 · Q-9 · Q-10

2024

Q-11 · Q-12 · Q-13

2025

Q-14 · Q-15 · Q-16 · Q-17

2026

Q-18 · Q-19

—

Q-20

19 submitted · 1 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA08355/220421 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Authority
Others
Covered area
583.39 sq m
Open area
847.61 sq m
Land cost
₹0.74 Cr
Estimated cost
₹7.5 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/210301/010526
Parking for sale
1

Escrow account

Bank
HDFC
Branch
INFOCITY GANDHINAGAR
IFSC
HDFC0002497
Account
XXXX-0634
Deposited
₹0.81 Cr
Withdrawn
₹0.99 Cr
Closing
₹0.01 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
BHAUMIKKUMAR CHANDRAVADANBHAI DONGA
Form-1 PDF
  • Block A+B86.66666666666667%
Phase actual dates (1 block)
  • Block A+B: excavation 2020-01-01 → slab

Filing PDFs

Project team on record

  • MEET PATEL · engineer
  • SPACE CITZ · architect
How is the paperwork score calculated?79 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    24 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2027-04-30 still ahead of 2026-09-26 -> 40/40
  • QPR filings 19/20 -> 24/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA08355/220421

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.