Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Delivered

Manorath Malhar

MANORATH MALHAR

Mixed Development63 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/11747

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA08546/020621

Manorath Malhar — residential developmentGandhinagar · representative residential imagery

Paperwork score

Some gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings9 / 15
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Manorath Reality
Project type
Mixed Development
Total units
63
Project cost
₹14.93 Cr
Carpet area
3,992.5 sq m
Price band
₹5L – ₹0L
Carpet area per unit
13.29-68.91 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Mixed Development — 63 units · carpet 3,992.47 sq m
  • Block A
  • Block B
  • Declared start 2021-01-05 · completion 2025-03-31
  • Professionals on record: 0 architect(s), 0 engineer(s) · land not itemised

Location

23.1956° N, 72.6083° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

63

Total units

61

Booked (97%)

2

Unsold (3%)

97% booked · 3% unsold

Tower A35 units

33 booked (94%) · 2 available (6%)

Tower B28 units

28 booked (100%) · 0 available (0%)

Flat-level inventory (63 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
A-SHOP-1A25.44BOOKED
A-SHOP-2A25.19BOOKED
A-SHOP-3A25.44BOOKED
A-SHOP-4A13.29BOOKED
A-SHOP-5A25.44BOOKED
A-SHOP-6A25.19BOOKED
A-SHOP-7A25.44UNBOOKED
A-101A67.77BOOKED
A-102A67.77BOOKED
A-103A67.77BOOKED
A-104A67.77BOOKED
A-201A67.77BOOKED
A-202A67.77BOOKED
A-203A67.77UNBOOKED
A-204A67.77BOOKED
A-301A67.77BOOKED
A-302A67.77BOOKED
A-303A67.77BOOKED
A-304A67.77BOOKED
A-401A67.77BOOKED
A-402A67.77BOOKED
A-403A67.77BOOKED
A-404A67.77BOOKED
A-501A67.77BOOKED
A-502A67.77BOOKED
A-503A67.77BOOKED
A-504A67.77BOOKED
A-601A67.77BOOKED
A-602A67.77BOOKED
A-603A67.77BOOKED
A-604A67.77BOOKED
A-701A67.77BOOKED
A702A67.77BOOKED
A-703A67.77BOOKED
A-704A67.77BOOKED
B-101B68.91BOOKED
B-102B68.91BOOKED
B-103B68.91BOOKED
B-104B68.91BOOKED
B-201B68.91BOOKED
B-202B68.91BOOKED
B-203B68.91BOOKED
B-204B68.91BOOKED
B-301B68.91BOOKED
B-302B68.91BOOKED
B-303B68.91BOOKED
B-304B68.91BOOKED
B-401B68.91BOOKED
B-402B68.91BOOKED
B-403B68.91BOOKED
B-404B68.91BOOKED
B-501B68.91BOOKED
B-502B68.91BOOKED
B-503B68.91BOOKED
B-504B68.91BOOKED
B-601B68.91BOOKED
B-602B68.91BOOKED
B-603B68.91BOOKED
B-604B68.91BOOKED
B-701B68.91BOOKED
B-702B68.91BOOKED
B-703B68.91BOOKED
B-704B68.91BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%2021202220232025November 2021 — 13.52% builtFebruary 2022 — 20.72% builtMay 2022 — 31.77% builtAugust 2022 — 46.86% builtNovember 2022 — 59.02% builtFebruary 2023 — 68.69% builtMay 2023 — 75.68% builtAugust 2023 — 100% builtApril 2025 — 100% built

9 quarterly returns · November 2021 (13.52%) to April 2025 (100%)

13.52%

Initial progress · November 2021

100%

Final progress · April 2025

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2021

    Registration

  2. 2023

    Annual Compliance

  3. Undated

    Annual Compliance

  4. 2026

    Snapshot reviewed

Full application ledger (5 rows)
  1. Registration — 2021-06-02 15:43:57.000000
  2. Annual Compliance — 2023-11-17 21:18:00
  3. Annual Compliance — 2023-11-17 21:18:00
  4. Annual Compliance — undated
  5. Annual Compliance — undated

Quarterly filing history

2021

Q-1 · Q-2

2022

Q-3 · Q-4 · Q-5

2023

Q-6 · Q-7 · Q-8 · Q-E

—

Q-9 · Q-10 · Q-11 · Q-12 · Q-13 · Q-14

9 submitted · 6 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA08546/020621 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Authority
Others
Covered area
732.65 sq m
Open area
1305.35 sq m
Land cost
₹2.09 Cr
Estimated cost
₹12.74 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/210308/010579
Covered parking
1 · 1420.86 sq m
Parking for sale
1

Escrow account

Bank
HDFC
Branch
KUDASAN BRANCH
IFSC
HDFC0009102
Account
XXXX-0323
Deposited
₹0.06 Cr
Closing
₹0.06 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
SAVAN P PANCHAL
Site visit
2023-03-31
Form-1 PDF
Open file
  • Block A100%
  • Block B100%
Phase actual dates (2 blocks)
  • Block A: excavation — → slab —
  • Block B: excavation — → slab —

Filing PDFs

How is the paperwork score calculated?70 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    15 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2025-03-31 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 9/15 -> 15/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: QPR filing rate 60.0% is below 90%; no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA08546/020621

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.