Skip to content
Compare
Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Delivered

Shreerang Solitaire-1

SHREERANG SOLITAIRE-1,R.S.NO.: 204, F.P.NO.: 165

ResidentialGroup Housing12 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/13921

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA10172/EX1/070425/301225

Shreerang Solitaire-1 — residential developmentGandhinagar · representative residential imagery

Paperwork score

Some gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings12 / 14
Recorded complaints2
Extensions1
Promoter projects1 completed

Project at a glance

Developer
Shree Rang Infratech
Project type
Residential / Group Housing
Total units
12
Project cost
₹9.45 Cr
Carpet area
2,439.1 sq m
Price band
₹80L – ₹0L
Carpet area per unit
188.85000000000002-238.14999999999998 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Residential/Group Housing — 12 units · carpet 2,439.14 sq m
  • Block Shreerang Solitaire - 1
  • Declared start 2021-08-12 · completion 2025-12-30
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.1598° N, 72.6574° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

12

Total units

8

Booked (67%)

4

Unsold (33%)

67% booked · 33% unsold

Tower Shreerang Solitaire - 112 units

8 booked (67%) · 4 available (33%)

Flat-level inventory (12 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
1Shreerang Solitaire - 1208.32BOOKED
2Shreerang Solitaire - 1208.32UNBOOKED
3Shreerang Solitaire - 1188.85000000000002BOOKED
4Shreerang Solitaire - 1188.85000000000002BOOKED
5Shreerang Solitaire - 1188.85000000000002UNBOOKED
6Shreerang Solitaire - 1224.25BOOKED
7Shreerang Solitaire - 1188.85000000000002BOOKED
8Shreerang Solitaire - 1188.85000000000002BOOKED
9Shreerang Solitaire - 1188.85000000000002BOOKED
10Shreerang Solitaire - 1188.85000000000002BOOKED
11Shreerang Solitaire - 1238.14999999999998UNBOOKED
12Shreerang Solitaire - 1238.14999999999998UNBOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%20222023202420252026October 2022 — 54.45% builtJanuary 2023 — 60.56% builtApril 2023 — 65.34% builtJuly 2023 — 68.53% builtOctober 2023 — 90.91% builtJanuary 2024 — 100% builtApril 2024 — 100% builtJuly 2024 — 100% builtOctober 2024 — 100% builtOctober 2025 — 100% builtJanuary 2026 — 100% built

11 quarterly returns · October 2022 (54.45%) to January 2026 (100%)

54.45%

Initial progress · October 2022

100%

Final progress · January 2026

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2022

    Registration · Complaint · Challan

  2. 2023

    Annual Compliance

  3. 2024

    Annual Compliance

  4. 2025

    Extension · Annual Compliance

  5. Undated

    Complaint · Annual Compliance

  6. 2026

    Snapshot reviewed

Full application ledger (9 rows)
  1. Registration — 2022-05-11 10:41:06.000000
  2. Extension — 2025-04-07 12:49:06
  3. Complaint — 2022-11-03 09:42:42 · GJ/CMP/SM/Gandhinagar/221013/0091 (CLOSED)
  4. Complaint — undated · CMP2805202500520 (HEARING_SCHEDULE)
  5. Challan — 2022-11-11 11:33:42 · GJ/CMP/SM/Gandhinagar/221013/0091 (status not published)
  6. Annual Compliance — 2023-11-17 20:47:25
  7. Annual Compliance — 2024-10-25 15:23:26
  8. Annual Compliance — 2025-12-05 23:02:11
  9. Annual Compliance — undated

Quarterly filing history

2022

Q-1 · Q-2

2023

Q-3 · Q-4 · Q-5

2024

Q-6 · Q-7 · Q-8 · Q-9

—

X-1 · X-2

2025

X-3 · X-4

2026

Q-E

12 submitted · 2 missing

Documents on file

41 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA10172/EX1/070425/301225 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Authority
Others
Covered area
1101.94 sq m
Open area
1101.94 sq m
Land cost
₹1.45 Cr
Estimated cost
₹8.5 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GUJRERA/220319/012592
Parking for sale
0

Escrow account

Bank
HDFC
Branch
RAYSAN
IFSC
HDFC0005065
Account
XXXX-2952
Deposited
₹0.96 Cr
Withdrawn
₹0.97 Cr
Closing
₹0 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
ARPIT PRIYAVADAN MEENA SHAH
Firm
GREY LEAF
Site visit
2025-12-25
Form-1 PDF
Open file
  • Block Shreerang Solitaire - 1100%
Phase actual dates (1 block)
  • Block Shreerang Solitaire - 1: excavation → slab

Filing PDFs

Project team on record

  • RAJAN H PATEL · engineer
  • MR. ARPIT SHAH (GREY LEAF) · architect
How is the paperwork score calculated?75 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    21 / 25

  • Promoter track record

    10 / 20

  • Complaints and extensions

    4 / 15

  • Delivery 2025-12-30 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 12/14 -> 21/25
  • Promoter completed projects 1 -> 10/20
  • Red flags 2 complaints (live) + 1 extension -> 4/15

Confidence Medium: QPR filing rate 85.7% is below 90%; 2 complaint entries on the ledger; 1 extension request on the ledger.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA10172/EX1/070425/301225

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.