Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Ongoing

Devkunj 80

Opp. Nanabar Samaj Party Plot, Shaligram Lakeview Road, Bh. Vaishnodevi Temple,

ResidentialGroup Housing80 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/16040

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/RN236AA10136/211022

Devkunj 80 — residential developmentGandhinagar · representative residential imagery

Paperwork score

Some gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusOngoing
Quarterly filings12 / 15
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Devkunj Corporation
Project type
Residential / Group Housing
Total units
80
Project cost
₹33.74 Cr
Carpet area
8,865.6 sq m
Price band
₹49L – ₹0L
Carpet area per unit
110.49-111.15 sq m
Status
Ongoing
Filing extras — blocks, inventory lines, dates
  • Residential/Group Housing — 80 units · carpet 8,865.6 sq m
  • Block A
  • Block B
  • Declared start 2022-07-01 · completion 2026-12-31
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.1409° N, 72.5508° E

Filed plot outline · 8 corners
Open in Google Maps

Units & inventory

80

Total units

47

Booked (59%)

33

Unsold (41%)

59% booked · 41% unsold

Tower A40 units

16 booked (40%) · 24 available (60%)

Tower B40 units

31 booked (78%) · 9 available (22%)

Flat-level inventory (80 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
101A110.49UNBOOKED
102A110.49BOOKED
103A110.49UNBOOKED
104A110.49UNBOOKED
201A110.49UNBOOKED
202A110.49BOOKED
203A110.49BOOKED
204A110.49BOOKED
301A110.49UNBOOKED
302A110.49UNBOOKED
303A110.49BOOKED
304A110.49UNBOOKED
401A110.49UNBOOKED
402A110.49UNBOOKED
403A110.49UNBOOKED
404A110.49UNBOOKED
501A110.49UNBOOKED
502A110.49BOOKED
503A110.49UNBOOKED
504A110.49BOOKED
601A110.49UNBOOKED
602A110.49BOOKED
603A110.49UNBOOKED
604A110.49UNBOOKED
701A110.49UNBOOKED
702A110.49BOOKED
703A110.49BOOKED
704A110.49UNBOOKED
801A110.49UNBOOKED
802A110.49BOOKED
803A110.49BOOKED
804A110.49UNBOOKED
901A110.49UNBOOKED
902A110.49UNBOOKED
903A110.49BOOKED
904A110.49UNBOOKED
1001A110.49UNBOOKED
1002A110.49BOOKED
1003A110.49BOOKED
1004A110.49BOOKED
101B111.15UNBOOKED
102B111.15BOOKED
103B111.15UNBOOKED
104B111.15UNBOOKED
201B111.15BOOKED
202B111.15BOOKED
203B111.15BOOKED
204B111.15UNBOOKED
301B111.15BOOKED
302B111.15BOOKED
303B111.15BOOKED
304B111.15BOOKED
401B111.15UNBOOKED
402B111.15BOOKED
403B111.15BOOKED
404B111.15BOOKED
501B111.15BOOKED
502B111.15BOOKED
503B111.15BOOKED
504B111.15BOOKED
601B111.15BOOKED
602B111.15BOOKED
603B111.15BOOKED
604B111.15BOOKED
701B111.15BOOKED
702B111.15BOOKED
703B111.15UNBOOKED
704B111.15BOOKED
801B111.15BOOKED
802B111.15BOOKED
803B111.15BOOKED
804B111.15BOOKED
901B111.15BOOKED
902B111.15BOOKED
903B111.15BOOKED
904B111.15BOOKED
1001B111.15UNBOOKED
1002B111.15UNBOOKED
1003B111.15UNBOOKED
1004B111.15BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%20232024202520262027April 2023 — 37.75% builtJuly 2023 — 42.79% builtOctober 2023 — 55.71% builtJanuary 2024 — 65.63% builtApril 2024 — 68.79% builtJuly 2024 — 75.24% builtOctober 2024 — 79.21% builtOctober 2025 — 99.325% builtJanuary 2026 — 99.47% builtJanuary 2027 — 100% built

10 quarterly returns · April 2023 (37.75%) to January 2027 (100%)

37.75%

Initial progress · April 2023

100%

Final progress · January 2027

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2022

    Registration

  2. 2023

    Annual Compliance

  3. 2024

    Annual Compliance

  4. 2025

    Annual Compliance

  5. Undated

    Annual Compliance

  6. 2026

    Snapshot reviewed

Full application ledger (6 rows)
  1. Registration — 2022-10-21 17:12:38.157000
  2. Annual Compliance — 2023-10-27 18:25:26
  3. Annual Compliance — 2024-10-29 15:54:33
  4. Annual Compliance — 2025-12-09 17:43:10
  5. Annual Compliance — undated
  6. Annual Compliance — undated

Quarterly filing history

2023

Q-1 · Q-2 · Q-3

2024

Q-4 · Q-5 · Q-6 · Q-7

2025

Q-8 · Q-9 · Q-10 · Q-11

2026

Q-12

—

Q-13 · Q-14 · BWA-1

12 submitted · 3 missing

Documents on file

25 documents

Missing from this record: Registration certificate, Commencement certificate, Draft agreement for sale.

Registration (0)Registration certificate
  • None on this record.
Land & title (4)Title · EC · Clearance

4 of 4 open directly

Approvals (5)Plans · CC · NOCs

5 of 5 open directly

Builder finances (6)Accounts · ITR · Audit reports

6 of 6 open directly

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/RN236AA10136/211022 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Khoraj
Survey no.
493/2
TP scheme
Khoraj
Final / sub plot
59/2 / --
Authority
Gandhinagar Municipal Corporation
Covered area
1260.43 sq m
Open area
1804.57 sq m
BU permission
Registration cert
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR MUNICIPAL CORPORATION/220929/016040
Covered parking
133 · 2652.18 sq m
Parking for sale
75

Escrow account

Bank
HDFC BANK
Branch
CHANDKHEDA GANDHI NAGAR ROAD
IFSC
HDFC0004894
Account
XXXX-2410
Deposited
₹11.17 Cr
Withdrawn
₹11.17 Cr

Inspection phases (Form-1)

Architect
AMIBEN RAJESHBHAI PATEL
Firm
Amiben R Patel
Site visit
2026-04-06
Form-1 PDF
Open file
  • Block A100%
  • Block B100%
Phase actual dates (2 blocks)
  • Block A: excavation → slab
  • Block B: excavation → slab

Filing PDFs

Project team on record

  • RAJAN HASMUKHBHAI PATEL · engineer
  • VIPREX PANKAJBHAI CHAVDA · architect
How is the paperwork score calculated?75 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    20 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2026-12-31 still ahead of 2026-09-26 -> 40/40
  • QPR filings 12/15 -> 20/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: QPR filing rate 80.0% is below 90%; no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/RN236AA10136/211022

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.