Ongoing

Parishram Florenza

S.NO.574, FP.111/2, B/H VAISHNODEVI TEMPLE, S.G.ROAD,

ResidentialGroup Housing80 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/17193

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA10253/300522

Parishram Florenza — residential developmentGandhinagar · representative residential imagery

Paperwork score

Complete record

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusOngoing
Quarterly filings14 / 16
Recorded complaints0
ExtensionsNone recorded
Promoter projects1 completed

Project at a glance

Developer
North-Parishram Inframark
Project type
Residential / Group Housing
Total units
80
Project cost
₹31.39 Cr
Carpet area
8,235.6 sq m
Price band
₹35L – ₹0L
Carpet area per unit
100.4-105.49 sq m
Status
Ongoing
Filing extras — blocks, inventory lines, dates
  • Residential/Group Housing — 80 units · carpet 8,235.6 sq m
  • Block A
  • Block B
  • Declared start 2022-02-24 · completion 2027-01-31
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.1385° N, 72.5460° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

80

Total units

58

Booked (73%)

22

Unsold (27%)

73% booked · 27% unsold

Tower A40 units

36 booked (90%) · 4 available (10%)

Tower B40 units

22 booked (55%) · 18 available (45%)

Flat-level inventory (80 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
101A100.4BOOKED
102A105.49BOOKED
103A105.49BOOKED
104A100.4UNBOOKED
201A100.4BOOKED
202A105.49BOOKED
203A105.49BOOKED
204A100.4BOOKED
301A100.4BOOKED
302A105.49BOOKED
303A105.49BOOKED
304A100.4BOOKED
401A100.4BOOKED
402A105.49BOOKED
403A105.49BOOKED
404A100.4BOOKED
501A100.4BOOKED
502A105.49BOOKED
503A105.49BOOKED
504A100.4BOOKED
601A100.4BOOKED
602A105.49BOOKED
603A105.49BOOKED
604A100.4BOOKED
701A100.4BOOKED
702A105.49BOOKED
703A105.49BOOKED
704A100.4BOOKED
801A100.4BOOKED
802A105.49BOOKED
803A105.49BOOKED
804A100.4BOOKED
901A100.4BOOKED
902A105.49BOOKED
903A105.49BOOKED
904A100.4BOOKED
1001A100.4BOOKED
1002A105.49BOOKED
1003A105.49BOOKED
1004A100.4BOOKED
101B100.4UNBOOKED
102B105.49BOOKED
103B105.49BOOKED
104B100.4BOOKED
201B100.4UNBOOKED
202B105.49BOOKED
203B105.49BOOKED
204B100.4UNBOOKED
301B100.4BOOKED
302B105.49BOOKED
303B105.49BOOKED
304B100.4BOOKED
401B100.4BOOKED
402B105.49BOOKED
403B105.49BOOKED
404B100.4UNBOOKED
501B100.4UNBOOKED
502B105.49BOOKED
503B105.49BOOKED
504B100.4UNBOOKED
601B100.4UNBOOKED
602B105.49BOOKED
603B105.49BOOKED
604B100.4UNBOOKED
701B100.4BOOKED
702B105.49BOOKED
703B105.49BOOKED
704B100.4UNBOOKED
801B100.4UNBOOKED
802B105.49BOOKED
803B105.49BOOKED
804B100.4UNBOOKED
901B100.4UNBOOKED
902B105.49BOOKED
903B105.49BOOKED
904B100.4BOOKED
1001B100.4UNBOOKED
1002B105.49BOOKED
1003B105.49BOOKED
1004B100.4BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 89.375%
0%25%50%75%100%202220232024202520262027October 2022 — 11.95% builtJanuary 2023 — 34% builtApril 2023 — 60.83% builtJuly 2023 — 66.27% builtOctober 2023 — 72.25% builtJanuary 2024 — 64.68% builtApril 2024 — 70.79% builtJuly 2024 — 71.98% builtOctober 2024 — 72.2% builtOctober 2025 — 100% builtJanuary 2026 — 100% builtFebruary 2027 — 89.375% built

12 quarterly returns · October 2022 (11.95%) to February 2027 (89.375%)

11.95%

Initial progress · October 2022

89.375%

Final progress · February 2027

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2022

    Registration · BCR

  2. 2023

    Annual Compliance

  3. 2024

    Annual Compliance

  4. 2025

    Annual Compliance

  5. Undated

    Annual Compliance

  6. 2026

    Snapshot reviewed

Full application ledger (7 rows)
  1. Registration — 2022-05-30 17:12:30.000000
  2. Annual Compliance — 2023-11-17 19:36:28
  3. Annual Compliance — 2024-09-29 21:33:43
  4. Annual Compliance — 2025-11-17 11:47:48
  5. Annual Compliance — undated
  6. Annual Compliance — undated
  7. BCR — 2022-11-16 18:07:30.000000

Quarterly filing history

2022

Q-1

2023

Q-2 · Q-3 · Q-4 · Q-5

2024

Q-6 · Q-7 · Q-8 · Q-9

2025

Q-10 · Q-11 · Q-12 · Q-13

2026

Q-14

—

Q-15 · Q-16

14 submitted · 2 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA10253/300522 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Authority
Others
Covered area
1111.4 sq m
Open area
1923.6 sq m
Land cost
₹3.29 Cr
Estimated cost
₹28.1 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GUJRERA/220421/012675
Covered parking
287 · 2538.95 sq m
Parking for sale
0

Escrow account

Bank
Mehsana Urban Co-Operative Bank Ltd.
Branch
S.G. HIGHWAY, AHMEDABAD
IFSC
MSNU0000044
Account
XXXX-0651
Deposited
₹2.09 Cr
Withdrawn
₹1.75 Cr
Closing
₹0.35 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
HARSHAD DHANJIBHAI MISTRY
Firm
H M ARCHITECTS
Site visit
2026-01-02
Form-1 PDF
Open file
  • Block A87.5%
  • Block B87.5%
Phase actual dates (2 blocks)
  • Block A: excavation → slab
  • Block B: excavation → slab

Filing PDFs

Project team on record

  • Setu Infrastructure · engineer
  • H.M.ARCHITECTS · architect
How is the paperwork score calculated?87 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    22 / 25

  • Promoter track record

    10 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2027-01-31 still ahead of 2026-09-26 -> 40/40
  • QPR filings 14/16 -> 22/25
  • Promoter completed projects 1 -> 10/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: QPR filing rate 87.5% is below 90%.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA10253/300522

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.