Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Delivered

Vashikaa Prime

Vashikaa Prime, Near Dev Paradise,

Mixed Development90 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/17304

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA10263/A1M/191122

Vashikaa Prime — residential developmentGandhinagar · representative residential imagery

Paperwork score

Some gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings12 / 14
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Vashikaa Land Developers Llp
Project type
Mixed Development
Total units
90
Project cost
₹31.89 Cr
Carpet area
6,921.2 sq m
Price band
₹20L – ₹0L
Carpet area per unit
26.72-80.69 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Mixed Development — 90 units · carpet 6,921.16 sq m
  • Block A
  • Declared start 2022-03-31 · completion 2025-10-31
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

22.9761° N, 72.6688° E

Filed plot outline · 6 corners
Open in Google Maps

Units & inventory

90

Total units

61

Booked (68%)

29

Unsold (32%)

68% booked · 32% unsold

Tower A90 units

61 booked (68%) · 29 available (32%)

Flat-level inventory (90 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
1A52.75BOOKED
2A47.84BOOKED
3A34.92BOOKED
4A33.03BOOKED
5A26.72BOOKED
6A37.37BOOKED
7A45.98UNBOOKED
8A49.63BOOKED
101A80.69BOOKED
102A79.78BOOKED
103A80.69BOOKED
104A80.69BOOKED
105A79.78BOOKED
106A80.69UNBOOKED
201A80.69BOOKED
202A79.78BOOKED
203A80.69BOOKED
204A80.69UNBOOKED
205A79.78BOOKED
206A80.69BOOKED
301A80.69BOOKED
302A79.78BOOKED
303A80.69BOOKED
304A80.69UNBOOKED
305A79.78BOOKED
306A80.69BOOKED
401A80.69BOOKED
402A79.78BOOKED
403A80.69BOOKED
404A80.69UNBOOKED
405A79.78UNBOOKED
406A80.69BOOKED
501A80.69BOOKED
502A79.78BOOKED
503A80.69BOOKED
504A80.69BOOKED
505A79.78UNBOOKED
506A80.69UNBOOKED
601A80.69BOOKED
602A79.78BOOKED
603A80.69BOOKED
604A80.69UNBOOKED
605A79.78UNBOOKED
606A80.69UNBOOKED
701A80.69BOOKED
702A79.78BOOKED
703A80.69BOOKED
704A80.69UNBOOKED
705A79.78BOOKED
706A80.69UNBOOKED
801A80.69BOOKED
802A79.78BOOKED
803A80.69BOOKED
804A80.69UNBOOKED
805A79.78UNBOOKED
806A80.69UNBOOKED
901A80.69BOOKED
902A79.78BOOKED
903A80.69BOOKED
904A80.69UNBOOKED
905A79.78UNBOOKED
906A80.69UNBOOKED
1001A80.69BOOKED
1002A79.78BOOKED
1003A80.69BOOKED
1004A80.69BOOKED
1005A79.78UNBOOKED
1006A80.69BOOKED
1101A80.69BOOKED
1102A79.78BOOKED
1103A80.69BOOKED
1104A80.69BOOKED
1105A79.78UNBOOKED
1106A80.69UNBOOKED
1201A80.69BOOKED
1202A79.78UNBOOKED
1203A80.69BOOKED
1204A80.69BOOKED
1205A79.78UNBOOKED
1206A80.69BOOKED
1301A80.69UNBOOKED
1302A79.78UNBOOKED
1303A80.69BOOKED
1304A80.69UNBOOKED
1305A79.78UNBOOKED
1306A80.69BOOKED
1401A80.69BOOKED
1402A80.69BOOKED
1403A80.69BOOKED
1404A80.69UNBOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%2022202320242025November 2022 — 6.38% builtFebruary 2023 — 19.92% builtMay 2023 — 25.5% builtAugust 2023 — 32.67% builtNovember 2023 — 38.78% builtJanuary 2024 — 34.84% builtApril 2024 — 38.3% builtJuly 2024 — 42.23% builtOctober 2024 — 58.76% builtNovember 2025 — 100% built

10 quarterly returns · November 2022 (6.38%) to November 2025 (100%)

6.38%

Initial progress · November 2022

100%

Final progress · November 2025

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2022

    Registration · Alteration · BCR

  2. 2023

    Annual Compliance

  3. 2024

    Annual Compliance

  4. 2025

    Annual Compliance

  5. Undated

    Annual Compliance

  6. 2026

    Snapshot reviewed

Full application ledger (7 rows)
  1. Registration — 2022-06-02 17:43:11.000000
  2. Alteration — 2022-11-19 15:13:24.000000
  3. Annual Compliance — 2023-11-17 19:40:50
  4. Annual Compliance — 2024-09-29 17:49:03
  5. Annual Compliance — 2025-07-02 18:48:10
  6. Annual Compliance — undated
  7. BCR — 2022-10-12 11:48:49.000000

Quarterly filing history

2022

Q-1

2023

Q-2 · Q-3 · Q-4 · Q-5

2024

Q-6 · Q-7 · Q-8 · Q-9

2025

Q-10 · Q-11 · Q-E

—

Q-12 · Q-13

12 submitted · 2 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA10263/A1M/191122 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Authority
Others
Covered area
803.21 sq m
Open area
1256.79 sq m
Land cost
₹5.59 Cr
Estimated cost
₹26.3 Cr
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GUJRERA/220509/012801
Covered parking
30 · 2325.06 sq m
Parking for sale
4

Escrow account

Bank
HDFC
Branch
Chandkheda
IFSC
HDFC0001083
Account
XXXX-9858
Deposited
₹7.65 Cr
Withdrawn
₹7.65 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
UNNATI BHARATBHAI PATEL
Firm
UNNATI BHARATBHAI PATEL
Site visit
2025-06-25
Form-1 PDF
Open file
  • Block A100%
Phase actual dates (1 block)
  • Block A: excavation → slab

Filing PDFs

Project team on record

  • Achal Jitendra Parikh · engineer
  • UNNATI BHARATBHAI PATEL · architect
How is the paperwork score calculated?76 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    21 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2025-10-31 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 12/14 -> 21/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: QPR filing rate 85.7% is below 90%; no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA10263/A1M/191122

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.