Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Ongoing

Shivalay Duplex

SHIVALAY DUPLEX

ResidentialGroup Housing33 unitsRERA Reg. No. PR/GJ/VADODARA/17544

Filing PR/GJ/VADODARA/VADODARA/Others/RAA10587/EX1/220926/310727

Shivalay Duplex — residential developmentVadodara · representative residential imagery

Paperwork score

Some gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusOngoing
Quarterly filings9 / 15
Recorded complaints1
Extensions1
Promoter projectsNone completed on record

Project at a glance

Developer
Destination Developers
Project type
Residential / Group Housing
Total units
33
Project cost
₹7.31 Cr
Carpet area
2,095.3 sq m
Price band
₹22L – ₹0L
Carpet area per unit
60.56-63.9 sq m
Status
Ongoing
Filing extras — blocks, inventory lines, dates
  • Residential/Group Housing — 33 units · carpet 2,095.34 sq m
  • Block DUPLEX NO 1 TO 33
  • Declared start 2022-04-01 · completion 2027-07-31
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

22.3976° N, 73.1335° E

Filed plot outline · 6 corners
Open in Google Maps

Units & inventory

33

Total units

16

Booked (48%)

17

Unsold (52%)

48% booked · 52% unsold

Tower DUPLEX NO 1 TO 3333 units

16 booked (48%) · 17 available (52%)

Flat-level inventory (33 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
1DUPLEX NO 1 TO 3363.9UNBOOKED
2DUPLEX NO 1 TO 3363.9UNBOOKED
3DUPLEX NO 1 TO 3363.9UNBOOKED
4DUPLEX NO 1 TO 3363.9UNBOOKED
5DUPLEX NO 1 TO 3363.9UNBOOKED
6DUPLEX NO 1 TO 3363.9UNBOOKED
7DUPLEX NO 1 TO 3363.9UNBOOKED
8DUPLEX NO 1 TO 3363.9BOOKED
9DUPLEX NO 1 TO 3363.9BOOKED
10DUPLEX NO 1 TO 3363.9BOOKED
11DUPLEX NO 1 TO 3363.9BOOKED
12DUPLEX NO 1 TO 3363.9BOOKED
13DUPLEX NO 1 TO 3363.9BOOKED
14DUPLEX NO 1 TO 3363.9BOOKED
15DUPLEX NO 1 TO 3363.9BOOKED
16DUPLEX NO 1 TO 3363.9BOOKED
17DUPLEX NO 1 TO 3363.9BOOKED
18DUPLEX NO 1 TO 3363.9BOOKED
19DUPLEX NO 1 TO 3363.9BOOKED
20DUPLEX NO 1 TO 3360.56UNBOOKED
21DUPLEX NO 1 TO 3360.56UNBOOKED
22DUPLEX NO 1 TO 3360.56UNBOOKED
23DUPLEX NO 1 TO 3360.56UNBOOKED
24DUPLEX NO 1 TO 3363.9BOOKED
25DUPLEX NO 1 TO 3363.9UNBOOKED
26DUPLEX NO 1 TO 3363.9UNBOOKED
27DUPLEX NO 1 TO 3363.9UNBOOKED
28DUPLEX NO 1 TO 3363.9UNBOOKED
29DUPLEX NO 1 TO 3363.9UNBOOKED
30DUPLEX NO 1 TO 3363.9UNBOOKED
31DUPLEX NO 1 TO 3363.9UNBOOKED
32DUPLEX NO 1 TO 3363.9UNBOOKED
33DUPLEX NO 1 TO 3363.9UNBOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 79.6824%
0%25%50%75%100%202320252026January 2023 — 0.8% builtApril 2023 — 15.94% builtJuly 2023 — 17.8% builtOctober 2023 — 18.86% builtOctober 2025 — 65.7444% builtJanuary 2026 — 79.6824% built

6 quarterly returns · January 2023 (0.8%) to January 2026 (79.6824%)

0.8%

Initial progress · January 2023

79.6824%

Final progress · January 2026

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2022

    Registration

  2. 2023

    Annual Compliance

  3. 2024

    Annual Compliance

  4. 2025

    Complaint · Annual Compliance

  5. 2026

    Extension

  6. Undated

    Annual Compliance

  7. 2026

    Snapshot reviewed

Full application ledger (8 rows)
  1. Registration — 2022-08-24 12:57:00.000000
  2. Extension — 2026-09-22 11:04:43
  3. Complaint — 2025-04-09 16:09:58 · CMP0608202401309 (CLOSED)
  4. Annual Compliance — 2023-11-17 19:48:41
  5. Annual Compliance — 2024-10-30 11:49:57
  6. Annual Compliance — 2025-10-30 16:43:52
  7. Annual Compliance — undated
  8. Annual Compliance — undated

Quarterly filing history

2023

Q-1 · Q-2 · Q-3 · Q-4

—

Q-5 · Q-6 · Q-7 · Q-8 · X-1 · X-2

2025

Q-9 · Q-10 · Q-11 · Q-12

2026

Q-13

9 submitted · 6 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/VADODARA/VADODARA/Others/RAA10587/EX1/220926/310727 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
SARGASAN
Survey no.
435
TP scheme
SARGASAN-TARAPUR-ADALAJ-UVARSAD
Final / sub plot
160 / - -
Authority
Gandhinagar Municipal Corporation
Covered area
1319.73 sq m
Open area
3171.87 sq m
BU permission
Registration cert
Ack no.
PR/VADODARA/VADODARA/GUJRERA/220714/013063
Parking for sale
0

Escrow account

Bank
IndusInd Bank Ltd.
Branch
JETALPUR ROAD
IFSC
INDB0000017
Account
XXXX-7878
Status
APPROVED

Inspection phases (Form-1)

Architect
RITEKSH PATEL
Form-1 PDF
  • Block DUPLEX NO 1 TO 3387.98044444444444%
Phase actual dates (1 block)
  • Block DUPLEX NO 1 TO 33: excavation 2022-06-01 → slab —

Filing PDFs

Project team on record

  • MADHUSUDAN PATEL · engineer
  • RITEKSH B PATEL · architect
How is the paperwork score calculated?62 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    15 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    7 / 15

  • Delivery 2027-07-31 still ahead of 2026-09-26 -> 40/40
  • QPR filings 9/15 -> 15/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 1 complaint + 1 extension -> 7/15

Confidence Medium: QPR filing rate 60.0% is below 90%; no completed project on the promoter record; 1 complaint entry on the ledger; 1 extension request on the ledger.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/VADODARA/VADODARA/Others/RAA10587/EX1/220926/310727

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.