Skip to content
Compare
Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Ongoing

Devasya Gold

"DEVASYA GOLD", FP NO.124/2, SURVEY NO.208/2, TPS:1(KOBA-KUDASAN),

ResidentialGroup Housing80 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/17572

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA10601/290822

Devasya Gold — residential developmentGandhinagar · representative residential imagery

Paperwork score

Complete record

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusOngoing
Quarterly filings16 / 16
Recorded complaints0
ExtensionsNone recorded
Promoter projects1 completed

Project at a glance

Developer
Somnath Developers
Project type
Residential / Group Housing
Total units
80
Project cost
₹20.85 Cr
Carpet area
6,158 sq m
Price band
₹28L – ₹0L
Carpet area per unit
73.71-80.24 sq m
Status
Ongoing
Filing extras — blocks, inventory lines, dates
  • Residential/Group Housing — 80 units · carpet 6,158 sq m
  • Block A
  • Block B
  • Declared start 2022-03-31 · completion 2027-04-30
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.1534° N, 72.6505° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

80

Total units

61

Booked (76%)

19

Unsold (24%)

76% booked · 24% unsold

Tower A40 units

35 booked (88%) · 5 available (12%)

Tower B40 units

26 booked (65%) · 14 available (35%)

Flat-level inventory (80 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
A-101A80.24BOOKED
A-102A80.24BOOKED
A-103A80.24UNBOOKED
A-104A80.24BOOKED
A-201A80.24BOOKED
A-202A80.24BOOKED
A-203A80.24BOOKED
A-204A80.24BOOKED
A-301A80.24BOOKED
A-302A80.24BOOKED
A-303A80.24BOOKED
A-304A80.24BOOKED
A-401A80.24BOOKED
A-402A80.24BOOKED
A-403A80.24BOOKED
A-404A80.24BOOKED
A-501A80.24BOOKED
A-502A80.24BOOKED
A-503A80.24BOOKED
A-504A80.24BOOKED
A-601A80.24BOOKED
A-602A80.24BOOKED
A-603A80.24BOOKED
A-604A80.24BOOKED
A-701A80.24BOOKED
A-702A80.24BOOKED
A-703A80.24BOOKED
A-704A80.24BOOKED
A-801A80.24BOOKED
A-802A80.24BOOKED
A-803A80.24BOOKED
A-804A80.24BOOKED
A-901A80.24BOOKED
A-902A80.24BOOKED
A-903A80.24BOOKED
A-904A80.24BOOKED
A-1001A80.24BOOKED
A-1002A80.24BOOKED
A-1003A80.24BOOKED
A-1004A80.24UNBOOKED
B-101B73.71BOOKED
B-102B73.71BOOKED
B-103B73.71BOOKED
B-104B73.71BOOKED
B-201B73.71BOOKED
B-202B73.71BOOKED
B-203B73.71BOOKED
B-204B73.71BOOKED
B-301B73.71BOOKED
B-302B73.71BOOKED
B-303B73.71BOOKED
B-304B73.71BOOKED
B-401B73.71BOOKED
B-402B73.71BOOKED
B-403B73.71BOOKED
B-404B73.71BOOKED
B-501B73.71BOOKED
B-502B73.71BOOKED
B-503B73.71BOOKED
B-504B73.71UNBOOKED
B-601B73.71BOOKED
B-602B73.71BOOKED
B-603B73.71BOOKED
B-604B73.71BOOKED
B-701B73.71BOOKED
B-702B73.71BOOKED
B-703B73.71BOOKED
B-704B73.71BOOKED
B-801B73.71UNBOOKED
B-802B73.71BOOKED
B-803B73.71BOOKED
B-804B73.71UNBOOKED
B-901B73.71BOOKED
B-902B73.71BOOKED
B-903B73.71BOOKED
B-904B73.71BOOKED
B-1001B73.71BOOKED
B-1002B73.71UNBOOKED
B-1003B73.71BOOKED
B-1004B73.71UNBOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%2023202420252026January 2023 — 21.99% builtApril 2023 — 38.89% builtJuly 2023 — 48.48% builtOctober 2023 — 54.11% builtJanuary 2024 — 57.8% builtApril 2024 — 60.72% builtJuly 2024 — 65.93% builtOctober 2024 — 69.95% builtOctober 2025 — 99.1% builtJanuary 2026 — 99.5% builtApril 2026 — 100% builtJuly 2026 — 100% built

12 quarterly returns · January 2023 (21.99%) to July 2026 (100%)

21.99%

Initial progress · January 2023

100%

Final progress · July 2026

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2022

    Registration

  2. 2023

    Annual Compliance

  3. 2024

    Annual Compliance

  4. 2025

    Annual Compliance

  5. Undated

    Annual Compliance

  6. 2026

    Snapshot reviewed

Full application ledger (7 rows)
  1. Registration — 2022-08-29 14:48:11.000000
  2. Annual Compliance — 2023-11-17 19:49:33
  3. Annual Compliance — 2024-10-08 14:26:31
  4. Annual Compliance — 2025-11-13 15:08:28
  5. Annual Compliance — undated
  6. Annual Compliance — undated
  7. Annual Compliance — 2023-11-17 19:49:33

Quarterly filing history

2022

Q-1

2023

Q-2 · Q-3 · Q-4

2024

Q-5 · Q-6 · Q-7 · Q-8

2025

Q-9 · Q-10 · Q-11 · Q-12 · BWA-1

2026

Q-13 · Q-14 · Q-15

16 submitted · 0 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA10601/290822 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Authority
Others
Covered area
954.93 sq m
Open area
1675.07 sq m
Land cost
₹1.53 Cr
Estimated cost
₹15.5 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GUJRERA/220714/013098
Covered parking
13 · 1801.9 sq m
Parking for sale
0

Escrow account

Bank
IDFC Bank
Branch
GANDHINAGAR
IFSC
IDFB0042343
Account
XXXX-8879
Deposited
₹5.12 Cr
Withdrawn
₹5.33 Cr
Closing
₹0.06 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
BHAUMIKKUMAR CHANDRAVADANBHAI DONGA
Form-1 PDF
  • Block A100%
  • Block B100%
Phase actual dates (2 blocks)
  • Block A: excavation 2022-03-31 → slab
  • Block B: excavation 2022-03-31 → slab

Filing PDFs

Project team on record

  • NARENDRA K PATEL (HNS DESIGN STUDIO) · engineer
  • BHAUMIKKUMAR C DONGA · architect
How is the paperwork score calculated?90 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    25 / 25

  • Promoter track record

    10 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2027-04-30 still ahead of 2026-09-26 -> 40/40
  • QPR filings 16/16 -> 25/25
  • Promoter completed projects 1 -> 10/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA10601/290822

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.