Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Ongoing

Mg Dreams

RESI. SUR NO 679, O.P. NO.: 48, F.P. NO.: 48

ResidentialGroup Housing70 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/17573

Filing PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA10555/170822

Mg Dreams — residential developmentGandhinagar · representative residential imagery

Paperwork score

Material gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusOngoing
Quarterly filings12 / 15
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Lalji Buildcon
Project type
Residential / Group Housing
Total units
70
Project cost
₹30.53 Cr
Carpet area
7,247.9 sq m
Price band
₹42L – ₹0L
Carpet area per unit
91.46-145.84 sq m
Status
Ongoing
Filing extras — blocks, inventory lines, dates
  • Residential/Group Housing — 70 units · carpet 7,247.92 sq m
  • Block A
  • Block B
  • Declared start 2022-06-15 · completion 2026-06-15
  • Professionals on record: 2 architect(s), 1 engineer(s) · land not itemised

Location

23.2409° N, 72.4839° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

70

Total units

61

Booked (87%)

9

Unsold (13%)

87% booked · 13% unsold

Tower A34 units

33 booked (97%) · 1 available (3%)

Tower B36 units

28 booked (78%) · 8 available (22%)

Flat-level inventory (70 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
A101A114.49BOOKED
A102A114.49BOOKED
A103A114.49BOOKED
A104A114.49BOOKED
A201A114.49BOOKED
A202A114.49BOOKED
A203A114.49BOOKED
A204A114.49BOOKED
A301A114.49BOOKED
A302A114.49BOOKED
A303A114.49BOOKED
A304A114.49BOOKED
A401A114.49BOOKED
A402A114.49BOOKED
A403A114.49UNBOOKED
A404A114.49BOOKED
A501A114.49BOOKED
A502A114.49BOOKED
A503A114.49BOOKED
A504A114.49BOOKED
A601A114.49BOOKED
A602A114.49BOOKED
A603A114.49BOOKED
A604A114.49BOOKED
A701A114.49BOOKED
A702A114.49BOOKED
A703A114.49BOOKED
A704A114.49BOOKED
A801A114.49BOOKED
A802A114.49BOOKED
A803A114.49BOOKED
A804A114.49BOOKED
A901A145.84BOOKED
A902A145.84BOOKED
B101B91.46BOOKED
B102B91.46BOOKED
B103B91.46BOOKED
B104B91.46BOOKED
B201B91.46BOOKED
B202B91.46BOOKED
B203B91.46BOOKED
B204B91.46UNBOOKED
B301B91.46BOOKED
B302B91.46BOOKED
B303B91.46BOOKED
B304B91.46BOOKED
B401B91.46BOOKED
B402B91.46BOOKED
B403B91.46BOOKED
B404B91.46BOOKED
B501B91.46UNBOOKED
B502B91.46BOOKED
B503B91.46BOOKED
B504B91.46BOOKED
B601B91.46BOOKED
B602B91.46BOOKED
B603B91.46UNBOOKED
B604B91.46BOOKED
B701B91.46BOOKED
B702B91.46BOOKED
B703B91.46BOOKED
B704B91.46BOOKED
B801B91.46BOOKED
B802B91.46UNBOOKED
B803B91.46BOOKED
B804B91.46BOOKED
B901B91.46UNBOOKED
B902B91.46UNBOOKED
B903B91.46UNBOOKED
B904B91.46UNBOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 98.85%
0%25%50%75%100%202320242026January 2023 — 30.54% builtApril 2023 — 43.34% builtJuly 2023 — 46.37% builtOctober 2023 — 51.63% builtJanuary 2024 — 53.73% builtApril 2024 — 56.62% builtJuly 2024 — 58.47% builtOctober 2024 — 63.29% builtJuly 2026 — 98.85% built

9 quarterly returns · January 2023 (30.54%) to July 2026 (98.85%)

30.54%

Initial progress · January 2023

98.85%

Final progress · July 2026

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2022

    Registration

  2. 2023

    Annual Compliance

  3. 2024

    Annual Compliance

  4. 2025

    Annual Compliance

  5. Undated

    Annual Compliance

  6. 2026

    Snapshot reviewed

Full application ledger (5 rows)
  1. Registration — 2022-08-17 11:08:46.000000
  2. Annual Compliance — 2023-11-17 19:49:35
  3. Annual Compliance — 2024-09-30 16:30:11
  4. Annual Compliance — 2025-07-10 18:56:36
  5. Annual Compliance — undated

Quarterly filing history

2022

Q-1

2023

Q-2 · Q-3 · Q-4

2024

Q-5 · Q-6 · Q-7 · Q-8

2025

Q-9 · Q-10 · Q-11 · Q-E

—

Q-12 · Q-13 · Q-14

12 submitted · 3 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA10555/170822 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Authority
AUDA
Covered area
1176.72 sq m
Open area
2105.28 sq m
Land cost
₹1.02 Cr
Estimated cost
₹24.36 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/KALOL/GUJRERA/220718/013097
Covered parking
70 · 4310.38 sq m
Parking for sale
0

Escrow account

Bank
Mehsana Urban Co-Operative Bank Ltd.
Branch
B.T. MALL, NAVJIVAN MILL COMP. KALOL
IFSC
MSNU0000012
Account
XXXX-1217
Deposited
₹2.12 Cr
Withdrawn
₹2.23 Cr
Closing
₹0.04 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
KEYUR RAJNIBHAI MEWADA
Firm
KEYUR MEWADA
Site visit
2025-04-23
Form-1 PDF
Open file
  • Block A100%
  • Block B100%
Phase actual dates (2 blocks)
  • Block A: excavation → slab
  • Block B: excavation → slab

Filing PDFs

Project team on record

  • RAJAN H. PATEL · engineer
  • KEYUR MEWADA · architect
  • AKASH PATEL · architect
How is the paperwork score calculated?59 / 100
  • Delivery standing

    24 / 40

  • Filing discipline

    20 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2026-06-15 elapsed 0 yr ago, progress 98.85% -> 24/40
  • QPR filings 12/15 -> 20/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: declared completion date elapsed this year with work still declared incomplete; QPR filing rate 80.0% is below 90%; no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA10555/170822

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.