Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Ongoing

Shreeji Siesta

Shreeji Siesta, Near School of Achievers Opposite Satvam Greens

Mixed Development60 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/17647

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA10686/EX1/110326/311226

Shreeji Siesta — residential developmentGandhinagar · representative residential imagery

Paperwork score

Some gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusOngoing
Quarterly filings14 / 15
Recorded complaints0
Extensions1
Promoter projectsNone completed on record

Project at a glance

Developer
Shreeji Buildcon
Project type
Mixed Development
Total units
60
Project cost
₹26.57 Cr
Carpet area
6,412.9 sq m
Price band
₹19L – ₹0L
Carpet area per unit
24.86-119.25 sq m
Status
Ongoing
Filing extras — blocks, inventory lines, dates
  • Mixed Development — 60 units · carpet 6,412.89 sq m
  • Block UNIT-01
  • Declared start 2022-06-08 · completion 2027-04-30
  • Professionals on record: 0 architect(s), 0 engineer(s) · land not itemised

Location

23.1723° N, 72.6292° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

60

Total units

40

Booked (67%)

20

Unsold (33%)

67% booked · 33% unsold

Tower UNIT-0160 units

40 booked (67%) · 20 available (33%)

Flat-level inventory (60 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
SHOP-01UNIT-0170.33UNBOOKED
SHOP-02UNIT-0140.5BOOKED
SHOP-03UNIT-0135.16UNBOOKED
SHOP-04UNIT-0143.46BOOKED
SHOP-05UNIT-0134.86UNBOOKED
SHOP-06UNIT-0132.39UNBOOKED
SHOP-07UNIT-0126.92UNBOOKED
SHOP-08UNIT-0124.86UNBOOKED
A-101UNIT-01119.25UNBOOKED
A-102UNIT-01116.01UNBOOKED
A-103UNIT-01118.59UNBOOKED
A-104UNIT-01115.72UNBOOKED
A-201UNIT-01119.25BOOKED
A-202UNIT-01116.01BOOKED
A-203UNIT-01118.59UNBOOKED
A-204UNIT-01115.72BOOKED
A-301UNIT-01119.25UNBOOKED
A-302UNIT-01116.01BOOKED
A-303UNIT-01118.59BOOKED
A-304UNIT-01115.72UNBOOKED
A-401UNIT-01119.25BOOKED
A-402UNIT-01116.01BOOKED
A-403UNIT-01118.59BOOKED
A-404UNIT-01115.72UNBOOKED
A-501UNIT-01119.25BOOKED
A-502UNIT-01116.01UNBOOKED
A-503UNIT-01118.59BOOKED
A-504UNIT-01115.72BOOKED
A-601UNIT-01119.25BOOKED
A-602UNIT-01116.01BOOKED
A-603UNIT-01118.59BOOKED
A-604UNIT-01115.72BOOKED
A-701UNIT-01119.25BOOKED
A-702UNIT-01116.01BOOKED
A-703UNIT-01118.59BOOKED
A-704UNIT-01115.72BOOKED
A-801UNIT-01119.25BOOKED
A-802UNIT-01116.01BOOKED
A-803UNIT-01118.59BOOKED
A-804UNIT-01115.72BOOKED
A-901UNIT-01119.25BOOKED
A-902UNIT-01116.01BOOKED
A-903UNIT-01118.59BOOKED
A-904UNIT-01115.72BOOKED
A-1001UNIT-01119.25BOOKED
A-1002UNIT-01116.01BOOKED
A-1003UNIT-01118.59BOOKED
A-1004UNIT-01115.72BOOKED
A-1101UNIT-01119.25BOOKED
A-1102UNIT-01116.01UNBOOKED
A-1103UNIT-01118.59BOOKED
A-1104UNIT-01115.72BOOKED
A-1201UNIT-01119.25UNBOOKED
A-1202UNIT-01116.01UNBOOKED
A-1203UNIT-01118.59BOOKED
A-1204UNIT-01115.72BOOKED
A-1301UNIT-01119.25UNBOOKED
A-1302UNIT-01116.01UNBOOKED
A-1303UNIT-01118.59BOOKED
A-1304UNIT-01115.72BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%2023202420252026February 2023 — 36.66% builtMay 2023 — 40.64% builtAugust 2023 — 56.31% builtNovember 2023 — 66.41% builtJanuary 2024 — 54.35% builtApril 2024 — 58.65% builtJuly 2024 — 60.35% builtOctober 2024 — 54.67% builtOctober 2025 — 93.15% builtApril 2026 — 100% builtJuly 2026 — 100% built

11 quarterly returns · February 2023 (36.66%) to July 2026 (100%)

36.66%

Initial progress · February 2023

100%

Final progress · July 2026

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2022

    Registration

  2. 2023

    Annual Compliance

  3. 2024

    Annual Compliance

  4. 2025

    Annual Compliance

  5. 2026

    Extension

  6. Undated

    Annual Compliance

  7. 2026

    Snapshot reviewed

Full application ledger (7 rows)
  1. Registration — 2022-09-27 10:12:19.000000
  2. Extension — 2026-03-11 11:04:41
  3. Annual Compliance — 2023-11-17 19:51:54
  4. Annual Compliance — 2024-10-29 14:40:54
  5. Annual Compliance — 2025-12-10 20:06:17
  6. Annual Compliance — undated
  7. Annual Compliance — undated

Quarterly filing history

2023

Q-1 · Q-2 · Q-3 · Q-4

2024

Q-5 · Q-6 · Q-7 · Q-8

2025

Q-9 · Q-10 · Q-11 · Q-12

—

X-1

2026

X-2 · X-3

14 submitted · 1 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA10686/EX1/110326/311226 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Authority
Others
Covered area
671.88 sq m
Open area
1297.12 sq m
Land cost
₹3.93 Cr
Estimated cost
₹22.64 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GUJRERA/220808/013181
Covered parking
60 · 2740.56 sq m
Parking for sale
0

Escrow account

Bank
HDFC
Branch
INFOCITY,GANDHINAGAR
IFSC
HDFC0002497
Account
XXXX-4101
Deposited
₹4.16 Cr
Withdrawn
₹4.19 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
MONIKABA RAJENDRASINH JADEJA
Form-1 PDF
  • Block UNIT-01100%
Phase actual dates (1 block)
  • Block UNIT-01: excavation 2022-06-08 → slab

Filing PDFs

How is the paperwork score calculated?74 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    23 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    11 / 15

  • Delivery 2027-04-30 still ahead of 2026-09-26 -> 40/40
  • QPR filings 14/15 -> 23/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 1 extension -> 11/15

Confidence Medium: no completed project on the promoter record; 1 extension request on the ledger.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA10686/EX1/110326/311226

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.