Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Ongoing

German Seven Star

Seven Star, B/h German Greencity,

ResidentialGroup Housing68 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/17824

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA10758/A1R/270423

German Seven Star — residential developmentGandhinagar · representative residential imagery

Paperwork score

Complete record

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusOngoing
Quarterly filings12 / 14
Recorded complaints0
ExtensionsNone recorded
Promoter projects1 completed

Project at a glance

Developer
Venya Developers Llp
Project type
Residential / Group Housing
Total units
68
Project cost
₹66.37 Cr
Carpet area
11,572.7 sq m
Price band
₹0L – ₹0L
Carpet area per unit
155.78-278.24 sq m
Status
Ongoing
Filing extras — blocks, inventory lines, dates
  • Residential/Group Housing — 68 units · carpet 11,572.72 sq m
  • Block A
  • Block B
  • Block C
  • Block D
  • Declared start 2022-06-02 · completion 2026-12-31
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.1098° N, 72.6323° E

Filed plot outline · 6 corners
Open in Google Maps

Units & inventory

68

Total units

37

Booked (54%)

31

Unsold (46%)

54% booked · 46% unsold

Tower A18 units

14 booked (78%) · 4 available (22%)

Tower B16 units

7 booked (44%) · 9 available (56%)

Tower C18 units

11 booked (61%) · 7 available (39%)

Tower D16 units

5 booked (31%) · 11 available (69%)

Flat-level inventory (68 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
A-101A155.78UNBOOKED
A-102A155.78UNBOOKED
A-201A155.78BOOKED
A-202A155.78BOOKED
A-301A155.78BOOKED
A-302A155.78BOOKED
A-401A155.78BOOKED
A-402A155.78BOOKED
A-501A155.78BOOKED
A-502A155.78BOOKED
A-601A155.78BOOKED
A-602A155.78BOOKED
A-701A155.78UNBOOKED
A-702A155.78BOOKED
A-801A155.78UNBOOKED
A-802A155.78BOOKED
A-901A278.24BOOKED
A-902A278.24BOOKED
B-101B155.78UNBOOKED
B-102B155.78UNBOOKED
B-201B155.78UNBOOKED
B-202B155.78UNBOOKED
B-301B155.78BOOKED
B-302B155.78BOOKED
B-401B155.78BOOKED
B-402B155.78BOOKED
B-501B155.78BOOKED
B-502B155.78BOOKED
B-601B155.78UNBOOKED
B-602B155.78BOOKED
B-701B155.78UNBOOKED
B-702B155.78BOOKED
B-801B278.24UNBOOKED
B-802B278.24BOOKED
C-101C155.78UNBOOKED
C-102C155.78UNBOOKED
C-201C155.78BOOKED
C-202C155.78UNBOOKED
C-301C155.78BOOKED
C-302C155.78BOOKED
C-401C155.78BOOKED
C-402C155.78BOOKED
C-501C155.78BOOKED
C-502C155.78BOOKED
C-601C155.78BOOKED
C-602C155.78BOOKED
C-701C155.78BOOKED
C-702C155.78UNBOOKED
C-801C155.78BOOKED
C-802C155.78BOOKED
C-901C278.24UNBOOKED
C-902C278.24UNBOOKED
D-101D155.78UNBOOKED
D-102D155.78UNBOOKED
D-201D155.78UNBOOKED
D-202D155.78UNBOOKED
D-301D155.78UNBOOKED
D-302D155.78UNBOOKED
D-401D155.78BOOKED
D-402D155.78UNBOOKED
D-501D155.78BOOKED
D-502D155.78BOOKED
D-601D155.78BOOKED
D-602D155.78BOOKED
D-701D155.78BOOKED
D-702D155.78BOOKED
D-801D278.24BOOKED
D-802D278.24UNBOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%20232024202520262027March 2023 — 21.21% builtJune 2023 — 39.01% builtSeptember 2023 — 44.19% builtDecember 2023 — 55.94% builtApril 2024 — 59.85% builtJuly 2024 — 65.09% builtOctober 2024 — 66.16% builtOctober 2025 — 99.02% builtJanuary 2026 — 100% builtJanuary 2027 — 100% built

10 quarterly returns · March 2023 (21.21%) to January 2027 (100%)

21.21%

Initial progress · March 2023

100%

Final progress · January 2027

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2022

    Registration

  2. 2023

    Alteration · Annual Compliance · BCR

  3. 2024

    Annual Compliance

  4. 2025

    Annual Compliance

  5. Undated

    Annual Compliance

  6. 2026

    Snapshot reviewed

Full application ledger (8 rows)
  1. Registration — 2022-10-10 12:29:14.000000
  2. Alteration — 2023-04-27 13:21:11.000000
  3. Annual Compliance — 2023-11-17 19:57:05
  4. Annual Compliance — 2024-09-26 18:58:31
  5. Annual Compliance — 2025-10-24 16:30:38
  6. Annual Compliance — undated
  7. Annual Compliance — undated
  8. BCR — 2023-05-09 19:18:10.000000

Quarterly filing history

2023

Q-1 · Q-2 · Q-3

2024

Q-4 · Q-5 · Q-6 · Q-7

2025

Q-8 · Q-9 · Q-10 · Q-11

2026

Q-12

—

Q-13 · Q-14

12 submitted · 2 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA10758/A1R/270423 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Authority
Others
Covered area
1644.28 sq m
Open area
3635.72 sq m
Land cost
₹13.67 Cr
Estimated cost
₹52.7 Cr
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GUJRERA/220920/013383
Covered parking
200 · 4211.22 sq m
Parking for sale
0

Escrow account

Bank
ICICI Bank
Branch
Motera Branch
IFSC
ICIC0003245
Account
XXXX-0833
Deposited
₹3.04 Cr
Withdrawn
₹3.04 Cr
Closing
₹0.07 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
SIVAM SHYAMALKUMAR GANDHI
Firm
M/S Shivam Gandhi
Site visit
2026-01-19
Form-1 PDF
Open file
  • Block A100%
  • Block B100%
  • Block C100%
  • Block D100%
Phase actual dates (4 blocks)
  • Block D: excavation → slab
  • Block A: excavation → slab
  • Block C: excavation → slab
  • Block B: excavation → slab

Filing PDFs

Project team on record

  • Achal J Parikh · engineer
  • Nikhil Vasudev Boghawala · architect
How is the paperwork score calculated?86 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    21 / 25

  • Promoter track record

    10 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2026-12-31 still ahead of 2026-09-26 -> 40/40
  • QPR filings 12/14 -> 21/25
  • Promoter completed projects 1 -> 10/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: QPR filing rate 85.7% is below 90%.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA10758/A1R/270423

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.