Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Ongoing

Vrundavan Greens

SURVEY NO 382/P, FINAL PLOT NO 169

ResidentialGroup Housing48 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/17904

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA10926/141122

Vrundavan Greens — residential developmentGandhinagar · representative residential imagery

Paperwork score

Complete record

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusOngoing
Quarterly filings15 / 16
Recorded complaints0
ExtensionsNone recorded
Promoter projects1 completed

Project at a glance

Developer
Raj Developers
Project type
Residential / Group Housing
Total units
48
Project cost
₹37.98 Cr
Carpet area
8,241.3 sq m
Price band
₹60L – ₹0L
Carpet area per unit
162.36-201.31 sq m
Status
Ongoing
Filing extras — blocks, inventory lines, dates
  • Residential/Group Housing — 48 units · carpet 8,241.27 sq m
  • Block TYPE-A
  • Block TYPE-B
  • Block TYPE-C
  • Block TYPE-D
  • Block TYPE-E
  • Block TYPE-F
  • Block TYPE-G
  • Block TYPE-H
  • Declared start 2022-08-31 · completion 2027-01-30
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.2634° N, 72.6691° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

48

Total units

17

Booked (35%)

31

Unsold (65%)

35% booked · 65% unsold

Tower TYPE-A2 units

0 booked (0%) · 2 available (100%)

Tower TYPE-B37 units

13 booked (35%) · 24 available (65%)

Tower TYPE-C2 units

0 booked (0%) · 2 available (100%)

Tower TYPE-D1 units

1 booked (100%) · 0 available (0%)

Tower TYPE-E1 units

0 booked (0%) · 1 available (100%)

Tower TYPE-F2 units

1 booked (50%) · 1 available (50%)

Tower TYPE-G2 units

2 booked (100%) · 0 available (0%)

Tower TYPE-H1 units

0 booked (0%) · 1 available (100%)

Flat-level inventory (48 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
1TYPE-A168.25UNBOOKED
30TYPE-A168.25UNBOOKED
2TYPE-B171.06UNBOOKED
3TYPE-B171.06UNBOOKED
4TYPE-B171.06UNBOOKED
5TYPE-B171.06UNBOOKED
6TYPE-B171.06UNBOOKED
7TYPE-B171.06UNBOOKED
8TYPE-B171.06UNBOOKED
9TYPE-B171.06UNBOOKED
10TYPE-B171.06UNBOOKED
11TYPE-B171.06UNBOOKED
12TYPE-B171.06UNBOOKED
13TYPE-B171.06UNBOOKED
14TYPE-B171.06UNBOOKED
17TYPE-B171.06UNBOOKED
18TYPE-B171.06UNBOOKED
19TYPE-B171.06UNBOOKED
20TYPE-B171.06UNBOOKED
21TYPE-B171.06BOOKED
22TYPE-B171.06BOOKED
23TYPE-B171.06BOOKED
24TYPE-B171.06BOOKED
25TYPE-B171.06BOOKED
26TYPE-B171.06BOOKED
27TYPE-B171.06BOOKED
28TYPE-B171.06UNBOOKED
29TYPE-B171.06BOOKED
35TYPE-B171.06UNBOOKED
36TYPE-B171.06UNBOOKED
37TYPE-B171.06UNBOOKED
38TYPE-B171.06UNBOOKED
39TYPE-B171.06UNBOOKED
41TYPE-B171.06UNBOOKED
42TYPE-B171.06BOOKED
43TYPE-B171.06BOOKED
44TYPE-B171.06BOOKED
45TYPE-B171.06BOOKED
46TYPE-B171.06BOOKED
15TYPE-C188.11UNBOOKED
40TYPE-C188.11UNBOOKED
16TYPE-D162.4BOOKED
31TYPE-E201.31UNBOOKED
32TYPE-F163.48000000000002UNBOOKED
33TYPE-F163.48000000000002BOOKED
34TYPE-G173.15BOOKED
47TYPE-G173.15BOOKED
48TYPE-H162.36UNBOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 99.6375%
0%25%50%75%100%2023202420252026April 2023 — 4.78% builtJuly 2023 — 6.19% builtOctober 2023 — 17.13% builtJanuary 2024 — 22.37% builtApril 2024 — 26.16% builtJuly 2024 — 30.54% builtOctober 2024 — 30.54% builtOctober 2025 — 66.84492499999999% builtJanuary 2026 — 71.62015000000001% builtApril 2026 — 78.88265% builtJuly 2026 — 99.6375% built

11 quarterly returns · April 2023 (4.78%) to July 2026 (99.6375%)

4.78%

Initial progress · April 2023

99.6375%

Final progress · July 2026

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2022

    Registration

  2. 2023

    Annual Compliance

  3. 2024

    Annual Compliance

  4. 2025

    Annual Compliance

  5. Undated

    Annual Compliance

  6. 2026

    Snapshot reviewed

Full application ledger (6 rows)
  1. Registration — 2022-11-14 14:52:25.000000
  2. Annual Compliance — 2023-11-17 19:59:28
  3. Annual Compliance — 2024-10-24 12:56:20
  4. Annual Compliance — 2025-10-28 11:35:36
  5. Annual Compliance — undated
  6. Annual Compliance — undated

Quarterly filing history

2023

Q-1 · Q-2 · Q-3

2024

Q-4 · Q-5 · Q-6 · Q-7

2025

Q-8 · Q-9 · Q-10 · Q-11 · BWA-1

2026

Q-12 · Q-13 · Q-14

—

BWA-2

15 submitted · 1 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA10926/141122 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Authority
Others
Covered area
3763.43 sq m
Open area
4347.53 sq m
Land cost
₹6.63 Cr
Estimated cost
₹31.34 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GUJRERA/221006/013471
Covered parking
48
Parking for sale
0

Escrow account

Bank
STATE BANK OF INDIA
Branch
INFOCITY, GANDHINAGAR UNIT GWGF/2, GROUND FLOOR INFOCITY, GANDHINAGAR GUJARAT
IFSC
SBIN0012700
Account
XXXX-6703
Deposited
₹2.57 Cr
Withdrawn
₹2.07 Cr
Closing
₹0.49 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
HIMANSHUKUMAR RASIKLAL RAVAL
Form-1 PDF
  • Block TYPE-D100%
  • Block TYPE-E98.88888888888889%
  • Block TYPE-F100%
  • Block TYPE-G100%
  • Block TYPE-H100%
  • Block TYPE-A99%
  • Block TYPE-B100%
  • Block TYPE-C98.88888888888889%
Phase actual dates (8 blocks)
  • Block TYPE-D: excavation 2022-08-31 → slab
  • Block TYPE-E: excavation 2022-08-31 → slab —
  • Block TYPE-F: excavation 2022-08-31 → slab —
  • Block TYPE-G: excavation 2022-08-31 → slab
  • Block TYPE-H: excavation 2022-08-31 → slab —
  • Block TYPE-A: excavation 2022-08-31 → slab
  • Block TYPE-B: excavation 2022-08-31 → slab
  • Block TYPE-C: excavation 2022-08-31 → slab

Filing PDFs

Project team on record

  • CHINATN H MEHTA · engineer
  • HIMANSHU RAVAL ARCHITECTS · architect
How is the paperwork score calculated?88 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    23 / 25

  • Promoter track record

    10 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2027-01-30 still ahead of 2026-09-26 -> 40/40
  • QPR filings 15/16 -> 23/25
  • Promoter completed projects 1 -> 10/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA10926/141122

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources