Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Delivered

Maruti Icon

Maruti Icon, Bh. Kunj Heights, TP-13,

Mixed Development81 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/18025

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA10974/281122

Maruti Icon — residential developmentGandhinagar · representative residential imagery

Paperwork score

Complete record

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings13 / 13
Recorded complaints0
ExtensionsNone recorded
Promoter projects1 completed

Project at a glance

Developer
Bhoomi Developers
Project type
Mixed Development
Total units
81
Project cost
₹20.53 Cr
Carpet area
5,341.5 sq m
Price band
₹10L – ₹0L
Carpet area per unit
10.48-79.91 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Mixed Development — 81 units · carpet 5,341.54 sq m
  • Block A
  • Block B
  • Declared start 2022-09-15 · completion 2026-03-31
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.2207° N, 72.6133° E

Filed plot outline · 7 corners
Open in Google Maps

Units & inventory

81

Total units

30

Booked (37%)

51

Unsold (63%)

37% booked · 63% unsold

Tower A37 units

21 booked (57%) · 16 available (43%)

Tower B44 units

9 booked (20%) · 35 available (80%)

Flat-level inventory (81 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
1A25.87UNBOOKED
2A27.91UNBOOKED
3A27.91UNBOOKED
4A33.4UNBOOKED
5A10.48BOOKED
6A25.25BOOKED
7A27.91UNBOOKED
8A24.91UNBOOKED
9A25.86UNBOOKED
101A79.91BOOKED
102A79.91BOOKED
103A79.91BOOKED
104A79.91BOOKED
201A79.91BOOKED
202A79.91BOOKED
203A79.91BOOKED
204A79.91BOOKED
301A79.91BOOKED
302A79.91BOOKED
303A79.91BOOKED
304A79.91BOOKED
401A79.91BOOKED
402A79.91BOOKED
403A79.91BOOKED
404A79.91BOOKED
501A79.91BOOKED
502A79.91BOOKED
503A79.91BOOKED
504A79.91UNBOOKED
601A79.91BOOKED
602A79.91BOOKED
603A79.91BOOKED
604A79.91BOOKED
701A79.91BOOKED
702A79.91BOOKED
703A79.91BOOKED
704A79.91BOOKED
1B65.57UNBOOKED
2B64.57UNBOOKED
101B65.89BOOKED
102B65.57BOOKED
103B64.57BOOKED
104B64.57UNBOOKED
105B65.57UNBOOKED
106B65.89BOOKED
201B65.89BOOKED
202B65.57BOOKED
203B64.57UNBOOKED
204B64.57BOOKED
205B65.57BOOKED
206B65.89UNBOOKED
301B65.89BOOKED
302B65.57UNBOOKED
303B64.57UNBOOKED
304B64.57BOOKED
305B65.57BOOKED
306B65.89UNBOOKED
401B65.89BOOKED
402B65.57BOOKED
403B64.57BOOKED
404B64.57BOOKED
405B65.57BOOKED
406B65.89UNBOOKED
501B65.89BOOKED
502B65.57UNBOOKED
503B64.57BOOKED
504B64.57BOOKED
505B65.57BOOKED
506B65.89UNBOOKED
601B65.89BOOKED
602B65.57UNBOOKED
603B64.57UNBOOKED
604B64.57UNBOOKED
605B65.57BOOKED
606B65.89BOOKED
701B65.89UNBOOKED
702B65.57UNBOOKED
703B64.57UNBOOKED
704B64.57UNBOOKED
705B65.57UNBOOKED
706B65.89BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%2023202420252026April 2023 — 15.3% builtJuly 2023 — 26.14% builtOctober 2023 — 42.71% builtJanuary 2024 — 56.95% builtApril 2024 — 58.49% builtJuly 2024 — 61.57% builtOctober 2024 — 64.15% builtOctober 2025 — 93.86240000000002% builtJanuary 2026 — 98.9% builtApril 2026 — 100% built

10 quarterly returns · April 2023 (15.3%) to April 2026 (100%)

15.3%

Initial progress · April 2023

100%

Final progress · April 2026

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2022

    Registration

  2. 2023

    Annual Compliance · BCR

  3. 2024

    Annual Compliance

  4. 2025

    Annual Compliance

  5. Undated

    Annual Compliance

  6. 2026

    Snapshot reviewed

Full application ledger (6 rows)
  1. Registration — 2022-11-28 11:56:16.000000
  2. Annual Compliance — 2023-11-17 20:02:47
  3. Annual Compliance — 2024-10-04 16:01:55
  4. Annual Compliance — 2025-12-06 19:07:15
  5. Annual Compliance — undated
  6. BCR — 2023-03-28 17:41:58.000000

Quarterly filing history

2023

Q-1 · Q-2 · Q-3

2024

Q-4 · Q-5 · Q-6 · Q-7

2025

Q-8 · Q-9 · Q-10 · Q-11

2026

Q-12 · Q-E

13 submitted · 0 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA10974/281122 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Authority
Others
Covered area
984.55 sq m
Open area
1334.45 sq m
Land cost
₹1.27 Cr
Estimated cost
₹19.26 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GUJRERA/221107/013616
Covered parking
2 · 1577.5 sq m
Parking for sale
1

Escrow account

Bank
HDFC
Branch
Chandkheda, Ahmedabad
IFSC
HDFC0001083
Account
XXXX-6841
Deposited
₹0.78 Cr
Withdrawn
₹0.78 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
BHAUMIKKUMAR CHANDRAVADANBHAI DONGA
Firm
ANTRIT ARCHITECTS
Site visit
2026-03-10
Form-1 PDF
Open file
  • Block A100%
  • Block B100%
Phase actual dates (2 blocks)
  • Block A: excavation → slab
  • Block B: excavation → slab

Filing PDFs

Project team on record

  • Dahyabhai Hargovandas Patel · engineer
  • Vikram Sharma Associates · architect
How is the paperwork score calculated?90 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    25 / 25

  • Promoter track record

    10 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2026-03-31 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 13/13 -> 25/25
  • Promoter completed projects 1 -> 10/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA10974/281122

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.