Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Ongoing

River View 77

FP 304, Opp. Mahakali Parlour

Mixed Development85 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/18047

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA11001/031222

River View 77 — residential developmentGandhinagar · representative residential imagery

Paperwork score

Some gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusOngoing
Quarterly filings12 / 15
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Katha Realty
Project type
Mixed Development
Total units
85
Project cost
₹18.14 Cr
Carpet area
4,547.8 sq m
Price band
₹27L – ₹0L
Carpet area per unit
22.55-59.66 sq m
Status
Ongoing
Filing extras — blocks, inventory lines, dates
  • Mixed Development — 85 units · carpet 4,547.83 sq m
  • Block A
  • Declared start 2022-08-01 · completion 2026-12-31
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.1652° N, 72.6610° E

Filed plot outline · 7 corners
Open in Google Maps

Units & inventory

85

Total units

44

Booked (52%)

41

Unsold (48%)

52% booked · 48% unsold

Tower A85 units

44 booked (52%) · 41 available (48%)

Flat-level inventory (85 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
A-101A54.47BOOKED
A-102A59.66BOOKED
A-103A54.47UNBOOKED
A-104A54.47BOOKED
A-105A59.66UNBOOKED
A-106A54.47BOOKED
A-201A54.47BOOKED
A-202A59.66UNBOOKED
A-203A54.47UNBOOKED
A-204A54.47UNBOOKED
A-205A59.66BOOKED
A-206A54.47UNBOOKED
A-301A54.47BOOKED
A-302A59.66BOOKED
A-303A54.47BOOKED
A-304A54.47UNBOOKED
A-305A59.66BOOKED
A-306A54.47BOOKED
A-401A54.47BOOKED
A-402A59.66BOOKED
A-403A54.47UNBOOKED
A-404A54.47UNBOOKED
A-405A59.66BOOKED
A-406A54.47BOOKED
A-501A54.47BOOKED
A-502A59.66BOOKED
A-503A54.47UNBOOKED
A-504A54.47UNBOOKED
A-505A59.66BOOKED
A-506A54.47UNBOOKED
A-601A54.47BOOKED
A-602A59.66BOOKED
A-603A54.47UNBOOKED
A-604A54.47BOOKED
A-605A59.66BOOKED
A-606A54.47UNBOOKED
A-701A54.47UNBOOKED
A-702A59.66BOOKED
A-703A54.47UNBOOKED
A-704A54.47BOOKED
A-705A59.66BOOKED
A-706A54.47UNBOOKED
A-801A54.47BOOKED
A-802A59.66BOOKED
A-803A54.47BOOKED
A-804A54.47BOOKED
A-805A59.66UNBOOKED
A-806A54.47BOOKED
A-901A54.47UNBOOKED
A-902A59.66BOOKED
A-903A54.47UNBOOKED
A-904A54.47BOOKED
A-905A59.66UNBOOKED
A-906A54.47BOOKED
A-1001A54.47UNBOOKED
A-1002A59.66BOOKED
A-1003A54.47UNBOOKED
A-1004A54.47BOOKED
A-1005A59.66BOOKED
A-1006A54.47BOOKED
A-1101A54.47UNBOOKED
A-1102A59.66BOOKED
A-1103A54.47BOOKED
A-1104A54.47UNBOOKED
A-1105A59.66BOOKED
A-1106A54.47BOOKED
A-1201A54.47BOOKED
A-1202A59.66UNBOOKED
A-1203A54.47BOOKED
A-1204A54.47BOOKED
A-1205A59.66BOOKED
A-1206A54.47BOOKED
A-1301A54.83UNBOOKED
A-1302A54.47BOOKED
A-1303A59.66UNBOOKED
A-1304A54.47BOOKED
A-1305A54.83UNBOOKED
1A27.41UNBOOKED
2A26.75UNBOOKED
3A42.78UNBOOKED
4A25.94UNBOOKED
5A25.33BOOKED
6A27.94BOOKED
7A24.47UNBOOKED
8A22.55BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%2023202420252027May 2023 — 25.5% builtAugust 2023 — 35.7% builtNovember 2023 — 38.14% builtJanuary 2024 — 57.38% builtApril 2024 — 59.02% builtJuly 2024 — 64.28% builtOctober 2024 — 65.88% builtOctober 2025 — 90% builtJanuary 2027 — 100% built

9 quarterly returns · May 2023 (25.5%) to January 2027 (100%)

25.5%

Initial progress · May 2023

100%

Final progress · January 2027

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2022

    Registration

  2. 2023

    Annual Compliance

  3. 2025

    Annual Compliance

  4. Undated

    Annual Compliance

  5. 2026

    Snapshot reviewed

Full application ledger (6 rows)
  1. Registration — 2022-12-03 12:15:59.000000
  2. Annual Compliance — 2023-11-17 20:03:25
  3. Annual Compliance — 2025-01-29 13:19:00
  4. Annual Compliance — 2025-10-23 09:34:08
  5. Annual Compliance — undated
  6. Annual Compliance — undated

Quarterly filing history

2023

Q-1 · Q-2 · Q-3

2024

Q-4 · Q-5 · Q-6 · Q-7

2025

Q-8 · Q-9 · Q-10 · Q-11 · BWA-1

—

Q-12 · Q-13 · Q-14

12 submitted · 3 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA11001/031222 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Authority
Others
Covered area
650.26 sq m
Open area
1257.74 sq m
Land cost
₹1.69 Cr
Estimated cost
₹16.45 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GUJRERA/221105/013639
Covered parking
1 · 1166.96 sq m
Parking for sale
1

Escrow account

Bank
HDFC
Branch
Raysan Branch
IFSC
HDFC0005065
Account
XXXX-9401
Deposited
₹1.22 Cr
Withdrawn
₹1.15 Cr
Closing
₹0.06 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
NIRAV NARESHBHAI NAKRANI
Firm
NIRAV NARESHBHAI NAKRANI
Site visit
2025-12-31
Form-1 PDF
Open file
  • Block A100%
Phase actual dates (1 block)
  • Block A: excavation → slab

Filing PDFs

Project team on record

  • Jitesh Jagyasi · engineer
  • Kalpan Shah · architect
How is the paperwork score calculated?75 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    20 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2026-12-31 still ahead of 2026-09-26 -> 40/40
  • QPR filings 12/15 -> 20/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: QPR filing rate 80.0% is below 90%; no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA11001/031222

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.