Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Ongoing

Shivalay Haritage

SHIVALAY HARITAGE, FP NO 149, B/H PANCHVATI FARM,

ResidentialGroup Housing57 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/18602

Filing PR/GJ/GANDHINAGAR/DEHGAM/AUDA/RAA11635/210423

Shivalay Haritage — residential developmentGandhinagar · representative residential imagery

Paperwork score

Some gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusOngoing
Quarterly filings8 / 13
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Shree Sai Corporation
Project type
Residential / Group Housing
Total units
57
Project cost
₹15.78 Cr
Carpet area
7,262.2 sq m
Price band
₹26L – ₹0L
Carpet area per unit
116.12-147.35 sq m
Status
Ongoing
Filing extras — blocks, inventory lines, dates
  • Residential/Group Housing — 57 units · carpet 7,262.22 sq m
  • Block A
  • Block A E
  • Block B C
  • Block C
  • Block D
  • Block E
  • Declared start 2023-01-13 · completion 2026-12-31
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.1539° N, 72.7995° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

57

Total units

36

Booked (63%)

21

Unsold (37%)

63% booked · 37% unsold

Tower A2 units

2 booked (100%) · 0 available (0%)

Tower A E24 units

14 booked (58%) · 10 available (42%)

Tower B C12 units

11 booked (92%) · 1 available (8%)

Tower C1 units

1 booked (100%) · 0 available (0%)

Tower D16 units

7 booked (44%) · 9 available (56%)

Tower E2 units

1 booked (50%) · 1 available (50%)

Flat-level inventory (57 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
5A116.12BOOKED
6A117.37BOOKED
1A E118.44BOOKED
2A E117.37BOOKED
3A E117.37BOOKED
4A E117.37BOOKED
7A E117.37BOOKED
8A E117.37BOOKED
9A E117.37BOOKED
10A E118.44BOOKED
40A E118.44BOOKED
41A E117.37UNBOOKED
42A E117.37BOOKED
43A E117.37BOOKED
44A E117.37BOOKED
45A E117.37BOOKED
46A E117.37UNBOOKED
47A E117.37BOOKED
50A E117.37UNBOOKED
51A E117.37UNBOOKED
52A E117.37UNBOOKED
53A E117.37UNBOOKED
54A E117.37UNBOOKED
55A E117.37UNBOOKED
56A E117.37BOOKED
57A E118.44UNBOOKED
11B C147.35BOOKED
12B C146.64BOOKED
13B C146.63BOOKED
14B C146.64BOOKED
15B C146.63BOOKED
16B C147.3BOOKED
17B C147.35BOOKED
19B C146.64BOOKED
20B C146.63UNBOOKED
21B C146.64BOOKED
22B C146.63BOOKED
23B C147.3BOOKED
18C146.26BOOKED
24D129.09BOOKED
25D129.09UNBOOKED
26D129.09UNBOOKED
27D129.09UNBOOKED
28D129.09UNBOOKED
29D129.09UNBOOKED
30D129.09BOOKED
31D129.09UNBOOKED
32D129.09BOOKED
33D129.09BOOKED
34D129.09BOOKED
35D129.09UNBOOKED
36D129.09UNBOOKED
37D129.09UNBOOKED
38D129.09BOOKED
39D129.09BOOKED
48E117.37BOOKED
49E116.12BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 82%
0%25%50%75%100%202320242027September 2023 — 6.51% builtDecember 2023 — 50.31% builtApril 2024 — 58.28% builtJuly 2024 — 60.69% builtOctober 2024 — 61.9% builtJanuary 2027 — 82% built

6 quarterly returns · September 2023 (6.51%) to January 2027 (82%)

6.51%

Initial progress · September 2023

82%

Final progress · January 2027

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2023

    Registration

  2. 2024

    Annual Compliance

  3. 2025

    Annual Compliance

  4. Undated

    Annual Compliance

  5. 2026

    Snapshot reviewed

Full application ledger (5 rows)
  1. Registration — 2023-04-21 12:03:07.000000
  2. Annual Compliance — 2024-10-24 20:50:30
  3. Annual Compliance — 2025-10-17 20:33:37
  4. Annual Compliance — undated
  5. Annual Compliance — undated

Quarterly filing history

2023

Q-1

2024

Q-2 · Q-3 · Q-4 · Q-5

2025

Q-6 · Q-7 · Q-8

—

Q-9 · Q-10 · Q-11 · Q-12 · BWA-1

8 submitted · 5 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/DEHGAM/AUDA/RAA11635/210423 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Authority
AUDA
Covered area
3576.2 sq m
Open area
3465.8 sq m
Land cost
₹1.93 Cr
Estimated cost
₹13.85 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/DEHGAM/GUJRERA/230309/014238R1
Parking for sale
0

Escrow account

Bank
ICICI Bank
Branch
DEHGAM, AHMEDABAD
IFSC
ICIC0001718
Account
XXXX-4038
Deposited
₹0.91 Cr
Withdrawn
₹0.8 Cr
Closing
₹0.19 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
PANKTI BHADRESHBHAI DHOLAKIYA
Firm
PANKTI BHADRESHBHAI DHOLAKIYA
Site visit
2025-09-30
Form-1 PDF
Open file
  • Block A80%
  • Block A E80%
  • Block B C80%
  • Block C80%
  • Block D80%
  • Block E80%
Phase actual dates (6 blocks)
  • Block A: excavation → slab
  • Block B C: excavation → slab
  • Block A E: excavation → slab
  • Block D: excavation → slab
  • Block C: excavation → slab
  • Block E: excavation → slab

Filing PDFs

Project team on record

  • ROHIT B PRAJAPATI · engineer
  • PANKTI B DHOLAKIA · architect
How is the paperwork score calculated?70 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    15 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2026-12-31 still ahead of 2026-09-26 -> 40/40
  • QPR filings 8/13 -> 15/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: QPR filing rate 61.5% is below 90%; no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/DEHGAM/AUDA/RAA11635/210423

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.