Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Ongoing

Arizona Prime

R.S.NO.1543/1,MANSA

Commercial62 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/18604

Filing PR/GJ/GANDHINAGAR/MANSA/Others/CAA12210/310823

Arizona Prime — residential developmentGandhinagar · representative residential imagery

Paperwork score

Complete record

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusOngoing
Quarterly filings9 / 12
Recorded complaints0
ExtensionsNone recorded
Promoter projects1 completed

Project at a glance

Developer
Ananta Construction
Project type
Commercial
Total units
62
Project cost
₹5.72 Cr
Carpet area
2,235.5 sq m
Price band
₹9L – ₹0L
Carpet area per unit
21.29-227.53 sq m
Status
Ongoing
Filing extras — blocks, inventory lines, dates
  • Commercial — 62 units · carpet 2,235.47 sq m
  • Block A
  • Declared start 2022-12-14 · completion 2027-03-31
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.4178° N, 72.6501° E

Filed plot outline · 6 corners
Open in Google Maps

Units & inventory

62

Total units

35

Booked (56%)

27

Unsold (44%)

56% booked · 44% unsold

Tower A62 units

35 booked (56%) · 27 available (44%)

Flat-level inventory (62 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
1A26.62UNBOOKED
2A27.12UNBOOKED
3A27.62BOOKED
4A27.62UNBOOKED
5A27.62BOOKED
6A27.62BOOKED
7A27.62BOOKED
8A27.62BOOKED
9A27.62BOOKED
10A27.11BOOKED
11A27.11BOOKED
12A27.53BOOKED
13A27.62BOOKED
14A27.62BOOKED
15A27.62BOOKED
16A27.62BOOKED
17A27.62BOOKED
18A27.62BOOKED
19A27.62BOOKED
20A27.62BOOKED
21A31.83BOOKED
22A31.69BOOKED
23A27.62BOOKED
24A27.62BOOKED
25A27.62BOOKED
26A27.62BOOKED
27A27.62BOOKED
28A27.62BOOKED
29A27.62BOOKED
30A27.62BOOKED
31A26.15BOOKED
101A27.34UNBOOKED
102A21.36UNBOOKED
103A21.36UNBOOKED
104A21.36UNBOOKED
105A21.36UNBOOKED
106A21.36UNBOOKED
107A21.36UNBOOKED
108A25.5UNBOOKED
109A25.5UNBOOKED
110A21.29UNBOOKED
111A21.36UNBOOKED
112A21.36UNBOOKED
113A21.36UNBOOKED
114A21.36UNBOOKED
115A21.36UNBOOKED
116A21.36UNBOOKED
117A21.36UNBOOKED
118A21.36UNBOOKED
119A25.52UNBOOKED
120A25.5BOOKED
121A21.36BOOKED
122A21.36BOOKED
123A21.36UNBOOKED
124A21.36UNBOOKED
125A21.36UNBOOKED
126A21.36UNBOOKED
127A27.34UNBOOKED
201A227.53BOOKED
202A157.4BOOKED
203A157.4BOOKED
204A227.53BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%2024202520262027January 2024 — 39.58% builtApril 2024 — 78.39% builtOctober 2024 — 81.22% builtOctober 2025 — 88% builtJanuary 2026 — 88% builtApril 2027 — 100% built

6 quarterly returns · January 2024 (39.58%) to April 2027 (100%)

39.58%

Initial progress · January 2024

100%

Final progress · April 2027

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2023

    Registration

  2. 2024

    Annual Compliance

  3. 2025

    Annual Compliance

  4. Undated

    Annual Compliance

  5. 2026

    Snapshot reviewed

Full application ledger (5 rows)
  1. Registration — 2023-08-31 13:22:17.000000
  2. Annual Compliance — 2024-10-30 16:17:07
  3. Annual Compliance — 2025-11-01 12:04:56
  4. Annual Compliance — undated
  5. Annual Compliance — undated

Quarterly filing history

2024

Q-1 · Q-2 · Q-3 · Q-4

2025

Q-5 · Q-6 · Q-7 · Q-8

2026

Q-9

—

Q-10 · Q-11 · BWA-1

9 submitted · 3 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/MANSA/Others/CAA12210/310823 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Authority
Others
Covered area
1018.44 sq m
Open area
2015.77 sq m
Land cost
₹3.95 Cr
Estimated cost
₹1.77 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/MANSA/GUJRERA/230615/014309
Covered parking
65 · 1313.93 sq m
Parking for sale
0

Escrow account

Bank
Mehsana Urban Co-Operative Bank Ltd.
Branch
MANSA
IFSC
MSNU0000011
Account
XXXX-1118
Status
APPROVED

Inspection phases (Form-1)

Architect
BHAUMIKKUMAR CHANDRAVADANBHAI DONGA
Firm
ANTRIT ARCHITECTS
Site visit
2026-01-20
Form-1 PDF
Open file
  • Block A100%
Phase actual dates (1 block)
  • Block A: excavation → slab

Filing PDFs

Project team on record

  • Krupal Thakar · engineer
  • Bhaumikkumar C. Donga · architect
How is the paperwork score calculated?84 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    19 / 25

  • Promoter track record

    10 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2027-03-31 still ahead of 2026-09-26 -> 40/40
  • QPR filings 9/12 -> 19/25
  • Promoter completed projects 1 -> 10/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: QPR filing rate 75.0% is below 90%.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/MANSA/Others/CAA12210/310823

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.