Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Ongoing

Royal Relexa Gold

Raysan Petrol Pump, PDPU Road,

ResidentialGroup Housing59 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/19296

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA12329/290923

Royal Relexa Gold — residential developmentGandhinagar · representative residential imagery

Paperwork score

Complete record

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusOngoing
Quarterly filings12 / 12
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
R R Buildcon
Project type
Residential / Group Housing
Total units
59
Project cost
₹44.7 Cr
Carpet area
9,287.1 sq m
Price band
₹65L – ₹0L
Carpet area per unit
122.54-261.2 sq m
Status
Ongoing
Filing extras — blocks, inventory lines, dates
  • Residential/Group Housing — 59 units · carpet 9,287.13 sq m
  • Block A
  • Block B
  • Declared start 2023-04-29 · completion 2028-09-30
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.1656° N, 72.6436° E

Filed plot outline · 4 corners
Open in Google Maps

Units & inventory

59

Total units

22

Booked (37%)

37

Unsold (63%)

37% booked · 63% unsold

Tower A24 units

10 booked (42%) · 14 available (58%)

Tower B35 units

12 booked (34%) · 23 available (66%)

Flat-level inventory (59 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
101A184.69UNBOOKED
102A184.69UNBOOKED
201A184.69UNBOOKED
202A184.69UNBOOKED
301A184.69UNBOOKED
302A184.69UNBOOKED
401A184.69UNBOOKED
402A184.69UNBOOKED
501A184.69BOOKED
502A184.69BOOKED
601A184.69UNBOOKED
602A184.69BOOKED
701A184.69BOOKED
702A184.69BOOKED
801A184.69UNBOOKED
802A184.69BOOKED
901A184.69BOOKED
902A184.69BOOKED
1001A184.69BOOKED
1002A184.69UNBOOKED
1101A184.69UNBOOKED
1102A184.69UNBOOKED
1201A261.2BOOKED
1202A261.2UNBOOKED
101B137.98UNBOOKED
102B126.44UNBOOKED
103B122.54UNBOOKED
201B137.98UNBOOKED
202B126.44BOOKED
203B122.54BOOKED
301B137.98UNBOOKED
302B126.44BOOKED
303B122.54UNBOOKED
401B137.98UNBOOKED
402B126.44UNBOOKED
403B122.54UNBOOKED
501B137.98UNBOOKED
502B126.44BOOKED
503B122.54UNBOOKED
601B137.98BOOKED
602B126.44BOOKED
603B122.54UNBOOKED
701B137.98UNBOOKED
702B126.44BOOKED
703B122.54UNBOOKED
801B137.98BOOKED
802B126.44UNBOOKED
803B122.54UNBOOKED
901B137.98UNBOOKED
902B126.44UNBOOKED
903B122.54UNBOOKED
1001B137.98BOOKED
1002B126.44UNBOOKED
1003B122.54UNBOOKED
1101B137.98BOOKED
1102B126.44UNBOOKED
1103B122.54BOOKED
1201B219.34BOOKED
1202B225.65UNBOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 57.95982222222223%
0%25%50%75%100%202420252026January 2024 — 28.17% builtApril 2024 — 31.52% builtJuly 2024 — 35.05% builtOctober 2024 — 41.28% builtOctober 2025 — 48.30117777777778% builtJanuary 2026 — 52.806622222222224% builtApril 2026 — 55.10482222222222% builtJuly 2026 — 57.95982222222223% built

8 quarterly returns · January 2024 (28.17%) to July 2026 (57.95982222222223%)

28.17%

Initial progress · January 2024

57.95982222222223%

Final progress · July 2026

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2023

    Registration

  2. 2024

    Annual Compliance · LEGAL_PCWF · BCR

  3. 2025

    Annual Compliance

  4. Undated

    Annual Compliance · BCR

  5. 2026

    Snapshot reviewed

Full application ledger (10 rows)
  1. Registration — 2023-09-29 12:54:19.000000
  2. Annual Compliance — 2024-10-19 18:15:33
  3. Annual Compliance — 2025-11-15 13:23:05
  4. Annual Compliance — undated
  5. Annual Compliance — undated
  6. Annual Compliance — undated
  7. LEGAL_PCWF — 2024-06-09 14:29:58
  8. LEGAL_PCWF — 2024-08-29 12:23:26
  9. BCR — undated
  10. BCR — 2024-04-22 14:03:41.021000

Quarterly filing history

2024

Q-1 · Q-2 · Q-3 · Q-4

2025

Q-5 · Q-6 · Q-7 · Q-8 · BWA-1

2026

Q-9 · Q-10 · Q-11

12 submitted · 0 missing

Documents on file

40 documents

Missing from this record: Registration certificate, Encumbrance certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA12329/290923 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Authority
Others
Covered area
978.32 sq m
Open area
1684.13 sq m
Land cost
₹10.14 Cr
Estimated cost
₹34.56 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GUJRERA/230701/015009
Covered parking
139 · 2776.98 sq m
Parking for sale
58

Escrow account

Bank
HDFC BANK
Branch
NIKOL
IFSC
HDFC0009394
Account
XXXX-6097
Deposited
₹5.05 Cr
Withdrawn
₹5.05 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
URVASHI LALITKUMAR TULI
Form-1 PDF
  • Block A57.82933333333334%
  • Block B63.80977777777778%
Phase actual dates (2 blocks)
  • Block A: excavation 2023-04-29 → slab
  • Block B: excavation 2023-04-29 → slab

Filing PDFs

Project team on record

  • RONAK S GAJJAR · engineer
  • CHIRAGKUMAR P. NAKRANI · architect
How is the paperwork score calculated?80 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    25 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2028-09-30 still ahead of 2026-09-26 -> 40/40
  • QPR filings 12/12 -> 25/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA12329/290923

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.