Ananta Happinest
F.P.No.1122/2
Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/MAA12326/A1M/130524/311228
Paperwork score
Complete record
A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.
Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.
Project at a glance
- Developer
- Ab Realty
- Project type
- Mixed Development
- Total units
- 127
- Project cost
- ₹28.79 Cr
- Carpet area
- 8,198.6 sq m
- Price band
- ₹14L – ₹0L
- Carpet area per unit
- 17.52-78.52 sq m
- Status
- Ongoing
Filing extras — blocks, inventory lines, dates
- Mixed Development — 127 units · carpet 8,198.62 sq m
- Block A
- Block B+C
- Declared start 2023-06-01 · completion 2029-04-30
- Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised
Location
23.2617° N, 72.6390° E
Units & inventory
127
Total units
39
Booked (31%)
88
Unsold (69%)
31% booked · 69% unsold
22 booked (43%) · 29 available (57%)
17 booked (22%) · 59 available (78%)
Flat-level inventory (127 units)
| Flat | Block | Carpet m² | Status |
|---|---|---|---|
| A 01 | A | 22.05 | BOOKED |
| A 02 | A | 22.05 | UNBOOKED |
| A 03 | A | 24.28 | BOOKED |
| A 04 | A | 20.29 | BOOKED |
| A 05 | A | 17.52 | BOOKED |
| A 06 | A | 20.29 | BOOKED |
| A 07 | A | 24.28 | UNBOOKED |
| A 08 | A | 22.05 | UNBOOKED |
| A 09 | A | 22.05 | UNBOOKED |
| A 101 | A | 78.52 | BOOKED |
| A 102 | A | 78.52 | BOOKED |
| A 103 | A | 78.52 | BOOKED |
| A 104 | A | 78.52 | BOOKED |
| A 201 | A | 78.52 | BOOKED |
| A 202 | A | 78.52 | BOOKED |
| A 203 | A | 78.52 | UNBOOKED |
| A 204 | A | 78.52 | BOOKED |
| A 301 | A | 78.52 | BOOKED |
| A 302 | A | 78.52 | BOOKED |
| A 303 | A | 78.52 | BOOKED |
| A 304 | A | 78.52 | BOOKED |
| A 401 | A | 78.52 | BOOKED |
| A 402 | A | 78.52 | BOOKED |
| A 403 | A | 78.52 | UNBOOKED |
| A 404 | A | 78.52 | BOOKED |
| A 501 | A | 78.52 | BOOKED |
| A 502 | A | 78.52 | BOOKED |
| A 503 | A | 78.52 | UNBOOKED |
| A 504 | A | 78.52 | BOOKED |
| A 601 | A | 78.52 | BOOKED |
| A 602 | A | 78.52 | BOOKED |
| A 603 | A | 78.52 | UNBOOKED |
| A 604 | A | 78.52 | BOOKED |
| A 701 | A | 78.52 | BOOKED |
| A 702 | A | 78.52 | BOOKED |
| A 703 | A | 78.52 | UNBOOKED |
| A 704 | A | 78.52 | UNBOOKED |
| A 801 | A | 78.52 | BOOKED |
| A 802 | A | 78.52 | UNBOOKED |
| A 803 | A | 78.52 | UNBOOKED |
| A 804 | A | 78.52 | UNBOOKED |
| A 901 | A | 78.52 | UNBOOKED |
| A 902 | A | 78.52 | UNBOOKED |
| A 903 | A | 78.52 | UNBOOKED |
| A 904 | A | 78.52 | UNBOOKED |
| A 1001 | A | 78.52 | UNBOOKED |
| A 1002 | A | 78.52 | UNBOOKED |
| A 1003 | A | 78.52 | UNBOOKED |
| A 1004 | A | 78.52 | BOOKED |
| A 1102 | A | 78.52 | UNBOOKED |
| A 1103 | A | 78.52 | UNBOOKED |
| B 101 | B+C | 61.92 | UNBOOKED |
| B 102 | B+C | 61.92 | BOOKED |
| B 103 | B+C | 61.92 | BOOKED |
| B 104 | B+C | 61.92 | BOOKED |
| B 201 | B+C | 61.92 | BOOKED |
| B 202 | B+C | 61.92 | BOOKED |
| B 203 | B+C | 61.92 | BOOKED |
| B 204 | B+C | 61.92 | BOOKED |
| B 301 | B+C | 61.92 | BOOKED |
| B 302 | B+C | 61.92 | BOOKED |
| B 303 | B+C | 61.92 | BOOKED |
| B 304 | B+C | 61.92 | BOOKED |
| B 401 | B+C | 61.92 | UNBOOKED |
| B 402 | B+C | 61.92 | BOOKED |
| B 403 | B+C | 61.92 | BOOKED |
| B 404 | B+C | 61.92 | BOOKED |
| B 501 | B+C | 61.92 | BOOKED |
| B 502 | B+C | 61.92 | BOOKED |
| B 503 | B+C | 61.92 | BOOKED |
| B 504 | B+C | 61.92 | BOOKED |
| B 601 | B+C | 61.92 | UNBOOKED |
| B 602 | B+C | 61.92 | BOOKED |
| B 603 | B+C | 61.92 | BOOKED |
| B 604 | B+C | 61.92 | BOOKED |
| B 701 | B+C | 61.92 | UNBOOKED |
| B 702 | B+C | 61.92 | BOOKED |
| B 703 | B+C | 61.92 | BOOKED |
| B 704 | B+C | 61.92 | UNBOOKED |
| B 801 | B+C | 61.92 | UNBOOKED |
| B 802 | B+C | 61.92 | BOOKED |
| B 803 | B+C | 61.92 | UNBOOKED |
| B 804 | B+C | 61.92 | UNBOOKED |
| B 901 | B+C | 61.92 | UNBOOKED |
| B 902 | B+C | 61.92 | UNBOOKED |
| B 903 | B+C | 61.92 | UNBOOKED |
| B 904 | B+C | 61.92 | UNBOOKED |
| B 1001 | B+C | 61.92 | UNBOOKED |
| B 1004 | B+C | 61.92 | UNBOOKED |
| C 101 | B+C | 61.92 | BOOKED |
| C 102 | B+C | 61.92 | UNBOOKED |
| C 103 | B+C | 61.92 | UNBOOKED |
| C 104 | B+C | 61.92 | UNBOOKED |
| C 201 | B+C | 61.92 | BOOKED |
| C 202 | B+C | 61.92 | BOOKED |
| C 203 | B+C | 61.92 | UNBOOKED |
| C 204 | B+C | 61.92 | BOOKED |
| C 301 | B+C | 61.92 | BOOKED |
| C 302 | B+C | 61.92 | UNBOOKED |
| C 303 | B+C | 61.92 | UNBOOKED |
| C 304 | B+C | 61.92 | UNBOOKED |
| C 401 | B+C | 61.92 | UNBOOKED |
| C 402 | B+C | 61.92 | UNBOOKED |
| C 403 | B+C | 61.92 | UNBOOKED |
| C 404 | B+C | 61.92 | UNBOOKED |
| C 501 | B+C | 61.92 | UNBOOKED |
| C 502 | B+C | 61.92 | UNBOOKED |
| C 503 | B+C | 61.92 | UNBOOKED |
| C 504 | B+C | 61.92 | UNBOOKED |
| C 601 | B+C | 61.92 | UNBOOKED |
| C 602 | B+C | 61.92 | UNBOOKED |
| C 603 | B+C | 61.92 | UNBOOKED |
| C 604 | B+C | 61.92 | UNBOOKED |
| C 701 | B+C | 61.92 | UNBOOKED |
| C 702 | B+C | 61.92 | UNBOOKED |
| C 703 | B+C | 61.92 | UNBOOKED |
| C 704 | B+C | 61.92 | UNBOOKED |
| C 801 | B+C | 61.92 | UNBOOKED |
| C 802 | B+C | 61.92 | BOOKED |
| C 803 | B+C | 61.92 | UNBOOKED |
| C 804 | B+C | 61.92 | UNBOOKED |
| C 901 | B+C | 61.92 | UNBOOKED |
| C 902 | B+C | 61.92 | UNBOOKED |
| C 903 | B+C | 61.92 | UNBOOKED |
| C 904 | B+C | 61.92 | UNBOOKED |
| C 1002 | B+C | 61.92 | UNBOOKED |
| C 1003 | B+C | 61.92 | UNBOOKED |
Booking status as filed — confirm availability with the builder.
Construction progress
Reported completion: 59.8944%6 quarterly returns · January 2024 (14.54%) to July 2026 (59.8944%)
14.54%
Initial progress · January 2024
59.8944%
Final progress · July 2026
Builder-declared quarterly returns — not an independent inspection.
RERA activity timeline
2023
Registration
2024
Alteration · Annual Compliance
2025
Annual Compliance
Undated
Annual Compliance
2026
Snapshot reviewed
Full application ledger (8 rows)
- Registration — 2023-09-29 12:35:37.000000
- Alteration — 2024-05-13 17:22:54.809000
- Annual Compliance — 2024-10-20 12:07:00
- Annual Compliance — 2025-10-25 14:37:07
- Annual Compliance — undated
- Annual Compliance — undated
- Annual Compliance — undated
- Annual Compliance — undated
Quarterly filing history
2024
Q-1 · Q-4
—
Q-2 · Q-3 · BWA-1
2025
Q-5 · Q-6 · Q-7 · Q-8
2026
Q-9 · Q-10 · Q-11
9 submitted · 3 missing
Documents on file
40 documentsMissing from this record: Registration certificate, Commencement certificate, NOCs from authorities.
Registration (0)Registration certificate
- None on this record.
Land & title (4)Title · EC · Clearance
4 of 4 open directly
Approvals (4)Plans · CC · NOCs
4 of 4 open directly
Builder finances (22)Accounts · ITR · Audit reports
- Auditor's report (1 of 3)
- Auditor's report (2 of 3)
- Auditor's report (3 of 3)
- Director's report (1 of 3)
- Director's report (2 of 3)
- Director's report (3 of 3)
- Income-tax return (1 of 3)
- Income-tax return (2 of 3)
- Income-tax return (3 of 3)
- PAN card
- auditedBalSheetDoc1
- auditedBalSheetDoc2_
- auditedBalSheetDoc3
- auditedProfitLossSheetDoc1
- auditedProfitLossSheetDoc2
- auditedProfitLossSheetDoc3
- auditedReportDoc1
- auditedReportDoc2
- auditedReportDoc3
- cashFlowStmtFileDoc1
- cashFlowStmtFileDoc2
- cashFlowStmtFileDoc3
22 of 22 open directly
Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.
View documents on GujRERASearch PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/MAA12326/A1M/130524/311228 → Documents tab
Filing depth
Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.
Land & money
- Village (moje)
- PETHAPUR
- Survey no.
- 1122/2, F.P. :- 1122/2
- TP scheme
- Gandhinagar Municipal Corporation
- Authority
- Gandhinagar Municipal Corporation
- Covered area
- 1224.31 sq m
- Open area
- 2235.69 sq m
- BU permission
- Registration cert
- Portal file
- Ack no.
- PR/GANDHINAGAR/GANDHINAGAR/GUJRERA/230701/015017
- Covered parking
- 217 · 2662.58 sq m
- Parking for sale
- 0
Escrow account
- Bank
- HDFC
- Branch
- RAYSAN
- IFSC
- HDFC0005065
- Account
- XXXX-1284
- Deposited
- ₹4.19 Cr
- Withdrawn
- ₹3.97 Cr
- Closing
- ₹0.31 Cr
- Status
- APPROVED
Inspection phases (Form-1)
- Architect
- BHAUMIKKUMAR CHANDRAVADANBHAI DONGA
- Form-1 PDF
- Block A82.68711111111111%
- Block B+C59.08933333333332%
- Block B+C59.08933333333332%
Phase actual dates (2 blocks)
- Block A: excavation 2023-06-01 → slab
- Block B+C: excavation 2023-06-01 → slab —
Filing PDFs
- REG_PROCESS · 2023-06-23 — Form-1 · Form-2
- ALT_PROCESS · 2024-02-10 — Form-1 · Form-2
- Q-1 · 2024-01-05 — Form-1 · Form-2
- Q-4 · 2024-10-04 — Form-1 · Form-2
- Q-5 · 2025-01-05 — ·
- Q-6 · 2025-04-04 — ·
- Q-7 · 2025-07-05 — ·
- Q-8 · 2025-10-05 — ·
- BWA-2 · 2025-10-12 — Form-1 · Form-2 · Form-3
- Q-9 · 2026-01-06 — ·
- Q-10 · 2026-04-10 — ·
- Q-11 · 2026-07-03 — ·
- Form-5 · 2023-24 · SUBMITTED — Audit file
- Form-5 · 2024-25 · SUBMITTED — Audit file
- Form-5 · 2025-26 · ACTIVE —
Project team on record
- CHANDRAKANT LALAJIBHAI MEHTA · engineer
- Bhaumikkumar Chandravadanbhai Donga · architect
How is the paperwork score calculated?84 / 100
Delivery standing
40 / 40
Filing discipline
19 / 25
Promoter track record
10 / 20
Complaints and extensions
15 / 15
- Delivery 2029-04-30 still ahead of 2026-09-26 -> 40/40
- QPR filings 9/12 -> 19/25
- Promoter completed projects 1 -> 10/20
- Red flags 0 complaints + 0 extensions -> 15/15
Confidence Medium: QPR filing rate 75.0% is below 90%.
Verify this yourself
If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:
PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/MAA12326/A1M/130524/311228
Open this project on GujRERARun the manual check →Sources
Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.
- MoHUA - Real Estate Regulatory Authorities of States / UTsThe national index of every state/UT RERA portal. Fallback when a state link moves.
- GujRERA - Gujarat Real Estate Regulatory AuthorityGujarat project / agent / complaint search and registrations.