Delivered

Pramukh 52

SURVEY NO 864,NEAR SHANTIVAN BUNGLOWS,

Mixed Development69 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/19502

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA12583/041123

Pramukh 52 — residential developmentGandhinagar · representative residential imagery

Paperwork score

Some gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings9 / 10
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Ekta Infra
Project type
Mixed Development
Total units
69
Project cost
₹17.16 Cr
Carpet area
4,631.9 sq m
Price band
₹15L – ₹0L
Carpet area per unit
21.19-80.82 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Mixed Development — 69 units · carpet 4,631.85 sq m
  • Block A
  • Declared start 2023-07-07 · completion 2026-03-31
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.1574° N, 72.5830° E

Filed plot outline · 6 corners
Open in Google Maps

Units & inventory

69

Total units

28

Booked (41%)

41

Unsold (59%)

41% booked · 59% unsold

Tower A69 units

28 booked (41%) · 41 available (59%)

Flat-level inventory (69 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
Shop-1A25.92BOOKED
Shop-2A25.92BOOKED
Shop-3A25.92BOOKED
Shop-4A25.92UNBOOKED
Shop-5A25.92UNBOOKED
Shop-6A25.92UNBOOKED
Shop-7A35.15UNBOOKED
Shop-8A37.99UNBOOKED
Shop-9A25.77BOOKED
Shop-10A21.3BOOKED
Shop-11A23.52BOOKED
Shop-12A21.19BOOKED
Shop-13A30.28BOOKED
Shop-14A25.2BOOKED
Shop-15A29.99BOOKED
Shop-16A35.11UNBOOKED
Shop-17A33.99UNBOOKED
101A80.82UNBOOKED
102A80.82UNBOOKED
103A80.82UNBOOKED
104A80.82BOOKED
201A80.82BOOKED
202A80.82BOOKED
203A80.82BOOKED
204A80.82BOOKED
301A80.82BOOKED
302A80.82BOOKED
303A80.82BOOKED
304A80.82BOOKED
401A80.82BOOKED
402A80.82BOOKED
403A80.82UNBOOKED
404A80.82UNBOOKED
501A80.82UNBOOKED
502A80.82BOOKED
503A80.82BOOKED
504A80.82BOOKED
601A80.82UNBOOKED
602A80.82UNBOOKED
603A80.82UNBOOKED
604A80.82BOOKED
701A80.82UNBOOKED
702A80.82UNBOOKED
703A80.82BOOKED
704A80.82BOOKED
801A80.82UNBOOKED
802A80.82UNBOOKED
803A80.82BOOKED
804A80.82BOOKED
901A80.82UNBOOKED
902A80.82UNBOOKED
903A80.82UNBOOKED
904A80.82UNBOOKED
1001A80.82UNBOOKED
1002A80.82UNBOOKED
1003A80.82UNBOOKED
1004A80.82BOOKED
1101A80.82UNBOOKED
1102A80.82UNBOOKED
1103A80.82UNBOOKED
1104A80.82UNBOOKED
1201A80.82UNBOOKED
1202A80.82UNBOOKED
1203A80.82UNBOOKED
1204A80.82UNBOOKED
1301A69.37UNBOOKED
1302A69.37BOOKED
1303A69.37UNBOOKED
1304A69.37UNBOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%202420252026July 2024 — 55.52% builtOctober 2024 — 69.38% builtOctober 2025 — 100% builtJanuary 2026 — 100% builtApril 2026 — 100% built

5 quarterly returns · July 2024 (55.52%) to April 2026 (100%)

55.52%

Initial progress · July 2024

100%

Final progress · April 2026

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2023

    Registration

  2. 2024

    Annual Compliance · LEGAL_PCWF

  3. 2025

    Annual Compliance

  4. Undated

    Annual Compliance

  5. 2026

    Snapshot reviewed

Full application ledger (5 rows)
  1. Registration — 2023-11-04 12:55:55.000000
  2. Annual Compliance — 2024-10-28 19:16:43
  3. Annual Compliance — 2025-12-10 18:54:20
  4. Annual Compliance — undated
  5. LEGAL_PCWF — 2024-02-13 14:26:17

Quarterly filing history

2024

Q-1 · Q-2 · Q-3

2025

Q-4 · Q-5 · Q-6 · Q-7

2026

Q-8 · Q-E

—

BWA-1

9 submitted · 1 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA12583/041123 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Authority
Others
Covered area
712.18 sq m
Open area
1194.82 sq m
Land cost
₹2.41 Cr
Estimated cost
₹14.75 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GUJRERA/230904/015239
Covered parking
87 · 967.51 sq m
Parking for sale
30

Escrow account

Bank
HDFC
Branch
TRIMANDIR ADALAJ
IFSC
HDFC0004065
Account
XXXX-2140
Deposited
₹0.59 Cr
Withdrawn
₹0.59 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
SURESH PRATAPJI SUTHAR
Firm
SURESH PRATAPJI SUTHAR
Site visit
2026-02-17
Form-1 PDF
Open file
  • Block A100%
Phase actual dates (1 block)
  • Block A: excavation → slab

Filing PDFs

Project team on record

  • JAY VRAJLAL SORATHIYA · engineer
  • SURESH PRATAPJI SUTHAR · architect
How is the paperwork score calculated?78 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    23 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2026-03-31 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 9/10 -> 23/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA12583/041123

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.