Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Ongoing

Gokuldham Premium Plots

GOKULDHAM PREMIUM PLOTS, B/H CIRCUIT HOUSE

Plotted Development61 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/19601

Filing PR/GJ/GANDHINAGAR/MANSA/Others/PAA12585/061123

Gokuldham Premium Plots — residential developmentGandhinagar · representative residential imagery

Paperwork score

Some gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusOngoing
Quarterly filings10 / 10
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Guruji Gokuldham Premium
Project type
Plotted Development
Total units
61
Project cost
₹5.79 Cr
Carpet area
6,253.5 sq m
Price band
₹3L – ₹0L
Carpet area per unit
25.2-199.64 sq m
Status
Ongoing
Filing extras — blocks, inventory lines, dates
  • Plotted Development — 61 units · carpet 6,253.47 sq m
  • Block A
  • Declared start 2023-06-09 · completion 2026-03-31
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.4115° N, 72.6535° E

Filed plot outline · 4 corners
Open in Google Maps

Units & inventory

61

Total units

57

Booked (93%)

4

Unsold (7%)

93% booked · 7% unsold

Tower A61 units

57 booked (93%) · 4 available (7%)

Flat-level inventory (61 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
1A93.72BOOKED
2A25.2BOOKED
3A28.13UNBOOKED
4A31.05BOOKED
5A33.85BOOKED
6A32.66BOOKED
51A96.59BOOKED
84A142.84BOOKED
85A92.83BOOKED
86A92.83BOOKED
87A92.83BOOKED
88A92.83BOOKED
89A102.05BOOKED
90A118.72BOOKED
91A99.01BOOKED
92A99.01BOOKED
93A99.01BOOKED
94A199.64BOOKED
95A139.44BOOKED
96A99.01BOOKED
97A99.01BOOKED
98A99.01BOOKED
99A118.72BOOKED
100A102.05BOOKED
101A92.83UNBOOKED
102A92.83UNBOOKED
103A92.83BOOKED
104A92.83BOOKED
105A143.75BOOKED
106A145.78BOOKED
107A92.83BOOKED
108A92.83BOOKED
109A92.83BOOKED
110A92.83BOOKED
111A102.05BOOKED
112A118.72BOOKED
113A99.01BOOKED
114A99.01BOOKED
115A177.67BOOKED
116A198BOOKED
117A107.24BOOKED
118A102.89BOOKED
119A102.05BOOKED
120A92.83BOOKED
121A92.83BOOKED
122A92.83BOOKED
123A92.83BOOKED
124A142.91BOOKED
125A139.33BOOKED
126A92.83BOOKED
127A92.83BOOKED
128A92.83BOOKED
129A92.83BOOKED
130A102.05BOOKED
131A139.75BOOKED
132A104.31BOOKED
133A95.31BOOKED
134A93.01BOOKED
135A92.96BOOKED
136A92.91BOOKED
137A139.44BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 12.5%
0%25%50%75%100%202420252026April 2024 — 1.56% builtJuly 2024 — 2.97% builtOctober 2024 — 1.56% builtOctober 2025 — 85.75% builtJanuary 2026 — 93.75% builtApril 2026 — 12.5% built

6 quarterly returns · April 2024 (1.56%) to April 2026 (12.5%)

1.56%

Initial progress · April 2024

12.5%

Final progress · April 2026

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2023

    Registration

  2. 2024

    Annual Compliance

  3. 2025

    Annual Compliance

  4. Undated

    Annual Compliance

  5. 2026

    Snapshot reviewed

Full application ledger (4 rows)
  1. Registration — 2023-11-06 13:04:37.000000
  2. Annual Compliance — 2024-10-24 20:57:47
  3. Annual Compliance — 2025-10-17 20:38:59
  4. Annual Compliance — undated

Quarterly filing history

2024

Q-1 · Q-2 · Q-3

2025

Q-4 · Q-5 · Q-6 · Q-7 · BWA-1

2026

Q-8 · Q-E

10 submitted · 0 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/MANSA/Others/PAA12585/061123 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Authority
Others
Open area
11209 sq m
Land cost
₹3.5 Cr
Estimated cost
₹2.29 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/MANSA/GUJRERA/230905/015390
Parking for sale
0

Escrow account

Bank
ICICI Bank
Branch
PALANPUR
IFSC
ICIC0007865
Account
XXXX-0583
Deposited
₹0.71 Cr
Withdrawn
₹0.55 Cr
Closing
₹0.16 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
PARTH NARENDRASINGH VAGHELA
Firm
PARTH NARENDRASINGH VAGHELA
Site visit
2026-03-16
Form-1 PDF
Open file
  • Block A18.75%
Phase actual dates (1 block)
  • Block A: excavation → slab —

Filing PDFs

Project team on record

  • RAHULKUMAR C. BADGURJAR · engineer
  • Shubham Arvindbhai Dudhagara · architect
How is the paperwork score calculated?64 / 100
  • Delivery standing

    24 / 40

  • Filing discipline

    25 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2026-03-31 elapsed 0 yr ago, progress 12.5% -> 24/40
  • QPR filings 10/10 -> 25/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: declared completion date elapsed this year with work still declared incomplete; no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/MANSA/Others/PAA12585/061123

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.