Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Ongoing

Ever Mark 445

Survey no. 445 FP no. 143 OP no. 143

ResidentialGroup Housing56 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/19612

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA12628/111123

Ever Mark 445 — residential developmentGandhinagar · representative residential imagery

Paperwork score

Some gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusOngoing
Quarterly filings10 / 11
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Krishna Corporate
Project type
Residential / Group Housing
Total units
56
Project cost
₹19.19 Cr
Carpet area
6,064.8 sq m
Price band
₹40L – ₹0L
Carpet area per unit
108.3-108.3 sq m
Status
Ongoing
Filing extras — blocks, inventory lines, dates
  • Residential/Group Housing — 56 units · carpet 6,064.8 sq m
  • Block A B
  • Declared start 2023-09-01 · completion 2028-07-31
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.2241° N, 72.6111° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

56

Total units

3

Booked (5%)

53

Unsold (95%)

5% booked · 95% unsold

Tower A B56 units

3 booked (5%) · 53 available (95%)

Flat-level inventory (56 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
101A B108.3BOOKED
102A B108.3UNBOOKED
103A B108.3BOOKED
104A B108.3BOOKED
201A B108.3UNBOOKED
202A B108.3BOOKED
203A B108.3UNBOOKED
204A B108.3UNBOOKED
301A B108.3UNBOOKED
302A B108.3UNBOOKED
303A B108.3UNBOOKED
304A B108.3UNBOOKED
401A B108.3UNBOOKED
402A B108.3UNBOOKED
403A B108.3UNBOOKED
404A B108.3UNBOOKED
501A B108.3UNBOOKED
502A B108.3UNBOOKED
503A B108.3BOOKED
504A B108.3BOOKED
601A B108.3UNBOOKED
602A B108.3UNBOOKED
603A B108.3UNBOOKED
604A B108.3UNBOOKED
701A B108.3UNBOOKED
702A B108.3BOOKED
703A B108.3UNBOOKED
704A B108.3UNBOOKED
801A B108.3UNBOOKED
802A B108.3UNBOOKED
803A B108.3UNBOOKED
804A B108.3UNBOOKED
901A B108.3UNBOOKED
902A B108.3UNBOOKED
903A B108.3UNBOOKED
904A B108.3BOOKED
1001A B108.3UNBOOKED
1002A B108.3UNBOOKED
1003A B108.3UNBOOKED
1004A B108.3BOOKED
1101A B108.3BOOKED
1102A B108.3UNBOOKED
1103A B108.3UNBOOKED
1104A B108.3UNBOOKED
1201A B108.3BOOKED
1202A B108.3UNBOOKED
1203A B108.3UNBOOKED
1204A B108.3UNBOOKED
1301A B108.3UNBOOKED
1302A B108.3UNBOOKED
1303A B108.3UNBOOKED
1304A B108.3UNBOOKED
1401A B108.3UNBOOKED
1402A B108.3UNBOOKED
1403A B108.3UNBOOKED
1404A B108.3UNBOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 86.1124%
0%25%50%75%100%202420252026April 2024 — 21.68% builtJuly 2024 — 22.95% builtOctober 2024 — 25.5% builtOctober 2025 — 69.3572% builtJanuary 2026 — 75.49400000000001% builtApril 2026 — 83.96600000000001% builtJuly 2026 — 86.1124% built

7 quarterly returns · April 2024 (21.68%) to July 2026 (86.1124%)

21.68%

Initial progress · April 2024

86.1124%

Final progress · July 2026

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2023

    Registration

  2. 2024

    Annual Compliance

  3. 2025

    Annual Compliance · LEGAL_PCWF

  4. Undated

    Annual Compliance

  5. 2026

    Snapshot reviewed

Full application ledger (7 rows)
  1. Registration — 2023-11-11 11:14:56.000000
  2. Annual Compliance — 2024-10-24 21:05:16
  3. Annual Compliance — 2025-10-17 20:40:10
  4. Annual Compliance — undated
  5. Annual Compliance — undated
  6. Annual Compliance — undated
  7. LEGAL_PCWF — 2025-01-22 19:03:07

Quarterly filing history

2024

Q-1 · Q-2 · Q-3

2025

Q-4 · Q-5 · Q-6 · Q-7

2026

Q-8 · Q-9 · Q-10

—

BWA-1

10 submitted · 1 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA12628/111123 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Authority
Others
Covered area
587.13 sq m
Open area
1172.87 sq m
Land cost
₹2 Cr
Estimated cost
₹17.2 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GUJRERA/231016/015408
Covered parking
108 · 1281.86 sq m
Parking for sale
5

Escrow account

Bank
Mehsana Urban Co-Operative Bank Ltd.
Branch
GANDHINAGAR
IFSC
MSNU0000046
Account
XXXX-0501
Status
APPROVED

Inspection phases (Form-1)

Architect
NILESH VISHNUBHAI PATEL
Form-1 PDF
  • Block A B89.46933333333332%
Phase actual dates (1 block)
  • Block A B: excavation 2023-09-01 → slab —

Filing PDFs

Project team on record

  • RAVAL MEHULKUMAR M · engineer
  • NILESH VISHNUBHAI PATEL · architect
How is the paperwork score calculated?78 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    23 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2028-07-31 still ahead of 2026-09-26 -> 40/40
  • QPR filings 10/11 -> 23/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA12628/111123

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.