Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Ongoing

Kunj Elite

CITY SURVEY NO NA283/1/P2 (OLD SURVEY NO 283/1)

Mixed Development75 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/19731

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/MAA12866/060224/300626

Kunj Elite — residential developmentGandhinagar · representative residential imagery

Paperwork score

Some gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusOngoing
Quarterly filings9 / 9
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Sadguru Buildcon
Project type
Mixed Development
Total units
75
Project cost
₹13.62 Cr
Carpet area
3,784 sq m
Price band
₹18L – ₹0L
Carpet area per unit
23.2-52.68 sq m
Status
Ongoing
Filing extras — blocks, inventory lines, dates
  • Mixed Development — 75 units · carpet 3,783.96 sq m
  • Block BLOCK A
  • Block BLOCK B
  • Declared start 2023-02-28 · completion 2026-06-30
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.2208° N, 72.6149° E

Filed plot outline · 6 corners
Open in Google Maps

Units & inventory

75

Total units

63

Booked (84%)

12

Unsold (16%)

84% booked · 16% unsold

Tower BLOCK A33 units

25 booked (76%) · 8 available (24%)

Tower BLOCK B42 units

38 booked (90%) · 4 available (10%)

Flat-level inventory (75 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
1BLOCK A23.2BOOKED
2BLOCK A23.35UNBOOKED
3BLOCK A36.02BOOKED
4BLOCK A23.35BOOKED
5BLOCK A23.2UNBOOKED
101BLOCK A52.1UNBOOKED
102BLOCK A52.1UNBOOKED
103BLOCK A52.1UNBOOKED
104BLOCK A52.1BOOKED
201BLOCK A52.1BOOKED
202BLOCK A52.1UNBOOKED
203BLOCK A52.1BOOKED
204BLOCK A52.1BOOKED
301BLOCK A52.1BOOKED
302BLOCK A52.1BOOKED
303BLOCK A52.1BOOKED
304BLOCK A52.1BOOKED
401BLOCK A52.1BOOKED
402BLOCK A52.1BOOKED
403BLOCK A52.1BOOKED
404BLOCK A52.1BOOKED
501BLOCK A52.1BOOKED
502BLOCK A52.1BOOKED
503BLOCK A52.1BOOKED
504BLOCK A52.1BOOKED
601BLOCK A52.1BOOKED
602BLOCK A52.1BOOKED
603BLOCK A52.1UNBOOKED
604BLOCK A52.1BOOKED
701BLOCK A52.1BOOKED
702BLOCK A52.1UNBOOKED
703BLOCK A52.1UNBOOKED
704BLOCK A52.1BOOKED
101BLOCK B52.09BOOKED
102BLOCK B52.68BOOKED
103BLOCK B52.09BOOKED
104BLOCK B52.09BOOKED
105BLOCK B52.68BOOKED
106BLOCK B52.09BOOKED
201BLOCK B52.09BOOKED
202BLOCK B52.68BOOKED
203BLOCK B52.09BOOKED
204BLOCK B52.09BOOKED
205BLOCK B52.68BOOKED
206BLOCK B52.09BOOKED
301BLOCK B52.09BOOKED
302BLOCK B52.68BOOKED
303BLOCK B52.09BOOKED
304BLOCK B52.09BOOKED
305BLOCK B52.68BOOKED
306BLOCK B52.09BOOKED
401BLOCK B52.09BOOKED
402BLOCK B52.68BOOKED
403BLOCK B52.09BOOKED
404BLOCK B52.09BOOKED
405BLOCK B52.68BOOKED
406BLOCK B52.09BOOKED
501BLOCK B52.09BOOKED
502BLOCK B52.68BOOKED
503BLOCK B52.09BOOKED
504BLOCK B52.09BOOKED
505BLOCK B52.68BOOKED
506BLOCK B52.09BOOKED
601BLOCK B52.09BOOKED
602BLOCK B52.68UNBOOKED
603BLOCK B52.09BOOKED
604BLOCK B52.09BOOKED
605BLOCK B52.68BOOKED
606BLOCK B52.09BOOKED
701BLOCK B52.09BOOKED
702BLOCK B52.68BOOKED
703BLOCK B52.09BOOKED
704BLOCK B52.09BOOKED
705BLOCK B52.68BOOKED
706BLOCK B52.09BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 89.375%
0%25%50%75%100%202420252026July 2024 — 38.89% builtOctober 2024 — 43.72% builtOctober 2025 — 70.634% builtJanuary 2026 — 74.10619999999999% builtApril 2026 — 97.02% builtJuly 2026 — 89.375% built

6 quarterly returns · July 2024 (38.89%) to July 2026 (89.375%)

38.89%

Initial progress · July 2024

89.375%

Final progress · July 2026

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2024

    Registration · Annual Compliance

  2. 2025

    Annual Compliance · BCR

  3. Undated

    Annual Compliance

  4. 2026

    Snapshot reviewed

Full application ledger (5 rows)
  1. Registration — 2024-02-06 18:06:44.806000
  2. Annual Compliance — 2024-10-24 17:50:52
  3. Annual Compliance — 2025-12-09 20:31:43
  4. Annual Compliance — undated
  5. BCR — 2025-07-25 11:30:31.427000

Quarterly filing history

2024

Q-1 · Q-2

2025

Q-3 · Q-4 · Q-5 · Q-6

2026

Q-7 · Q-8 · Q-E

9 submitted · 0 missing

Documents on file

24 documents

Missing from this record: Registration certificate, Commencement certificate.

Registration (0)Registration certificate
  • None on this record.
Land & title (4)Title · EC · Clearance

4 of 4 open directly

Approvals (5)Plans · CC · NOCs

5 of 5 open directly

Builder finances (6)Accounts · ITR · Audit reports

6 of 6 open directly

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/MAA12866/060224/300626 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
VAVOL
Survey no.
283/1
TP scheme
VAVOL
Final / sub plot
80
Authority
Gandhinagar Municipal Corporation
Covered area
853.93 sq m
Open area
846.07 sq m
BU permission
Registration cert
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR MUNICIPAL CORPORATION/231204/019731
Covered parking
70 · 1441.17 sq m
Parking for sale
16

Escrow account

Bank
KOTAK MAHINDRA BANK LIMITED
Branch
GANDHINAGAR
IFSC
KKBK0000879
Account
XXXX-0272
Deposited
₹7.06 Cr
Withdrawn
₹7.05 Cr
Closing
₹0.02 Cr

Inspection phases (Form-1)

Architect
DEVANG BABUBHAI VAGHELA
Firm
SPLINE DESIGN
Site visit
2026-06-12
Form-1 PDF
Open file
  • Block BLOCK A87.5%
  • Block BLOCK B87.5%
Phase actual dates (2 blocks)
  • Block BLOCK B: excavation → slab
  • Block BLOCK A: excavation → slab

Filing PDFs

Project team on record

  • HARSH RAJESHBHAI SANGHVI · engineer
  • DEVANG BABUBHAI VAGHELA · architect
How is the paperwork score calculated?64 / 100
  • Delivery standing

    24 / 40

  • Filing discipline

    25 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2026-06-30 elapsed 0 yr ago, progress 89.375% -> 24/40
  • QPR filings 9/9 -> 25/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: declared completion date elapsed this year with work still declared incomplete; no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/MAA12866/060224/300626

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.