Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Ongoing

Sahjanand Sanskar

Block No.356, O.P. 329, F.P.No.329 in TP No.29 Sargasan-tarapur-Adalaj-Uvarsad

Mixed Development64 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/26386

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Urban Development Authority/MAA15158/010525/310328

Sahjanand Sanskar — residential developmentGandhinagar · representative residential imagery

Paperwork score

Some gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusOngoing
Quarterly filings3 / 4
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Shreeji Siddhi Buildcon
Project type
Mixed Development
Total units
64
Project cost
₹13.23 Cr
Carpet area
4,705.8 sq m
Price band
₹10L – ₹0L
Carpet area per unit
22.52-81.08 sq m
Status
Ongoing
Filing extras — blocks, inventory lines, dates
  • Mixed Development — 64 units · carpet 4,705.84 sq m
  • Block A
  • Block B
  • Declared start 2025-01-29 · completion 2028-07-31
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.1918° N, 72.6037° E

Filed plot outline · 4 corners
Open in Google Maps

Units & inventory

64

Total units

28

Booked (44%)

36

Unsold (56%)

44% booked · 56% unsold

Tower A37 units

17 booked (46%) · 20 available (54%)

Tower B27 units

11 booked (41%) · 16 available (59%)

Flat-level inventory (64 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
101A81UNBOOKED
102A81UNBOOKED
103A81BOOKED
104A81UNBOOKED
201A81.08BOOKED
202A81.08BOOKED
203A81.08BOOKED
204A81.08UNBOOKED
301A81.08BOOKED
302A81.08UNBOOKED
303A81.08BOOKED
304A81.08UNBOOKED
401A81.08UNBOOKED
402A81.08BOOKED
403A81.08UNBOOKED
404A81.08UNBOOKED
501A81.08BOOKED
502A81.08BOOKED
503A81.08BOOKED
504A81.08BOOKED
601A81.08BOOKED
602A81.08UNBOOKED
603A81.08UNBOOKED
604A81.08UNBOOKED
701A81.08BOOKED
702A81.08UNBOOKED
703A81.08UNBOOKED
704A81.08BOOKED
1A28.83BOOKED
2A33.44BOOKED
3A28.73UNBOOKED
4A24.19UNBOOKED
5A22.88UNBOOKED
6A22.52UNBOOKED
7A28.83UNBOOKED
8A28.83UNBOOKED
9A28.83UNBOOKED
101B81BOOKED
102B81UNBOOKED
103B81UNBOOKED
104B81UNBOOKED
201B81.08UNBOOKED
202B81.08UNBOOKED
203B81.08BOOKED
204B81.08UNBOOKED
301B81.08UNBOOKED
302B81.08UNBOOKED
303B81.08BOOKED
304B81.08BOOKED
401B81.08BOOKED
402B81.08BOOKED
403B81.08BOOKED
404B81.08BOOKED
501B81.08UNBOOKED
502B81.08BOOKED
503B81.08BOOKED
504B81.08UNBOOKED
601B81.08BOOKED
602B81.08UNBOOKED
603B81.08BOOKED
604B81.08UNBOOKED
701B81.08UNBOOKED
702B81.08UNBOOKED
703B81.08UNBOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 64.6852%
0%25%50%75%100%20252026October 2025 — 32.2148% builtApril 2026 — 46.885999999999996% builtJuly 2026 — 64.6852% built

3 quarterly returns · October 2025 (32.2148%) to July 2026 (64.6852%)

32.2148%

Initial progress · October 2025

64.6852%

Final progress · July 2026

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2025

    Registration

  2. Undated

    Annual Compliance

  3. 2026

    Snapshot reviewed

Full application ledger (4 rows)
  1. Registration — 2025-05-01 11:37:44.153000
  2. Annual Compliance — undated
  3. Annual Compliance — undated
  4. Annual Compliance — undated

Quarterly filing history

2025

Q-1

—

Q-2

2026

Q-3 · Q-4

3 submitted · 1 missing

Documents on file

31 documents

Missing from this record: Registration certificate, Commencement certificate, Draft agreement for sale.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Urban Development Authority/MAA15158/010525/310328 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
TARAPUR
Survey no.
356
TP scheme
SARGASAN - TARAPUR - ADALAJ - UVARSAD
Final / sub plot
329 / --
Authority
Gandhinagar Urban Development Authority
Covered area
918.75 sq m
Open area
1023.25 sq m
BU permission
Registration cert
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR URBAN DEVELOPMENT AUTHORITY/250304/026386
Covered parking
74 · 1533.2 sq m
Parking for sale
0

Escrow account

Bank
IDFC First Bank Ltd
Branch
GANDHINAGAR BRANCH
IFSC
IDFB0042343
Account
XXXX-7281
Deposited
₹1.6 Cr
Withdrawn
₹1.4 Cr
Closing
₹0.2 Cr

Inspection phases (Form-1)

Architect
CHARMI SURESHCHANDRA SARADVA
Form-1 PDF
  • Block A61.55555555555556%
  • Block B80.41155555555555%
Phase actual dates (2 blocks)
  • Block A: excavation 2025-01-29 → slab
  • Block B: excavation 2025-01-29 → slab

Filing PDFs

Project team on record

  • NITINKUMAR PATEL · engineer
  • Charmi Sureshchandra Saradva · architect
How is the paperwork score calculated?74 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    19 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2028-07-31 still ahead of 2026-09-26 -> 40/40
  • QPR filings 3/4 -> 19/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: QPR filing rate 75.0% is below 90%; no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Urban Development Authority/MAA15158/010525/310328

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.