Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Ongoing

Shivalay Industrial Park

OPP. GOKULAM BUNGALOWS, NR.UMIYA MATA MANDIR

Commercial48 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/26832

Filing PR/GJ/GANDHINAGAR/DEHGAM/Ahmedabad Urban Development Authority/CAA15374/230625/300627

Shivalay Industrial Park — residential developmentGandhinagar · representative residential imagery

Paperwork score

Complete record

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusOngoing
Quarterly filings5 / 5
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Radheshyamdevelopers
Project type
Commercial
Total units
48
Project cost
₹7.18 Cr
Carpet area
2,681 sq m
Price band
₹14L – ₹0L
Carpet area per unit
33.41-78.47999999999999 sq m
Status
Ongoing
Filing extras — blocks, inventory lines, dates
  • Commercial — 48 units · carpet 2,681.05 sq m
  • Block A
  • Block B
  • Block C
  • Block D
  • Block E
  • Declared start 2024-11-11 · completion 2027-10-30
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.1640° N, 72.7977° E

Filed plot outline · 6 corners
Open in Google Maps

Units & inventory

48

Total units

3

Booked (6%)

45

Unsold (94%)

6% booked · 94% unsold

Tower A8 units

0 booked (0%) · 8 available (100%)

Tower B10 units

0 booked (0%) · 10 available (100%)

Tower C6 units

0 booked (0%) · 6 available (100%)

Tower D12 units

1 booked (8%) · 11 available (92%)

Tower E12 units

2 booked (17%) · 10 available (83%)

Flat-level inventory (48 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
1A51.86UNBOOKED
2A52.21BOOKED
3A52.059999999999995BOOKED
4A78.47999999999999UNBOOKED
5A54.099999999999994BOOKED
6A56.45UNBOOKED
7A56.52UNBOOKED
8A58.120000000000005UNBOOKED
14B57.910000000000004UNBOOKED
15B56.739999999999995UNBOOKED
16B56.739999999999995UNBOOKED
17B56.739999999999995UNBOOKED
18B54.39UNBOOKED
19B54.39UNBOOKED
20B56.739999999999995UNBOOKED
21B56.739999999999995UNBOOKED
22B56.739999999999995UNBOOKED
23B57.910000000000004UNBOOKED
27C57.57UNBOOKED
28C56.41UNBOOKED
29C56.41UNBOOKED
30C56.41UNBOOKED
31C56.41UNBOOKED
32C56.21UNBOOKED
40D52.82BOOKED
41D56.739999999999995UNBOOKED
42D56.739999999999995UNBOOKED
43D56.739999999999995UNBOOKED
44D56.739999999999995UNBOOKED
45D57.910000000000004UNBOOKED
46D57.910000000000004UNBOOKED
47D56.739999999999995UNBOOKED
48D56.739999999999995UNBOOKED
49D56.739999999999995UNBOOKED
50D56.739999999999995UNBOOKED
51D56.41UNBOOKED
52E56.48UNBOOKED
53E56.81UNBOOKED
54E56.81UNBOOKED
55E56.81UNBOOKED
56E56.81UNBOOKED
57E57.97UNBOOKED
58E59.14BOOKED
59E57.95BOOKED
60E55.86UNBOOKED
61E55.61UNBOOKED
62E34.160000000000004BOOKED
63E33.41BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 82.69%
0%25%50%75%100%20252026October 2025 — 63.22648000000001% builtJanuary 2026 — 76.49820000000001% builtApril 2026 — 80.6682% builtJuly 2026 — 82.69% built

4 quarterly returns · October 2025 (63.22648000000001%) to July 2026 (82.69%)

63.22648000000001%

Initial progress · October 2025

82.69%

Final progress · July 2026

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2025

    Registration

  2. Undated

    Annual Compliance

  3. 2026

    Snapshot reviewed

Full application ledger (3 rows)
  1. Registration — 2025-06-23 11:48:55.957000
  2. Annual Compliance — undated
  3. Annual Compliance — undated

Quarterly filing history

2025

Q-1 · BWA-1

2026

Q-2 · Q-3 · Q-4

5 submitted · 0 missing

Documents on file

32 documents

Missing from this record: Registration certificate, Commencement certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/DEHGAM/Ahmedabad Urban Development Authority/CAA15374/230625/300627 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
DAHEGAM
Survey no.
145/P
TP scheme
DAHEGAM
Final / sub plot
20 / --
Authority
Ahmedabad Urban Development Authority
Covered area
2148.65 sq m
Open area
3418.35 sq m
BU permission
Registration cert
Ack no.
PR/AHMEDABAD/AHMEDABAD CITY/AHMEDABAD URBAN DEVELOPMENT AUTHORITY/250416/026832
Parking for sale
6

Escrow account

Bank
KOTAK MAHINDRA BANK LIMITED
Branch
BAPUNAGAR BRANCH
IFSC
KKBK0002572
Account
XXXX-0769
Deposited
₹0.29 Cr
Closing
₹0.29 Cr

Inspection phases (Form-1)

Architect
DHAVAL NATUBHAI MEWADA
Form-1 PDF
  • Block E100%
  • Block D82.22222222222223%
  • Block A82.22222222222223%
  • Block C82.22222222222223%
  • Block B82.22222222222223%
Phase actual dates (5 blocks)
  • Block E: excavation 2024-11-11 → slab
  • Block D: excavation 2024-11-11 → slab
  • Block A: excavation 2024-11-11 → slab
  • Block C: excavation 2024-11-11 → slab
  • Block B: excavation 2024-11-11 → slab

Filing PDFs

Project team on record

  • HARDIKBHAI PUNAMCHANDRA UPADHYAY · engineer
  • DHAVAL NATUBHAI MEWADA · architect
How is the paperwork score calculated?80 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    25 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2027-10-30 still ahead of 2026-09-26 -> 40/40
  • QPR filings 5/5 -> 25/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/DEHGAM/Ahmedabad Urban Development Authority/CAA15374/230625/300627

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.