Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Ongoing

Sarvasva Pearl

F.P. NO-92/2, B/H GARMENT ZONE K. RAHEJA ROAD

Mixed Development58 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/27303

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/MAA15642/050825/310529

Sarvasva Pearl — residential developmentGandhinagar · representative residential imagery

Paperwork score

Complete record

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusOngoing
Quarterly filings3 / 3
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Madhav Developers
Project type
Mixed Development
Total units
58
Project cost
₹38.85 Cr
Carpet area
6,997.6 sq m
Price band
₹50L – ₹0L
Carpet area per unit
54.77-127.58 sq m
Status
Ongoing
Filing extras — blocks, inventory lines, dates
  • Mixed Development — 58 units · carpet 6,997.61 sq m
  • Block A
  • Declared start 2025-01-18 · completion 2029-09-30
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.1545° N, 72.6373° E

Filed plot outline · 6 corners
Open in Google Maps

Units & inventory

58

Total units

0

Booked (0%)

58

Unsold (100%)

0% booked · 100% unsold

Tower A58 units

0 booked (0%) · 58 available (100%)

Flat-level inventory (58 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
1A68.44UNBOOKED
2A67.38UNBOOKED
3A56.11UNBOOKED
4A56.4BOOKED
5A60.35UNBOOKED
6A54.77UNBOOKED
101A127.58UNBOOKED
102A127.58UNBOOKED
103A127.58UNBOOKED
104A127.58UNBOOKED
201A127.58UNBOOKED
202A127.58UNBOOKED
203A127.58UNBOOKED
204A127.58UNBOOKED
301A127.58UNBOOKED
302A127.58BOOKED
303A127.58UNBOOKED
304A127.58UNBOOKED
401A127.58UNBOOKED
402A127.58BOOKED
403A127.58UNBOOKED
404A127.58UNBOOKED
501A127.58UNBOOKED
502A127.58UNBOOKED
503A127.58BOOKED
504A127.58UNBOOKED
601A127.58UNBOOKED
602A127.58BOOKED
603A127.58UNBOOKED
604A127.58UNBOOKED
701A127.58UNBOOKED
702A127.58UNBOOKED
703A127.58UNBOOKED
704A127.58BOOKED
801A127.58BOOKED
802A127.58UNBOOKED
803A127.58UNBOOKED
804A127.58UNBOOKED
901A127.58BOOKED
902A127.58UNBOOKED
903A127.58UNBOOKED
904A127.58UNBOOKED
1001A127.58UNBOOKED
1002A127.58UNBOOKED
1003A127.58UNBOOKED
1004A127.58UNBOOKED
1101A127.58BOOKED
1102A127.58UNBOOKED
1103A127.58UNBOOKED
1104A127.58UNBOOKED
1201A127.58UNBOOKED
1202A127.58UNBOOKED
1203A127.58UNBOOKED
1204A127.58UNBOOKED
1301A127.58UNBOOKED
1302A127.58UNBOOKED
1303A127.58UNBOOKED
1304A127.58UNBOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 35.059133333333335%
0%25%50%75%100%2026January 2026 — 20.571200000000005% builtApril 2026 — 30.286800000000003% builtJuly 2026 — 35.059133333333335% built

3 quarterly returns · January 2026 (20.571200000000005%) to July 2026 (35.059133333333335%)

20.571200000000005%

Initial progress · January 2026

35.059133333333335%

Final progress · July 2026

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2025

    Registration

  2. 2026

    LEGAL_PCWF

  3. Undated

    Annual Compliance

  4. 2026

    Snapshot reviewed

Full application ledger (6 rows)
  1. Registration — 2025-08-05 12:45:39.287000
  2. Annual Compliance — undated
  3. Annual Compliance — undated
  4. Annual Compliance — undated
  5. Annual Compliance — undated
  6. LEGAL_PCWF — 2026-01-19 13:45:59

Quarterly filing history

2026

Q-1 · Q-2 · Q-3

3 submitted · 0 missing

Documents on file

31 documents

Missing from this record: Registration certificate, Commencement certificate, Draft agreement for sale.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/MAA15642/050825/310529 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
KUDASAN
Survey no.
536/P
TP scheme
KUDASAN - KOBA
Final / sub plot
92/2 / --
Authority
Gandhinagar Municipal Corporation
Covered area
759.83 sq m
Open area
1214.17 sq m
BU permission
Registration cert
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR MUNICIPAL CORPORATION/250608/027303
Covered parking
212 · 2139.81 sq m
Parking for sale
21

Escrow account

Bank
HDFC BANK
Branch
RAYSAN
IFSC
HDFC0005065
Account
XXXX-0530

Inspection phases (Form-1)

Architect
URVASHI LALITKUMAR TULI
Form-1 PDF
  • Block A43.51644444444444%
  • Block A43.51644444444444%
Phase actual dates (1 block)
  • Block A: excavation 2026-08-20 → slab

Filing PDFs

  • REG_PROCESS · 2025-06-08 — Form-1 · Form-2 · Form-3
  • Q-1 · 2026-01-07 — ·
  • Q-2 · 2026-04-07 — ·
  • Q-3 · 2026-07-07 — ·
  • Form-5 · 2025-26 · ACTIVE —
  • Form-5 · 2026-27 · ACTIVE —

Project team on record

  • PARTH PATEL · engineer
  • Urvashi Lalitkumar Tuli · architect
How is the paperwork score calculated?80 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    25 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2029-09-30 still ahead of 2026-09-26 -> 40/40
  • QPR filings 3/3 -> 25/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/MAA15642/050825/310529

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.