Ongoing

D-Sky 62

D-Sky 62, Opp. Rivera Bunglows and Shilpgram Bunglows,

Mixed Development62 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/28109

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Ahmedabad Municipal Corporation/MAA15930/300925/311228

D-Sky 62 — residential developmentGandhinagar · representative residential imagery

Paperwork score

Complete record

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusOngoing
Quarterly filings3 / 3
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Kailash Developers
Project type
Mixed Development
Total units
62
Project cost
₹11.17 Cr
Carpet area
3,840.5 sq m
Price band
₹19L – ₹0L
Carpet area per unit
30.0-65.23 sq m
Status
Ongoing
Filing extras — blocks, inventory lines, dates
  • Mixed Development — 62 units · carpet 3,840.54 sq m
  • Block A
  • Block B
  • Declared start 2024-12-30 · completion 2029-04-30
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.1007° N, 72.6654° E

Filed plot outline · 4 corners
Open in Google Maps

Units & inventory

62

Total units

0

Booked (0%)

62

Unsold (100%)

0% booked · 100% unsold

Tower A34 units

0 booked (0%) · 34 available (100%)

Tower B28 units

0 booked (0%) · 28 available (100%)

Flat-level inventory (62 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
1A46UNBOOKED
2A37.06UNBOOKED
3A37.06BOOKED
4A46UNBOOKED
101A46UNBOOKED
102A30UNBOOKED
103A30UNBOOKED
104A46UNBOOKED
A-101A65.23UNBOOKED
A-104A65.23UNBOOKED
A-201A65.23UNBOOKED
A-202A65.23UNBOOKED
A-203A65.23UNBOOKED
A-204A65.23UNBOOKED
A-301A65.23BOOKED
A-302A65.23BOOKED
A-303A65.23UNBOOKED
A-304A65.23UNBOOKED
A-401A65.23UNBOOKED
A-402A65.23UNBOOKED
A-403A65.23UNBOOKED
A-404A65.23UNBOOKED
A-501A65.23UNBOOKED
A-502A65.23UNBOOKED
A-503A65.23UNBOOKED
A-504A65.23UNBOOKED
A-601A65.23UNBOOKED
A-602A65.23BOOKED
A-603A65.23UNBOOKED
A-604A65.23UNBOOKED
A-701A65.23UNBOOKED
A-702A65.23UNBOOKED
A-703A65.23UNBOOKED
A-704A65.23UNBOOKED
B-101B65.23UNBOOKED
B-102B65.23UNBOOKED
B-103B65.23BOOKED
B-104B65.23UNBOOKED
B-201B65.23UNBOOKED
B-202B65.23UNBOOKED
B-203B65.23UNBOOKED
B-204B65.23UNBOOKED
B-301B65.23UNBOOKED
B-302B65.23UNBOOKED
B-303B65.23UNBOOKED
B-304B65.23UNBOOKED
B-401B65.23UNBOOKED
B-402B65.23UNBOOKED
B-403B65.23UNBOOKED
B-404B65.23BOOKED
B-501B65.23UNBOOKED
B-502B65.23BOOKED
B-503B65.23UNBOOKED
B-504B65.23UNBOOKED
B-601B65.23UNBOOKED
B-602B65.23UNBOOKED
B-603B65.23UNBOOKED
B-604B65.23UNBOOKED
B-701B65.23UNBOOKED
B-702B65.23UNBOOKED
B-703B65.23UNBOOKED
B-704B65.23UNBOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 36%
0%25%50%75%100%2026January 2026 — 25% builtApril 2026 — 28% builtJuly 2026 — 36% built

3 quarterly returns · January 2026 (25%) to July 2026 (36%)

25%

Initial progress · January 2026

36%

Final progress · July 2026

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2025

    Registration · LEGAL_PCWF

  2. Undated

    Annual Compliance

  3. 2026

    Snapshot reviewed

Full application ledger (6 rows)
  1. Registration — 2025-09-30 13:44:15.522000
  2. Annual Compliance — undated
  3. Annual Compliance — undated
  4. Annual Compliance — undated
  5. Annual Compliance — undated
  6. LEGAL_PCWF — 2025-12-29 14:50:44

Quarterly filing history

2026

Q-1 · Q-2 · Q-3

3 submitted · 0 missing

Documents on file

25 documents

Missing from this record: Registration certificate, Commencement certificate, Draft agreement for sale.

Registration (0)Registration certificate
  • None on this record.
Land & title (4)Title · EC · Clearance

4 of 4 open directly

Approvals (5)Plans · CC · NOCs

5 of 5 open directly

Builder finances (6)Accounts · ITR · Audit reports

6 of 6 open directly

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Ahmedabad Municipal Corporation/MAA15930/300925/311228 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Chiloda-Naroda
Survey no.
171/1
TP scheme
Chiloda-Naroda
Final / sub plot
64 / --
Authority
Ahmedabad Municipal Corporation
Covered area
768.61 sq m
Open area
870.39 sq m
BU permission
Registration cert
Ack no.
PR/AHMEDABAD/AHMEDABAD CITY/AHMEDABAD MUNICIPAL CORPORATION/250725/028109
Covered parking
133 · 1168.49 sq m
Parking for sale
5

Escrow account

Bank
ICICI BANK LIMITED
Branch
AHMEDABAD - NARODA
IFSC
ICIC0000844
Account
XXXX-3431

Inspection phases (Form-1)

Architect
KHUSHILKUMAR MANOJKUMAR KANANI
Form-1 PDF
  • Block A43.333333333333336%
  • Block B36.666666666666664%
Phase actual dates (2 blocks)
  • Block A: excavation 2025-06-30 → slab
  • Block B: excavation 2025-06-30 → slab

Filing PDFs

  • REG_PROCESS · 2025-07-25 — Form-1 · Form-2 · Form-3
  • Q-1 · 2026-01-07 — ·
  • Q-2 · 2026-04-03 — ·
  • Q-3 · 2026-07-04 — ·
  • Form-5 · 2025-26 · ACTIVE —
  • Form-5 · 2026-27 · ACTIVE —

Project team on record

  • KETAN KANUBHAI PATEL · engineer
  • KHUSHILKUMAR MANOJKUMAR KANANI · architect
How is the paperwork score calculated?80 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    25 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2029-04-30 still ahead of 2026-09-26 -> 40/40
  • QPR filings 3/3 -> 25/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Ahmedabad Municipal Corporation/MAA15930/300925/311228

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.