Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Delivered

Vivaan Infinity

VIVAN INFINITY, S NO 344/1, TP NO 234, F P NO 186

ResidentialGroup Housing76 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/292

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA00283/280917

Vivaan Infinity — residential developmentGandhinagar · representative residential imagery

Paperwork score

Some gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings8 / 9
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Infinity Realty
Project type
Residential / Group Housing
Total units
76
Project cost
₹10.38 Cr
Carpet area
5,041.8 sq m
Price band
₹20L – ₹0L
Carpet area per unit
58.85-73.08 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Residential/Group Housing — 76 units · carpet 5,041.8 sq m
  • Block BLOCK A
  • Block BLOCK B
  • Declared start 2017-04-03 · completion 2019-12-31
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.1338° N, 72.5753° E

Filed plot outline · 9 corners
Open in Google Maps

Units & inventory

76

Total units

71

Booked (93%)

5

Unsold (7%)

93% booked · 7% unsold

Tower BLOCK A38 units

37 booked (97%) · 1 available (3%)

Tower BLOCK B38 units

34 booked (89%) · 4 available (11%)

Flat-level inventory (76 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
101BLOCK A73.08BOOKED
102BLOCK A58.85BOOKED
103BLOCK A58.85BOOKED
104BLOCK A73.08UNBOOKED
201BLOCK A73.08BOOKED
202BLOCK A58.85BOOKED
203BLOCK A58.85BOOKED
204BLOCK A73.08BOOKED
301BLOCK A73.08BOOKED
302BLOCK A58.85BOOKED
303BLOCK A58.85BOOKED
304BLOCK A73.08BOOKED
401BLOCK A73.08BOOKED
402BLOCK A58.85BOOKED
403BLOCK A58.85BOOKED
404BLOCK A73.08BOOKED
501BLOCK A73.08BOOKED
502BLOCK A58.85BOOKED
503BLOCK A58.85BOOKED
504BLOCK A73.08BOOKED
601BLOCK A73.08BOOKED
602BLOCK A58.85BOOKED
603BLOCK A58.85BOOKED
604BLOCK A73.08BOOKED
701BLOCK A73.08BOOKED
702BLOCK A58.85BOOKED
703BLOCK A58.85BOOKED
704BLOCK A73.08BOOKED
801BLOCK A73.08BOOKED
802BLOCK A58.85BOOKED
803BLOCK A58.85BOOKED
804BLOCK A73.08BOOKED
901BLOCK A73.08BOOKED
902BLOCK A58.85BOOKED
903BLOCK A58.85BOOKED
904BLOCK A73.08BOOKED
1001BLOCK A73.08BOOKED
1004BLOCK A73.08BOOKED
101BLOCK B73.08BOOKED
102BLOCK B58.85BOOKED
103BLOCK B58.85BOOKED
104BLOCK B73.08BOOKED
201BLOCK B73.08BOOKED
202BLOCK B58.85BOOKED
203BLOCK B58.85BOOKED
204BLOCK B73.08BOOKED
301BLOCK B73.08BOOKED
302BLOCK B58.85BOOKED
303BLOCK B58.85BOOKED
304BLOCK B73.08BOOKED
401BLOCK B73.08BOOKED
402BLOCK B58.85BOOKED
403BLOCK B58.85BOOKED
404BLOCK B73.08UNBOOKED
501BLOCK B73.08BOOKED
502BLOCK B58.85BOOKED
503BLOCK B58.85BOOKED
504BLOCK B73.08BOOKED
601BLOCK B73.08UNBOOKED
602BLOCK B58.85BOOKED
603BLOCK B58.85BOOKED
604BLOCK B73.08BOOKED
701BLOCK B73.08BOOKED
702BLOCK B58.85BOOKED
703BLOCK B58.85BOOKED
704BLOCK B73.08BOOKED
801BLOCK B73.08UNBOOKED
802BLOCK B58.85BOOKED
803BLOCK B58.85BOOKED
804BLOCK B73.08BOOKED
901BLOCK B73.08BOOKED
902BLOCK B58.85UNBOOKED
903BLOCK B58.85BOOKED
904BLOCK B73.08BOOKED
1001BLOCK B73.08BOOKED
1004BLOCK B73.08BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%201820192020May 2018 — 30.74% builtAugust 2018 — 45.22% builtNovember 2018 — 61.66% builtFebruary 2019 — 65.59% builtMay 2019 — 100% builtAugust 2019 — 100% builtNovember 2019 — 100% builtJanuary 2020 — 100% built

8 quarterly returns · May 2018 (30.74%) to January 2020 (100%)

30.74%

Initial progress · May 2018

100%

Final progress · January 2020

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2017

    Registration

  2. 2019

    Annual Compliance

  3. 2021

    Annual Compliance

  4. Undated

    Annual Compliance

  5. 2026

    Snapshot reviewed

Full application ledger (4 rows)
  1. Registration — 2017-09-28 18:21:56.000000
  2. Annual Compliance — undated
  3. Annual Compliance — 2019-10-25 15:08:43
  4. Annual Compliance — 2021-01-30 15:18:49

Quarterly filing history

—

Q-1

2018

Q-2 · Q-3 · Q-4

2019

Q-5 · Q-6 · Q-7 · Q-8 · Q-E

8 submitted · 1 missing

Documents on file

39 documents

Missing from this record: Registration certificate, Title clearance certificate, Title report.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA00283/280917 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Zundal
TP scheme
Zundal
Final / sub plot
-
Authority
Ahmedabad Urban Development Authority
Covered area
716.17 sq m
Open area
1348.43 sq m
Land cost
₹0.38 Cr
Estimated cost
₹10 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/AUDA/170731/000167
Covered parking
1 · 1024.39 sq m
Parking for sale
1

Escrow account

Bank
Kalupur Commercial Co-operative Bank Ltd.
Branch
ASHRAM ROAD BRANCH
IFSC
KCCB0ASR010
Account
XXXX-0007
Deposited
₹3.51 Cr
Withdrawn
₹3.35 Cr
Closing
₹0.47 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
RAKESH PRAJAPATI
Site visit
2019-09-30
Form-1 PDF
Open file
  • Block BLOCK A100%
  • Block BLOCK B100%
Phase actual dates (2 blocks)
  • Block BLOCK B: excavation — → slab —
  • Block BLOCK A: excavation — → slab —

Filing PDFs

Project team on record

  • JAYESH D DESAI · engineer
  • PARESH M CHAVADA · architect
How is the paperwork score calculated?77 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    22 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2019-12-31 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 8/9 -> 22/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: QPR filing rate 88.9% is below 90%; no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA00283/280917

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.