Capitol Flora And Capitol Icon 2
Capitol Flora
Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA00503/A1M/EX1/260619
Paperwork score
Material gaps
A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.
Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.
Project at a glance
- Developer
- Kalp Infrastructure Private Limited
- Project type
- Mixed Development
- Total units
- 128
- Project cost
- ₹48.27 Cr
- Carpet area
- 4,239.8 sq m
- Price band
- ₹6L – ₹0L
- Carpet area per unit
- 29.02-53.18 sq m
- Status
- Ongoing
Filing extras — blocks, inventory lines, dates
- Mixed Development — 128 units · carpet 4,239.8 sq m
- Block Block A
- Block Block B
- Block Block C
- Block Block D
- Block Block K
- Block Block I
- Declared start 2015-06-10 · completion 2019-12-31
- Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised
Location
23.1856° N, 72.6180° E
Units & inventory
128
Total units
114
Booked (89%)
14
Unsold (11%)
89% booked · 11% unsold
17 booked (85%) · 3 available (15%)
20 booked (100%) · 0 available (0%)
20 booked (100%) · 0 available (0%)
18 booked (90%) · 2 available (10%)
21 booked (75%) · 7 available (25%)
18 booked (90%) · 2 available (10%)
Flat-level inventory (128 units)
| Flat | Block | Carpet m² | Status |
|---|---|---|---|
| A 11 | Block A | 32.7 | BOOKED |
| A 12 | Block A | 32.7 | BOOKED |
| A 13 | Block A | 32.7 | BOOKED |
| A 14 | Block A | 32.7 | UNBOOKED |
| A 21 | Block A | 32.7 | BOOKED |
| A 22 | Block A | 32.7 | BOOKED |
| A 23 | Block A | 32.7 | BOOKED |
| A 24 | Block A | 32.7 | BOOKED |
| A 31 | Block A | 32.7 | BOOKED |
| A 32 | Block A | 32.7 | BOOKED |
| A 33 | Block A | 32.7 | BOOKED |
| A 34 | Block A | 32.7 | BOOKED |
| A 41 | Block A | 32.7 | BOOKED |
| A 42 | Block A | 32.7 | UNBOOKED |
| A 43 | Block A | 32.7 | UNBOOKED |
| A 44 | Block A | 32.7 | BOOKED |
| A 51 | Block A | 32.7 | BOOKED |
| A 52 | Block A | 32.7 | BOOKED |
| A 53 | Block A | 32.7 | BOOKED |
| A 54 | Block A | 32.7 | BOOKED |
| B 11 | Block B | 32.7 | BOOKED |
| B 12 | Block B | 32.7 | BOOKED |
| B 13 | Block B | 32.7 | BOOKED |
| B 14 | Block B | 32.7 | BOOKED |
| B 21 | Block B | 32.7 | BOOKED |
| B 22 | Block B | 32.7 | BOOKED |
| B 23 | Block B | 32.7 | BOOKED |
| B 24 | Block B | 32.7 | BOOKED |
| B 31 | Block B | 32.7 | BOOKED |
| B 32 | Block B | 32.7 | BOOKED |
| B 33 | Block B | 32.7 | BOOKED |
| B 34 | Block B | 32.7 | BOOKED |
| B 41 | Block B | 32.7 | BOOKED |
| B 42 | Block B | 32.7 | BOOKED |
| B 43 | Block B | 32.7 | BOOKED |
| B 44 | Block B | 32.7 | BOOKED |
| B 51 | Block B | 32.7 | BOOKED |
| B 52 | Block B | 32.7 | BOOKED |
| B 53 | Block B | 32.7 | BOOKED |
| B 54 | Block B | 32.7 | BOOKED |
| C 11 | Block C | 32.7 | BOOKED |
| C 12 | Block C | 32.7 | BOOKED |
| C 13 | Block C | 32.7 | BOOKED |
| C 14 | Block C | 32.7 | BOOKED |
| C 21 | Block C | 32.7 | BOOKED |
| C 22 | Block C | 32.7 | BOOKED |
| C 23 | Block C | 32.7 | BOOKED |
| C 24 | Block C | 32.7 | BOOKED |
| C 31 | Block C | 32.7 | BOOKED |
| C 32 | Block C | 32.7 | BOOKED |
| C 33 | Block C | 32.7 | BOOKED |
| C 34 | Block C | 32.7 | BOOKED |
| C 41 | Block C | 32.7 | BOOKED |
| C 42 | Block C | 32.7 | BOOKED |
| C 43 | Block C | 32.7 | BOOKED |
| C 44 | Block C | 32.7 | BOOKED |
| C 51 | Block C | 32.7 | BOOKED |
| C 52 | Block C | 32.7 | BOOKED |
| C 53 | Block C | 32.7 | BOOKED |
| C 54 | Block C | 32.7 | BOOKED |
| D 11 | Block D | 32.7 | BOOKED |
| D 12 | Block D | 32.7 | BOOKED |
| D 13 | Block D | 32.7 | UNBOOKED |
| D 14 | Block D | 32.7 | UNBOOKED |
| D 21 | Block D | 32.7 | BOOKED |
| D 22 | Block D | 32.7 | BOOKED |
| D 23 | Block D | 32.7 | BOOKED |
| D 24 | Block D | 32.7 | BOOKED |
| D 31 | Block D | 32.7 | BOOKED |
| D 32 | Block D | 32.7 | BOOKED |
| D 33 | Block D | 32.7 | BOOKED |
| D 34 | Block D | 32.7 | BOOKED |
| D 41 | Block D | 32.7 | BOOKED |
| D 42 | Block D | 32.7 | BOOKED |
| D 43 | Block D | 32.7 | BOOKED |
| D 44 | Block D | 32.7 | BOOKED |
| D 51 | Block D | 32.7 | BOOKED |
| D 52 | Block D | 32.7 | BOOKED |
| D 53 | Block D | 32.7 | BOOKED |
| D 54 | Block D | 32.7 | BOOKED |
| I 11 | Block I | 32.7 | BOOKED |
| I 12 | Block I | 32.7 | BOOKED |
| I 13 | Block I | 32.7 | BOOKED |
| I 14 | Block I | 32.7 | BOOKED |
| I 21 | Block I | 32.7 | BOOKED |
| I 22 | Block I | 32.7 | BOOKED |
| I 23 | Block I | 32.7 | BOOKED |
| I 24 | Block I | 32.7 | BOOKED |
| I 31 | Block I | 32.7 | BOOKED |
| I 32 | Block I | 32.7 | BOOKED |
| I 33 | Block I | 32.7 | BOOKED |
| I 34 | Block I | 32.7 | BOOKED |
| I 41 | Block I | 32.7 | BOOKED |
| I 42 | Block I | 32.7 | BOOKED |
| I 43 | Block I | 32.7 | BOOKED |
| I 44 | Block I | 32.7 | BOOKED |
| I 51 | Block I | 32.7 | UNBOOKED |
| I 52 | Block I | 32.7 | UNBOOKED |
| I 53 | Block I | 32.7 | BOOKED |
| I 54 | Block I | 32.7 | BOOKED |
| FF 11 | Block K | 43.25 | UNBOOKED |
| FF 12 | Block K | 29.02 | UNBOOKED |
| FF 13 | Block K | 29.02 | UNBOOKED |
| FF 14 | Block K | 29.02 | UNBOOKED |
| FF 15 | Block K | 29.02 | UNBOOKED |
| FF 16 | Block K | 29.02 | UNBOOKED |
| FF 17 | Block K | 39.29 | UNBOOKED |
| GF 1 | Block K | 53.18 | BOOKED |
| GF 2 | Block K | 38.95 | BOOKED |
| GF 3 | Block K | 38.95 | BOOKED |
| GF 4 | Block K | 38.95 | BOOKED |
| GF 5 | Block K | 38.95 | BOOKED |
| GF 6 | Block K | 38.95 | BOOKED |
| GF 7 | Block K | 38.95 | BOOKED |
| SF 21 | Block K | 43.25 | BOOKED |
| SF 22 | Block K | 29.02 | BOOKED |
| SF 23 | Block K | 29.02 | BOOKED |
| SF 24 | Block K | 29.02 | BOOKED |
| SF 25 | Block K | 29.02 | BOOKED |
| SF 26 | Block K | 29.02 | BOOKED |
| SF 27 | Block K | 39.29 | BOOKED |
| TF 31 | Block K | 43.25 | BOOKED |
| TF 32 | Block K | 29.02 | BOOKED |
| TF 33 | Block K | 29.02 | BOOKED |
| TF 34 | Block K | 29.02 | BOOKED |
| TF 35 | Block K | 29.02 | BOOKED |
| TF 36 | Block K | 29.02 | BOOKED |
| TF 37 | Block K | 39.29 | BOOKED |
Booking status as filed — confirm availability with the builder.
Construction progress
Reported completion: 75.39%6 quarterly returns · March 2018 (88.96%) to January 2020 (75.39%)
88.96%
Initial progress · March 2018
75.39%
Final progress · January 2020
Builder-declared quarterly returns — not an independent inspection.
RERA activity timeline
2017
Registration
2018
Alteration
2019
Extension · Annual Compliance
2021
Complaint
Undated
Annual Compliance
2026
Snapshot reviewed
Full application ledger (6 rows)
- Registration — 2017-10-18 16:44:12.000000
- Alteration — 2018-09-28 16:43:17.000000
- Extension — 2019-06-26 14:31:34
- Complaint — 2021-02-08 15:45:50 · GJ/CMP/NCQR/Gandhinagar/201026/0066 (CLOSED)
- Annual Compliance — undated
- Annual Compliance — 2019-10-31 12:47:22
Quarterly filing history
2018
Q-1 · Q-2 · Q-3 · Q-4
—
X-1 · X-2 · X-4
2019
X-3
2020
Q-E
6 submitted · 3 missing
Documents on file
39 documentsMissing from this record: Registration certificate, Title clearance certificate, Title report.
Registration (0)Registration certificate
- None on this record.
Land & title (2)Title · EC · Clearance
2 of 2 open directly
Approvals (6)Plans · CC · NOCs
- Commencement certificate
- Sanctioned plan
- Approved layout plan
- Approved building plan
- Area development plan
- NOCs from authorities
6 of 6 open directly
Builder finances (22)Accounts · ITR · Audit reports
- Auditor's report (1 of 3)
- Auditor's report (2 of 3)
- Auditor's report (3 of 3)
- Director's report (1 of 3)
- Director's report (2 of 3)
- Director's report (3 of 3)
- Income-tax return (1 of 3)
- Income-tax return (2 of 3)
- Income-tax return (3 of 3)
- PAN card
- auditedBalSheetDoc1
- auditedBalSheetDoc2_
- auditedBalSheetDoc3
- auditedProfitLossSheetDoc1
- auditedProfitLossSheetDoc2
- auditedProfitLossSheetDoc3
- auditedReportDoc1
- auditedReportDoc2
- auditedReportDoc3
- cashFlowStmtFileDoc1
- cashFlowStmtFileDoc2
- cashFlowStmtFileDoc3
22 of 22 open directly
Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.
View documents on GujRERASearch PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA00503/A1M/EX1/260619 → Documents tab
Filing depth
Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.
Land & money
- Village (moje)
- Sargasan
- TP scheme
- Sargasan- Kudasan-Por
- Final / sub plot
- -
- Authority
- Gandhinagar Urban Development Authority
- Covered area
- 2610 sq m
- Open area
- 4485 sq m
- Land cost
- ₹8.27 Cr
- Estimated cost
- ₹36 Cr
- BU permission
- Completion certificate
- Registration cert
- Portal file
- Ack no.
- PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/170926/002790
- Covered parking
- 320 · 6576 sq m
- Parking for sale
- 60
Escrow account
- Bank
- Yes Bank
- Branch
- C G ROAD BRANCH
- IFSC
- YESB0000007
- Account
- XXXX-0207
- Deposited
- ₹5.54 Cr
- Withdrawn
- ₹5.56 Cr
- Closing
- ₹0.01 Cr
- Status
- APPROVED
Inspection phases (Form-1)
- Architect
- DIPAN APPA
- Site visit
- 2019-12-25
- Form-1 PDF
- Open file
- Block Block A100%
- Block Block B100%
- Block Block C100%
- Block Block D100%
- Block Block E Removed as per authority order on Promoter Request36%
- Block Block F Removed as per authority order on Promoter Request36%
- Block Block G Removed as per authority order on Promoter Request30%
- Block Block H Removed as per authority order on Promoter Request30%
- Block Block I100%
- Block Block J Removed as per authority order on Promoter Request49.5%
- Block Block K100%
Phase actual dates (11 blocks)
- Block Block K: excavation — → slab —
- Block Block A: excavation — → slab —
- Block Block B: excavation — → slab —
- Block Block C: excavation — → slab —
- Block Block D: excavation — → slab —
- Block Block E Removed as per authority order on Promoter Request: excavation — → slab —
- Block Block F Removed as per authority order on Promoter Request: excavation — → slab —
- Block Block G Removed as per authority order on Promoter Request: excavation — → slab —
- Block Block H Removed as per authority order on Promoter Request: excavation — → slab —
- Block Block I: excavation — → slab —
- Block Block J Removed as per authority order on Promoter Request: excavation — → slab —
Filing PDFs
- REG_PROCESS · 2017-09-26 — · Form-2
- ALT_PROCESS · 2018-05-19 — Form-1 ·
- EXT_PROCESS · 2019-05-27 — Form-1 · Form-2
- Q-1 · 2018-04-18 — Form-1 · Form-2
- Q-2 · 2018-05-02 — Form-1 · Form-2
- Q-3 · 2018-08-06 — Form-1 · Form-2
- Q-4 · 2018-11-07 — Form-1 · Form-2
- X-3 · 2019-08-07 — Form-1 · Form-2
- Q-E · 2020-11-23 — Form-1 · Form-2
- Form-5 · 2017-18 · SUBMITTED — Audit file
- Form-5 · 2018-19 · SUBMITTED — Audit file
- Form-5 · 2019-20 · EXEMPT —
Project team on record
- NARESH K SHAH · engineer
- DIPAN APPA · architect
How is the paperwork score calculated?24 / 100
Delivery standing
0 / 40
Filing discipline
17 / 25
Promoter track record
0 / 20
Complaints and extensions
7 / 15
- Delivery 2019-12-31 elapsed 6 yr ago, progress 75.39% -> 0/40
- QPR filings 6/9 -> 17/25
- Promoter completed projects 0 -> 0/20
- Red flags 1 complaint + 1 extension -> 7/15
Confidence Medium: declared completion date elapsed 6 years ago with work still declared incomplete; QPR filing rate 66.7% is below 90%; no completed project on the promoter record; 1 complaint entry on the ledger; 1 extension request on the ledger.
Verify this yourself
If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:
PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA00503/A1M/EX1/260619
Open this project on GujRERARun the manual check →Sources
Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.
- MoHUA - Real Estate Regulatory Authorities of States / UTsThe national index of every state/UT RERA portal. Fallback when a state link moves.
- GujRERA - Gujarat Real Estate Regulatory AuthorityGujarat project / agent / complaint search and registrations.