Sangath Life
K ROAD NEAR GIDC
Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA03585/EX1/260219
Paperwork score
Material gaps
A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.
Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.
Project at a glance
- Developer
- Sanyam Infrastructure
- Project type
- Residential / Group Housing
- Total units
- 105
- Project cost
- ₹22 Cr
- Carpet area
- 5,510.2 sq m
- Price band
- ₹10L – ₹0L
- Carpet area per unit
- 51.46-53.44 sq m
- Status
- Ongoing
Filing extras — blocks, inventory lines, dates
- Residential/Group Housing — 105 units · carpet 5,510.22 sq m
- Block A
- Block B
- Block C
- Block D
- Block E
- Block F
- Block G
- Block H
- Block I
- Declared start 2012-09-28 · completion 2020-02-18
- Professionals on record: 0 architect(s), 0 engineer(s) · land not itemised
Location
23.2353° N, 72.6236° E
Units & inventory
105
Total units
69
Booked (66%)
36
Unsold (34%)
66% booked · 34% unsold
8 booked (67%) · 4 available (33%)
8 booked (67%) · 4 available (33%)
9 booked (75%) · 3 available (25%)
7 booked (58%) · 5 available (42%)
11 booked (92%) · 1 available (8%)
9 booked (75%) · 3 available (25%)
7 booked (58%) · 5 available (42%)
5 booked (42%) · 7 available (58%)
5 booked (56%) · 4 available (44%)
Flat-level inventory (105 units)
| Flat | Block | Carpet m² | Status |
|---|---|---|---|
| 101 | A | 51.46 | BOOKED |
| 102 | A | 53.44 | BOOKED |
| 103 | A | 53.44 | UNBOOKED |
| 104 | A | 51.46 | BOOKED |
| 201 | A | 51.46 | BOOKED |
| 202 | A | 53.44 | BOOKED |
| 203 | A | 53.44 | BOOKED |
| 204 | A | 51.46 | BOOKED |
| 301 | A | 51.46 | UNBOOKED |
| 302 | A | 53.44 | UNBOOKED |
| 303 | A | 53.44 | UNBOOKED |
| 304 | A | 51.46 | BOOKED |
| 101 | B | 51.46 | UNBOOKED |
| 102 | B | 53.44 | UNBOOKED |
| 103 | B | 53.44 | UNBOOKED |
| 104 | B | 51.46 | BOOKED |
| 201 | B | 51.46 | BOOKED |
| 202 | B | 53.44 | BOOKED |
| 203 | B | 53.44 | BOOKED |
| 204 | B | 51.46 | BOOKED |
| 301 | B | 51.46 | UNBOOKED |
| 302 | B | 53.44 | BOOKED |
| 303 | B | 53.44 | BOOKED |
| 304 | B | 51.46 | BOOKED |
| 101 | C | 51.46 | BOOKED |
| 102 | C | 53.44 | BOOKED |
| 103 | C | 53.44 | UNBOOKED |
| 104 | C | 51.46 | BOOKED |
| 201 | C | 51.46 | BOOKED |
| 202 | C | 53.44 | BOOKED |
| 203 | C | 53.44 | UNBOOKED |
| 204 | C | 51.46 | BOOKED |
| 301 | C | 51.46 | BOOKED |
| 302 | C | 53.44 | BOOKED |
| 303 | C | 53.44 | UNBOOKED |
| 304 | C | 51.46 | BOOKED |
| 101 | D | 51.46 | BOOKED |
| 102 | D | 53.44 | BOOKED |
| 103 | D | 53.44 | UNBOOKED |
| 104 | D | 51.46 | BOOKED |
| 201 | D | 51.46 | BOOKED |
| 202 | D | 53.44 | UNBOOKED |
| 203 | D | 53.44 | BOOKED |
| 204 | D | 51.46 | BOOKED |
| 301 | D | 51.46 | UNBOOKED |
| 302 | D | 53.44 | UNBOOKED |
| 303 | D | 53.44 | UNBOOKED |
| 304 | D | 51.46 | BOOKED |
| 101 | E | 51.46 | BOOKED |
| 102 | E | 53.44 | BOOKED |
| 103 | E | 53.44 | BOOKED |
| 104 | E | 51.46 | BOOKED |
| 201 | E | 51.46 | BOOKED |
| 202 | E | 53.44 | BOOKED |
| 203 | E | 53.44 | BOOKED |
| 204 | E | 51.46 | BOOKED |
| 301 | E | 51.46 | BOOKED |
| 302 | E | 53.44 | UNBOOKED |
| 303 | E | 53.44 | BOOKED |
| 304 | E | 51.46 | BOOKED |
| 101 | F | 51.46 | BOOKED |
| 102 | F | 53.44 | BOOKED |
| 103 | F | 53.44 | BOOKED |
| 104 | F | 51.46 | BOOKED |
| 201 | F | 51.46 | BOOKED |
| 202 | F | 53.44 | BOOKED |
| 203 | F | 53.44 | BOOKED |
| 204 | F | 51.46 | BOOKED |
| 301 | F | 51.46 | BOOKED |
| 302 | F | 53.44 | UNBOOKED |
| 303 | F | 53.44 | UNBOOKED |
| 304 | F | 51.46 | UNBOOKED |
| 101 | G | 51.46 | UNBOOKED |
| 102 | G | 53.44 | UNBOOKED |
| 103 | G | 53.44 | BOOKED |
| 104 | G | 51.46 | BOOKED |
| 201 | G | 51.46 | BOOKED |
| 202 | G | 53.44 | UNBOOKED |
| 203 | G | 53.44 | BOOKED |
| 204 | G | 51.46 | BOOKED |
| 301 | G | 51.46 | UNBOOKED |
| 302 | G | 53.44 | UNBOOKED |
| 303 | G | 53.44 | BOOKED |
| 304 | G | 51.46 | BOOKED |
| 101 | H | 51.46 | UNBOOKED |
| 102 | H | 53.44 | BOOKED |
| 103 | H | 53.44 | UNBOOKED |
| 104 | H | 51.46 | UNBOOKED |
| 201 | H | 51.46 | BOOKED |
| 202 | H | 53.44 | UNBOOKED |
| 203 | H | 53.44 | BOOKED |
| 204 | H | 51.46 | UNBOOKED |
| 301 | H | 51.46 | BOOKED |
| 302 | H | 53.44 | BOOKED |
| 303 | H | 53.44 | UNBOOKED |
| 304 | H | 51.46 | UNBOOKED |
| 101 | I | 53.44 | UNBOOKED |
| 102 | I | 51.46 | BOOKED |
| 103 | I | 53.44 | BOOKED |
| 201 | I | 53.44 | UNBOOKED |
| 202 | I | 51.46 | UNBOOKED |
| 203 | I | 53.44 | UNBOOKED |
| 301 | I | 53.44 | BOOKED |
| 302 | I | 51.46 | BOOKED |
| 303 | I | 53.44 | BOOKED |
Booking status as filed — confirm availability with the builder.
Construction progress
Reported completion: 87.25%3 quarterly returns · March 2019 (100%) to March 2020 (87.25%)
100%
Initial progress · March 2019
87.25%
Final progress · March 2020
Builder-declared quarterly returns — not an independent inspection.
RERA activity timeline
2018
Registration
2019
Extension · Annual Compliance
2021
Annual Compliance
2023
Complaint
2026
Snapshot reviewed
Full application ledger (5 rows)
- Registration — 2018-10-04 17:35:48.000000
- Extension — 2019-02-26 17:30:44
- Complaint — 2023-01-10 17:30:12 · CMP1406202200294 (CLOSED)
- Annual Compliance — 2019-10-14 10:04:27
- Annual Compliance — 2021-01-29 16:03:36
Quarterly filing history
2019
Q-1 · X-1 · Q-E
—
X-2 · X-3 · X-4
3 submitted · 3 missing
Documents on file
39 documentsMissing from this record: Registration certificate, Title clearance certificate, Title report.
Registration (0)Registration certificate
- None on this record.
Land & title (2)Title · EC · Clearance
2 of 2 open directly
Approvals (6)Plans · CC · NOCs
- Commencement certificate
- Sanctioned plan
- Approved layout plan
- Approved building plan
- Area development plan
- NOCs from authorities
6 of 6 open directly
Builder finances (22)Accounts · ITR · Audit reports
- Auditor's report (1 of 3)
- Auditor's report (2 of 3)
- Auditor's report (3 of 3)
- Director's report (1 of 3)
- Director's report (2 of 3)
- Director's report (3 of 3)
- Income-tax return (1 of 3)
- Income-tax return (2 of 3)
- Income-tax return (3 of 3)
- PAN card
- auditedBalSheetDoc1
- auditedBalSheetDoc2_
- auditedBalSheetDoc3
- auditedProfitLossSheetDoc1
- auditedProfitLossSheetDoc2
- auditedProfitLossSheetDoc3
- auditedReportDoc1
- auditedReportDoc2
- auditedReportDoc3
- cashFlowStmtFileDoc1
- cashFlowStmtFileDoc2
- cashFlowStmtFileDoc3
22 of 22 open directly
Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.
View documents on GujRERASearch PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA03585/EX1/260219 → Documents tab
Filing depth
Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.
Land & money
- Village (moje)
- Vavol
- TP scheme
- Vavol
- Authority
- Gandhinagar Urban Development Authority
- Covered area
- 2383 sq m
- Open area
- 573 sq m
- Land cost
- ₹3 Cr
- Estimated cost
- ₹19 Cr
- BU permission
- Registration cert
- Portal file
- Ack no.
- PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/170928/002878
- Covered parking
- 1 · 2624 sq m
- Parking for sale
- 0
Escrow account
- Bank
- STATE BANK OF INDIA
- Branch
- IIT GANDHINAGAR
- IFSC
- SBIN0011770
- Account
- XXXX-9247
- Status
- APPROVED
Inspection phases (Form-1)
- Architect
- DHAVAL MEWADA
- Site visit
- 2019-06-30
- Form-1 PDF
- Open file
- Block A85%
- Block B85%
- Block C85%
- Block D85%
- Block E85%
- Block F85%
- Block G85%
- Block H85%
- Block I85%
Phase actual dates (9 blocks)
- Block A: excavation — → slab —
- Block B: excavation — → slab —
- Block C: excavation — → slab —
- Block D: excavation — → slab —
- Block E: excavation — → slab —
- Block F: excavation — → slab —
- Block G: excavation — → slab —
- Block H: excavation — → slab —
- Block I: excavation — → slab —
Filing PDFs
- REG_PROCESS · 2017-09-28 — ·
- EXT_PROCESS · 2019-02-16 — Form-1 · Form-2
- Q-1 · 2019-02-06 — Form-1 · Form-2
- X-1 · 2019-05-05 — Form-1 · Form-2
- Q-E · 2019-08-07 — Form-1 · Form-2
- Form-5 · 2018-19 · SUBMITTED — Audit file
- Form-5 · 2019-20 · SUBMITTED — Audit file
How is the paperwork score calculated?20 / 100
Delivery standing
0 / 40
Filing discipline
13 / 25
Promoter track record
0 / 20
Complaints and extensions
7 / 15
- Delivery 2020-02-18 elapsed 6 yr ago, progress 87.25% -> 0/40
- QPR filings 3/6 -> 13/25
- Promoter completed projects 0 -> 0/20
- Red flags 1 complaint + 1 extension -> 7/15
Confidence Medium: declared completion date elapsed 6 years ago with work still declared incomplete; QPR filing rate 50.0% is below 90%; no completed project on the promoter record; 1 complaint entry on the ledger; 1 extension request on the ledger.
Verify this yourself
If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:
PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA03585/EX1/260219
Open this project on GujRERARun the manual check →Sources
Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.
- MoHUA - Real Estate Regulatory Authorities of States / UTsThe national index of every state/UT RERA portal. Fallback when a state link moves.
- GujRERA - Gujarat Real Estate Regulatory AuthorityGujarat project / agent / complaint search and registrations.