Delivered

Bansari Elegance

Nr. BJP Kamlam

Mixed Development74 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/4772

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA00983/EX1/240220

Bansari Elegance — residential developmentGandhinagar · representative residential imagery

Paperwork score

Some gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings9 / 14
Recorded complaints1
Extensions1
Promoter projectsNone completed on record

Project at a glance

Developer
Astha Developers
Project type
Mixed Development
Total units
74
Project cost
₹10.96 Cr
Carpet area
5,511.6 sq m
Price band
₹12L – ₹0L
Carpet area per unit
30.34-104.55 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Mixed Development — 74 units · carpet 5,511.63 sq m
  • Block A+B
  • Block C+D
  • Declared start 2017-08-01 · completion 2021-06-30
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.1457° N, 72.6349° E

Filed plot outline · 9 corners
Open in Google Maps

Units & inventory

74

Total units

73

Booked (99%)

1

Unsold (1%)

99% booked · 1% unsold

Tower A+B48 units

47 booked (98%) · 1 available (2%)

Tower C+D26 units

26 booked (100%) · 0 available (0%)

Flat-level inventory (74 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
A102A+B72.03BOOKED
A103A+B72.36BOOKED
A104A+B72.36BOOKED
A105A+B69.78BOOKED
A106A+B70.41BOOKED
A202A+B72.03BOOKED
A203A+B72.36BOOKED
A206A+B70.41BOOKED
A301A+B72.65BOOKED
A302A+B72.03BOOKED
A401A+B72.65BOOKED
A403A+B72.36BOOKED
A404A+B72.36BOOKED
A405A+B69.78BOOKED
A406A+B70.41BOOKED
A502A+B72.03BOOKED
A505A+B69.78BOOKED
A503A+B72.36BOOKED
A606A+B70.41BOOKED
A702A+B72.03BOOKED
A704A+B72.36BOOKED
A705A+B69.78BOOKED
A706A+B70.41BOOKED
Shop 2A+B30.34BOOKED
SHOP 5A+B30.34BOOKED
Shop 6A+B33.32BOOKED
A101A+B72.65BOOKED
A201A+B72.65BOOKED
A204A+B72.36BOOKED
A205A+B69.78BOOKED
A303A+B72.36BOOKED
A304A+B72.36BOOKED
A305A+B69.78BOOKED
A306A+B70.41BOOKED
A402A+B72.03BOOKED
A501A+B72.65BOOKED
A504A+B72.36BOOKED
A506A+B70.41BOOKED
A601A+B72.65BOOKED
A602A+B72.03BOOKED
A603A+B72.36BOOKED
A604A+B72.36BOOKED
A605A+B69.78BOOKED
A701A+B72.65BOOKED
A703A+B72.36UNBOOKED
Shop 1A+B33.32BOOKED
Shop 3A+B32.44BOOKED
Shop 4A+B32.44BOOKED
B101C+D104.55BOOKED
B102C+D94.14BOOKED
B202C+D94.14BOOKED
B203C+D94.14BOOKED
B301C+D104.55BOOKED
B302C+D94.14BOOKED
B303C+D94.14BOOKED
B401C+D104.55BOOKED
B501C+D104.55BOOKED
B503C+D94.14BOOKED
B601C+D104.55BOOKED
B701C+D104.55BOOKED
B702C+D94.14BOOKED
B703C+D94.14BOOKED
B103C+D94.14BOOKED
B201C+D104.55BOOKED
B402C+D94.14BOOKED
B403C+D94.14BOOKED
B502C+D94.14BOOKED
B602C+D94.14BOOKED
B603C+D94.14BOOKED
Shop 7C+D42.86BOOKED
Shop 8C+D56.3BOOKED
Shop 9C+D64.17BOOKED
Shop 10C+D56.3BOOKED
Shop 11C+D42.86BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%2018201920202021May 2018 — 32.67% builtAugust 2018 — 41.82% builtNovember 2018 — 46.98% builtFebruary 2019 — 61.8% builtMay 2019 — 73.15% builtAugust 2019 — 76.96% builtNovember 2019 — 85.4% builtAugust 2020 — 100% builtJuly 2021 — 100% built

9 quarterly returns · May 2018 (32.67%) to July 2021 (100%)

32.67%

Initial progress · May 2018

100%

Final progress · July 2021

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2017

    Registration

  2. 2019

    Annual Compliance

  3. 2020

    Extension

  4. 2021

    Annual Compliance

  5. 2024

    Complaint

  6. Undated

    Annual Compliance · BCR

  7. 2026

    Snapshot reviewed

Full application ledger (8 rows)
  1. Registration — 2017-12-12 15:21:55.000000
  2. Extension — 2020-02-24 17:58:55
  3. Complaint — 2024-12-21 14:54:50 · CMP0409202301106 (CLOSED)
  4. Annual Compliance — undated
  5. Annual Compliance — 2019-10-15 20:43:09
  6. Annual Compliance — 2021-01-30 16:00:01
  7. Annual Compliance — undated
  8. BCR — undated

Quarterly filing history

2018

Q-1 · Q-2 · Q-3

2019

Q-4 · Q-5 · Q-6 · Q-7

—

X-1 · X-2 · X-4 · X-5 · X-6

2020

X-3 · Q-E

9 submitted · 5 missing

Documents on file

39 documents

Missing from this record: Registration certificate, Title clearance certificate, Title report.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA00983/EX1/240220 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Kudasan
TP scheme
Kudasan-Koba
Authority
Gandhinagar Urban Development Authority
Covered area
964.44 sq m
Open area
1534.56 sq m
Land cost
₹1.61 Cr
Estimated cost
₹8.5 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/171124/004048
Covered parking
75 · 1995 sq m
Parking for sale
25

Escrow account

Bank
HDFC
Branch
NARODA
IFSC
HDFC0000958
Account
XXXX-3822
Closing
₹0 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
URVASHI TULI
Site visit
2020-06-26
Form-1 PDF
Open file
  • Block A+B100%
  • Block C+D100%
Phase actual dates (2 blocks)
  • Block A+B: excavation — → slab —
  • Block C+D: excavation — → slab —

Filing PDFs

Project team on record

  • Amee Associates · engineer
  • The Grid Architects · architect
How is the paperwork score calculated?63 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    16 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    7 / 15

  • Delivery 2021-06-30 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 9/14 -> 16/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 1 complaint + 1 extension -> 7/15

Confidence Medium: QPR filing rate 64.3% is below 90%; no completed project on the promoter record; 1 complaint entry on the ledger; 1 extension request on the ledger.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA00983/EX1/240220

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.