Delivered

Sneh Kunj Elegance

Sneh kunj Elegance, B/h-Shivalay Parisar

ResidentialGroup Housing62 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/5148

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA01365/200118

Sneh Kunj Elegance — residential developmentGandhinagar · representative residential imagery

Paperwork score

Some gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings9 / 11
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Sneh Corporation
Project type
Residential / Group Housing
Total units
62
Project cost
₹11.5 Cr
Carpet area
6,324 sq m
Price band
₹17L – ₹0L
Carpet area per unit
95.26-125.11 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Residential/Group Housing — 62 units · carpet 6,324.02 sq m
  • Block A
  • Block B
  • Block C
  • Declared start 2017-07-19 · completion 2020-09-30
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.1779° N, 72.6310° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

62

Total units

53

Booked (85%)

9

Unsold (15%)

85% booked · 15% unsold

Tower A24 units

22 booked (92%) · 2 available (8%)

Tower B24 units

22 booked (92%) · 2 available (8%)

Tower C14 units

9 booked (64%) · 5 available (36%)

Flat-level inventory (62 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
A101A95.26BOOKED
A102A95.26BOOKED
A103A95.26BOOKED
A104A95.26BOOKED
A201A95.26BOOKED
A202A95.26UNBOOKED
A203A95.26BOOKED
A204A95.26BOOKED
A301A95.26BOOKED
A302A95.26BOOKED
A303A95.26BOOKED
A304A95.26BOOKED
A401A95.26BOOKED
A402A95.26BOOKED
A403A95.26BOOKED
A404A95.26BOOKED
A501A95.26BOOKED
A502A95.26BOOKED
A503A95.26BOOKED
A504A95.26BOOKED
A601A95.26BOOKED
A602A95.26BOOKED
A603A95.26BOOKED
A604A95.26UNBOOKED
B101B95.26BOOKED
B102B95.26BOOKED
B103B95.26BOOKED
B104B95.26BOOKED
B201B95.26BOOKED
B202B95.26BOOKED
B203B95.26BOOKED
B204B95.26BOOKED
B301B95.26BOOKED
B302B95.26BOOKED
B303B95.26BOOKED
B304B95.26BOOKED
B401B95.26BOOKED
B402B95.26BOOKED
B403B95.26BOOKED
B404B95.26BOOKED
B501B95.26BOOKED
B502B95.26UNBOOKED
B503B95.26BOOKED
B504B95.26BOOKED
B601B95.26UNBOOKED
B602B95.26BOOKED
B603B95.26BOOKED
B604B95.26BOOKED
C101C125.11BOOKED
C102C125.11UNBOOKED
C201C125.11BOOKED
C202C125.11BOOKED
C301C125.11BOOKED
C302C125.11BOOKED
C401C125.11BOOKED
C402C125.11UNBOOKED
C501C125.11BOOKED
C502C125.11BOOKED
C601C125.11UNBOOKED
C602C125.11UNBOOKED
C701C125.11BOOKED
C702C125.11UNBOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%201820192020June 2018 — 43% builtSeptember 2018 — 51.71% builtDecember 2018 — 59.41% builtMarch 2019 — 69.95% builtJune 2019 — 77.56% builtSeptember 2019 — 100% builtDecember 2019 — 100% builtMarch 2020 — 100% builtOctober 2020 — 100% built

9 quarterly returns · June 2018 (43%) to October 2020 (100%)

43%

Initial progress · June 2018

100%

Final progress · October 2020

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2018

    Registration

  2. 2019

    Annual Compliance

  3. Undated

    Annual Compliance

  4. 2026

    Snapshot reviewed

Full application ledger (3 rows)
  1. Registration — 2018-01-20 18:06:17.000000
  2. Annual Compliance — undated
  3. Annual Compliance — 2019-10-20 15:48:15

Quarterly filing history

2018

Q-1 · Q-2

2019

Q-3 · Q-4 · Q-5 · Q-6

2020

Q-7 · Q-8 · Q-E

—

Q-9 · Q-10

9 submitted · 2 missing

Documents on file

39 documents

Missing from this record: Registration certificate, Title clearance certificate, Title report.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA01365/200118 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Kudasan
TP scheme
( Kudasan -Sargasan-Dhotakuva-por )
Final / sub plot
-
Authority
Gandhinagar Urban Development Authority
Covered area
1256.93 sq m
Open area
1937.07 sq m
Land cost
₹3.5 Cr
Estimated cost
₹8 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/171230/004378
Covered parking
3 · 1256.93 sq m
Parking for sale
0

Escrow account

Bank
Corporation Bank
Branch
VIJAPUR BRANCH
IFSC
CORP0001372
Account
XXXX-8307
Closing
₹0.25 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
KAPIL R MODI
Site visit
2019-10-31
Form-1 PDF
Open file
  • Block A100%
  • Block B100%
  • Block C100%
Phase actual dates (3 blocks)
  • Block A: excavation — → slab —
  • Block B: excavation — → slab —
  • Block C: excavation — → slab —

Filing PDFs

Project team on record

  • Himanshu Patel · engineer
  • Kapil R. Modi · architect
How is the paperwork score calculated?75 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    20 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2020-09-30 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 9/11 -> 20/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: QPR filing rate 81.8% is below 90%; no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA01365/200118

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.