Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Delivered

Madhav Bugalows

Madhav Bungalows, Nr. Gayatri Mandir

ResidentialGroup Housing52 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/5854

Filing PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA02745/300518

Madhav Bugalows — residential developmentGandhinagar · representative residential imagery

Paperwork score

Some gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings7 / 8
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Madhav Corporation
Project type
Residential / Group Housing
Total units
52
Project cost
₹13.35 Cr
Carpet area
4,553.7 sq m
Price band
₹28L – ₹0L
Carpet area per unit
82.7-90.91 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Residential/Group Housing — 52 units · carpet 4,553.68 sq m
  • Block TYPE-C
  • Block TYPE-B
  • Block TYPE-D
  • Block TYPE-A
  • Declared start 2016-06-01 · completion 2020-03-31
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.2490° N, 72.4831° E

Filed plot outline · 6 corners
Open in Google Maps

Units & inventory

52

Total units

52

Booked (100%)

0

Unsold (0%)

100% booked · 0% unsold

Tower TYPE-C12 units

12 booked (100%) · 0 available (0%)

Tower TYPE-B8 units

8 booked (100%) · 0 available (0%)

Tower TYPE-D8 units

8 booked (100%) · 0 available (0%)

Tower TYPE-A24 units

24 booked (100%) · 0 available (0%)

Flat-level inventory (52 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
A-29TYPE-A90.91BOOKED
A-30TYPE-A90.91BOOKED
A-31TYPE-A90.91BOOKED
A-32TYPE-A90.91BOOKED
A-33TYPE-A90.91BOOKED
A-34TYPE-A90.91BOOKED
A-35TYPE-A90.91BOOKED
A-36TYPE-A90.91BOOKED
A-37TYPE-A90.91BOOKED
A-38TYPE-A90.91BOOKED
A-39TYPE-A90.91BOOKED
A-40TYPE-A90.91BOOKED
A-1-41TYPE-A90.25BOOKED
A-1-42TYPE-A90.25BOOKED
A-1-43TYPE-A90.25BOOKED
A-1-44TYPE-A90.25BOOKED
A-1-45TYPE-A90.25BOOKED
A-1-46TYPE-A90.25BOOKED
A-1-47TYPE-A90.25BOOKED
A-1-48TYPE-A90.25BOOKED
A-1-49TYPE-A90.25BOOKED
A-1-50TYPE-A90.25BOOKED
A-1-51TYPE-A90.25BOOKED
A-1-52TYPE-A90.25BOOKED
B-13TYPE-B82.7BOOKED
B-14TYPE-B82.7BOOKED
B-15TYPE-B82.7BOOKED
B-16TYPE-B82.7BOOKED
B-25TYPE-B82.7BOOKED
B-26TYPE-B82.7BOOKED
B-27TYPE-B82.7BOOKED
B-28TYPE-B82.7BOOKED
C-1TYPE-C87.8BOOKED
C-2TYPE-C87.8BOOKED
C-3TYPE-C87.8BOOKED
C-4TYPE-C87.8BOOKED
C-5TYPE-C87.8BOOKED
C-6TYPE-C87.8BOOKED
C-7TYPE-C87.8BOOKED
C-8TYPE-C87.8BOOKED
C-9TYPE-C87.8BOOKED
C-10TYPE-C87.8BOOKED
C-11TYPE-C87.8BOOKED
C-12TYPE-C87.8BOOKED
D-17TYPE-D83.07BOOKED
D-18TYPE-D83.07BOOKED
D-19TYPE-D83.07BOOKED
D-20TYPE-D83.07BOOKED
D-21TYPE-D83.07BOOKED
D-22TYPE-D83.07BOOKED
D-23TYPE-D83.07BOOKED
D-24TYPE-D83.07BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%201820192020October 2018 — 93.28% builtJanuary 2019 — 93.28% builtApril 2019 — 96.54% builtJuly 2019 — 99.31% builtOctober 2019 — 99.49% builtJanuary 2020 — 100% builtApril 2020 — 100% built

7 quarterly returns · October 2018 (93.28%) to April 2020 (100%)

93.28%

Initial progress · October 2018

100%

Final progress · April 2020

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2018

    Registration

  2. 2019

    Annual Compliance

  3. 2026

    Snapshot reviewed

Full application ledger (2 rows)
  1. Registration — 2018-05-30 14:17:09.000000
  2. Annual Compliance — 2019-12-14 17:34:54

Quarterly filing history

2018

Q-1 · Q-2

2019

Q-3 · Q-4 · Q-5 · Q-6

—

Q-7

2020

Q-E

7 submitted · 1 missing

Documents on file

39 documents

Missing from this record: Registration certificate, Title clearance certificate, Title report.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA02745/300518 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Kalol
TP scheme
( Kalol-Ola-Borisana )
Authority
Ahmedabad Urban Development Authority
Covered area
3016.83 sq m
Open area
4403.17 sq m
Land cost
₹6.45 Cr
Estimated cost
₹6.9 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/KALOL/AUDA/180329/004988
Parking for sale
0

Escrow account

Bank
Axis Bank
Branch
Kalol
IFSC
UTIB0000452
Account
XXXX-6030
Deposited
₹0.35 Cr
Withdrawn
₹0.35 Cr
Closing
₹0 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
SWATI H MANGE
Site visit
2020-02-29
Form-1 PDF
Open file
  • Block TYPE-A100%
  • Block TYPE-B100%
  • Block TYPE-C100%
  • Block TYPE-D100%
Phase actual dates (4 blocks)
  • Block TYPE-A: excavation — → slab —
  • Block TYPE-B: excavation — → slab —
  • Block TYPE-C: excavation — → slab —
  • Block TYPE-D: excavation — → slab —

Filing PDFs

Project team on record

  • Paresh M Chavda · engineer
  • Praful A Shrimali · architect
How is the paperwork score calculated?77 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    22 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2020-03-31 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 7/8 -> 22/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: QPR filing rate 87.5% is below 90%; no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA02745/300518

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.