Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Delivered

Yash Parisar

Survey No. 408,OP No.11,

ResidentialGroup Housing80 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/5947

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA02539/EX1/200921

Yash Parisar — residential developmentGandhinagar · representative residential imagery

Paperwork score

Some gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings14 / 16
Recorded complaints4
Extensions1
Promoter projectsNone completed on record

Project at a glance

Developer
Riddhi Developer
Project type
Residential / Group Housing
Total units
80
Project cost
₹30.35 Cr
Carpet area
7,291.4 sq m
Price band
₹25L – ₹0L
Carpet area per unit
83.56-96.71 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Residential/Group Housing — 80 units · carpet 7,291.38 sq m
  • Block BLOCK A
  • Block BLOCK B
  • Block BLOCK C
  • Declared start 2017-12-22 · completion 2022-05-31
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.1615° N, 72.6431° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

80

Total units

77

Booked (96%)

3

Unsold (4%)

96% booked · 4% unsold

Tower BLOCK A26 units

25 booked (96%) · 1 available (4%)

Tower BLOCK B26 units

25 booked (96%) · 1 available (4%)

Tower BLOCK C28 units

27 booked (96%) · 1 available (4%)

Flat-level inventory (80 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
A-101BLOCK A96.71BOOKED
A-102BLOCK A96.71BOOKED
A-103BLOCK A96.71BOOKED
A-104BLOCK A96.71BOOKED
A-201BLOCK A96.71BOOKED
A-202BLOCK A96.71BOOKED
A-203BLOCK A96.71BOOKED
A-204BLOCK A96.71BOOKED
A-301BLOCK A96.71BOOKED
A-302BLOCK A96.71BOOKED
A-303BLOCK A96.71BOOKED
A-304BLOCK A96.71BOOKED
A-401BLOCK A96.71BOOKED
A-402BLOCK A96.71BOOKED
A-403BLOCK A96.71BOOKED
A-404BLOCK A96.71BOOKED
A-501BLOCK A96.71BOOKED
A-502BLOCK A96.71BOOKED
A-503BLOCK A96.71BOOKED
A-504BLOCK A96.71BOOKED
A-601BLOCK A96.71BOOKED
A-602BLOCK A96.71BOOKED
A-603BLOCK A96.71BOOKED
A-604BLOCK A96.71BOOKED
A-701BLOCK A96.71UNBOOKED
A-702BLOCK A96.71BOOKED
B-101BLOCK B93.74BOOKED
B-102BLOCK B93.74BOOKED
B-103BLOCK B93.74UNBOOKED
B-104BLOCK B93.74BOOKED
B-201BLOCK B93.74BOOKED
B-202BLOCK B93.74BOOKED
B-203BLOCK B93.74BOOKED
B-204BLOCK B93.74BOOKED
B-301BLOCK B93.74BOOKED
B-302BLOCK B93.74BOOKED
B-303BLOCK B93.74BOOKED
B-304BLOCK B93.74BOOKED
B-401BLOCK B93.74BOOKED
B-402BLOCK B93.74BOOKED
B-403BLOCK B93.74BOOKED
B-404BLOCK B93.74BOOKED
B-501BLOCK B93.74BOOKED
B-502BLOCK B93.74BOOKED
B-503BLOCK B93.74BOOKED
B-504BLOCK B93.74BOOKED
B-601BLOCK B93.74BOOKED
B-602BLOCK B93.74BOOKED
B-603BLOCK B93.74BOOKED
B-604BLOCK B93.74BOOKED
B-701BLOCK B93.74BOOKED
B-702BLOCK B93.74BOOKED
C-101BLOCK C83.56BOOKED
C-102BLOCK C83.56BOOKED
C-103BLOCK C83.56BOOKED
C-104BLOCK C83.56BOOKED
C-201BLOCK C83.56BOOKED
C-202BLOCK C83.56BOOKED
C-203BLOCK C83.56BOOKED
C-204BLOCK C83.56BOOKED
C-301BLOCK C83.56BOOKED
C-302BLOCK C83.56BOOKED
C-303BLOCK C83.56BOOKED
C-304BLOCK C83.56BOOKED
C-401BLOCK C83.56BOOKED
C-402BLOCK C83.56BOOKED
C-403BLOCK C83.56BOOKED
C-404BLOCK C83.56BOOKED
C-501BLOCK C83.56BOOKED
C-502BLOCK C83.56BOOKED
C-503BLOCK C83.56BOOKED
C-504BLOCK C83.56BOOKED
C-601BLOCK C83.56BOOKED
C-602BLOCK C83.56BOOKED
C-603BLOCK C83.56BOOKED
C-604BLOCK C83.56BOOKED
C-701BLOCK C83.56BOOKED
C-702BLOCK C83.56BOOKED
C-703BLOCK C83.56BOOKED
C-704BLOCK C83.56UNBOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%20182019202020212022October 2018 — 40.11% builtJanuary 2019 — 44.31% builtApril 2019 — 50.79% builtJuly 2019 — 51.74% builtOctober 2019 — 60.24% builtJanuary 2020 — 62.55% builtApril 2020 — 67.63% builtOctober 2020 — 78.46% builtJanuary 2021 — 85.96% builtApril 2021 — 94.07% builtJuly 2021 — 100% builtJanuary 2022 — 100% builtApril 2022 — 100% builtJune 2022 — 100% built

14 quarterly returns · October 2018 (40.11%) to June 2022 (100%)

40.11%

Initial progress · October 2018

100%

Final progress · June 2022

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2018

    Registration

  2. 2019

    Complaint · Annual Compliance

  3. 2021

    Extension · Annual Compliance

  4. 2023

    Annual Compliance

  5. 2025

    Complaint

  6. 2026

    Complaint

  7. Undated

    Challan

  8. 2026

    Snapshot reviewed

Full application ledger (11 rows)
  1. Registration — 2018-05-03 13:49:34.000000
  2. Extension — 2021-09-20 12:09:05
  3. Complaint — 2019-04-05 16:35:25 · SM-65/2019 (CLOSED)
  4. Complaint — 2026-09-14 13:01:24 · GJ/CMP/OFC/Gandhinagar/220310/000056 (CLOSED)
  5. Complaint — 2025-06-05 14:10:54 · CMP0312202200612 (CLOSED)
  6. Complaint — 2025-06-05 14:19:57 · CMP2802202300764 (CLOSED)
  7. Challan — undated · SM-65/2019 (status not published)
  8. Annual Compliance — 2019-10-25 12:17:43
  9. Annual Compliance — 2021-01-30 15:34:57
  10. Annual Compliance — 2023-11-17 21:07:41
  11. Annual Compliance — 2023-11-17 21:07:41

Quarterly filing history

2018

Q-1 · Q-2

2019

Q-3 · Q-4 · Q-5 · Q-6

2020

Q-7 · Q-9 · Q-10

—

Q-8 · X-1

2021

X-1 · X-2 · X-2

2022

X-3 · Q-E

14 submitted · 2 missing

Documents on file

39 documents

Missing from this record: Registration certificate, Title clearance certificate, Title report.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA02539/EX1/200921 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Kudasan
TP scheme
( Kudasan-Randesan-Raysan )
Authority
Gandhinagar Urban Development Authority
Covered area
1382.95 sq m
Open area
2405.05 sq m
Land cost
₹3.46 Cr
Estimated cost
₹26.9 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/180414/005079
Covered parking
257 · 3537 sq m
Parking for sale
0

Escrow account

Bank
STATE BANK OF INDIA
Branch
Suman City,Sector 11,Gandhinagar
IFSC
SBIN0032214
Account
XXXX-5596
Deposited
₹0.37 Cr
Withdrawn
₹0.81 Cr
Closing
₹0.06 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
PRAGNA P MACHHAR
Site visit
2022-05-16
Form-1 PDF
Open file
  • Block BLOCK A100%
  • Block BLOCK B100%
  • Block BLOCK C100%
Phase actual dates (3 blocks)
  • Block BLOCK A: excavation — → slab —
  • Block BLOCK B: excavation — → slab —
  • Block BLOCK C: excavation — → slab —

Filing PDFs

Project team on record

  • Vasant Soni · engineer
  • Pragna Machhar · architect
How is the paperwork score calculated?66 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    22 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    4 / 15

  • Delivery 2022-05-31 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 14/16 -> 22/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 4 complaints + 1 extension -> 4/15

Confidence Medium: QPR filing rate 87.5% is below 90%; no completed project on the promoter record; 4 complaint entries on the ledger; 1 extension request on the ledger.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA02539/EX1/200921

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.