Delivered

Shree Satvat

"SHREE SATVAT", Near D M Service Station,

Mixed Development63 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/6165

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA02789/EX1/051219

Shree Satvat — residential developmentGandhinagar · representative residential imagery

Paperwork score

Some gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings7 / 9
Recorded complaints0
Extensions1
Promoter projectsNone completed on record

Project at a glance

Developer
Saumya Developers
Project type
Mixed Development
Total units
63
Project cost
₹10.08 Cr
Carpet area
5,185.9 sq m
Price band
₹16L – ₹0L
Carpet area per unit
18.28-130.45 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Mixed Development — 63 units · carpet 5,185.86 sq m
  • Block A
  • Block B
  • Block C
  • Declared start 2017-12-22 · completion 2020-09-30
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.1584° N, 72.6531° E

Filed plot outline · 6 corners
Open in Google Maps

Units & inventory

63

Total units

43

Booked (68%)

20

Unsold (32%)

68% booked · 32% unsold

Tower A23 units

21 booked (91%) · 2 available (9%)

Tower B20 units

15 booked (75%) · 5 available (25%)

Tower C20 units

7 booked (35%) · 13 available (65%)

Flat-level inventory (63 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
A-01A35.5UNBOOKED
A-02A28.67UNBOOKED
A-03A36.88BOOKED
A-04A21BOOKED
A-05A22.79BOOKED
A-06A22.84BOOKED
A-07A22.74BOOKED
A-08A29.63BOOKED
A-09A27.81BOOKED
A-10A19.07BOOKED
A-11A18.28BOOKED
A-101A116.89BOOKED
A-102A120.34BOOKED
A-103A130.45BOOKED
A-104A128.53BOOKED
A-201A116.89BOOKED
A-202A113.51BOOKED
A-203A118.01BOOKED
A-204A118.01BOOKED
A-301A116.89BOOKED
A-302A113.51BOOKED
A-303A118.01BOOKED
A-304A118.01BOOKED
B-101B92.19BOOKED
B-102B92.19UNBOOKED
B-103B70.59BOOKED
B-104B70.59BOOKED
B-201B92.19BOOKED
B-202B92.19UNBOOKED
B-203B70.59BOOKED
B-204B70.59BOOKED
B-301B92.19BOOKED
B-302B92.19UNBOOKED
B-303B70.59BOOKED
B-304B70.59BOOKED
B-401B92.19BOOKED
B-402B92.19UNBOOKED
B-403B70.59BOOKED
B-404B70.59BOOKED
B-501B92.19BOOKED
B-502B92.19UNBOOKED
B-503B70.59BOOKED
B-504B70.59BOOKED
C-101C92.19UNBOOKED
C-102C92.19UNBOOKED
C-103C92.19BOOKED
C-104C92.19BOOKED
C-201C92.19UNBOOKED
C-202C92.19BOOKED
C-203C92.19BOOKED
C-204C92.19BOOKED
C-301C92.19UNBOOKED
C-302C92.19UNBOOKED
C-303C92.19BOOKED
C-304C92.19BOOKED
C-401C92.19UNBOOKED
C-402C92.19UNBOOKED
C-403C92.19UNBOOKED
C-404C92.19UNBOOKED
C-501C92.19UNBOOKED
C-502C92.19UNBOOKED
C-503C92.19UNBOOKED
C-504C92.19UNBOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%201820192020November 2018 — 46.52% builtFebruary 2019 — 58.85% builtMay 2019 — 68.47% builtAugust 2019 — 76.88% builtNovember 2019 — 88.36% builtFebruary 2020 — 95.91% builtOctober 2020 — 100% built

7 quarterly returns · November 2018 (46.52%) to October 2020 (100%)

46.52%

Initial progress · November 2018

100%

Final progress · October 2020

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2018

    Registration

  2. 2019

    Extension · Annual Compliance

  3. 2021

    Annual Compliance

  4. 2026

    Snapshot reviewed

Full application ledger (4 rows)
  1. Registration — 2018-06-01 16:09:14.000000
  2. Extension — 2019-12-05 11:43:02
  3. Annual Compliance — 2019-10-31 14:48:01
  4. Annual Compliance — 2021-01-27 13:00:47

Quarterly filing history

2018

Q-1

2019

Q-2 · Q-3 · Q-4 · Q-5

2020

X-1 · Q-E

—

X-2 · X-3

7 submitted · 2 missing

Documents on file

39 documents

Missing from this record: Registration certificate, Title clearance certificate, Title report.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA02789/EX1/051219 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Raisan
TP scheme
( Raisan-Randesan-Koba )
Authority
Gandhinagar Urban Development Authority
Covered area
1476.17 sq m
Open area
2229.83 sq m
Land cost
₹2.08 Cr
Estimated cost
₹8 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/180503/005283
Covered parking
64 · 3464.1 sq m
Parking for sale
6

Escrow account

Bank
ORIENTAL BANK OF COMMERCE
Branch
RAYSAN, GANDHINAGAR
IFSC
ORBC0101953
Account
XXXX-0086
Deposited
₹0.54 Cr
Withdrawn
₹0.45 Cr
Closing
₹1.27 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
MANUBHAI DESAI
Site visit
2020-01-30
Form-1 PDF
Open file
  • Block A100%
  • Block B100%
  • Block C100%
Phase actual dates (3 blocks)
  • Block A: excavation — → slab —
  • Block B: excavation — → slab —
  • Block C: excavation — → slab —

Filing PDFs

Project team on record

  • RAJESH PATEL · engineer
  • MANUBHAI DESAI · architect
How is the paperwork score calculated?70 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    19 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    11 / 15

  • Delivery 2020-09-30 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 7/9 -> 19/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 1 extension -> 11/15

Confidence Medium: QPR filing rate 77.8% is below 90%; no completed project on the promoter record; 1 extension request on the ledger.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA02789/EX1/051219

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.