Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Ongoing

Bosky Pride

375 1 A Q OP 157

Commercial79 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/6409

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/CAA04047/171118

Bosky Pride — residential developmentGandhinagar · representative residential imagery

Paperwork score

Material gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusOngoing
Quarterly filings15 / 16
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Rudra Infrastructure
Project type
Commercial
Total units
79
Project cost
₹3.42 Cr
Carpet area
2,205.7 sq m
Price band
₹3L – ₹0L
Carpet area per unit
15.16-79.42 sq m
Status
Ongoing
Filing extras — blocks, inventory lines, dates
  • Commercial — 79 units · carpet 2,205.71 sq m
  • Block A
  • Declared start 2017-02-07 · completion 2022-09-30
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.2659° N, 72.6689° E

Filed plot outline · 8 corners
Open in Google Maps

Units & inventory

79

Total units

43

Booked (54%)

36

Unsold (46%)

54% booked · 46% unsold

Tower A79 units

43 booked (54%) · 36 available (46%)

Flat-level inventory (79 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
1A27.52BOOKED
2A29.66BOOKED
3A32.49BOOKED
4A33.93BOOKED
5A36.07BOOKED
6A38.21BOOKED
7A27.45BOOKED
8A26.66BOOKED
9A26.14BOOKED
10A25.62UNBOOKED
11A24.83BOOKED
12A21.64BOOKED
13A23.79BOOKED
14A23.79BOOKED
15A23.79BOOKED
16A23.79BOOKED
17A23.79BOOKED
18A20.65BOOKED
19A37.4BOOKED
20A35.46BOOKED
21A35.46BOOKED
22A36.11BOOKED
23A21.91BOOKED
24A23.82BOOKED
25A23.82BOOKED
26A23.82BOOKED
27A21.43BOOKED
28A21.91BOOKED
29A21.91BOOKED
30A22.86BOOKED
101A27.79BOOKED
102A24.31BOOKED
103A27.03BOOKED
104A28.59BOOKED
105A30.73BOOKED
106A34.97BOOKED
107A27.45BOOKED
108A18.04BOOKED
109A33.09UNBOOKED
110A31.89UNBOOKED
111A30.32UNBOOKED
112A29.98BOOKED
113A15.16UNBOOKED
114A23.79BOOKED
115A37.4BOOKED
116A27.15BOOKED
117A27.15BOOKED
118A27.65BOOKED
119A21.91UNBOOKED
120A23.82UNBOOKED
121A23.82UNBOOKED
122A23.82UNBOOKED
123A21.43UNBOOKED
124A21.91UNBOOKED
125A21.91UNBOOKED
126A22.86UNBOOKED
201A70.28UNBOOKED
202A79.42UNBOOKED
203A71.05UNBOOKED
204A18.56UNBOOKED
205A18.04UNBOOKED
206A33.6UNBOOKED
207A31.89UNBOOKED
208A30.32UNBOOKED
209A29.98UNBOOKED
210A15.16UNBOOKED
211A15.16UNBOOKED
212A28.64UNBOOKED
213A27.15UNBOOKED
214A27.15UNBOOKED
215A27.65UNBOOKED
216A21.91UNBOOKED
217A23.82UNBOOKED
218A23.82UNBOOKED
219A23.82UNBOOKED
220A21.91UNBOOKED
221A21.91UNBOOKED
222A21.91UNBOOKED
223A22.86UNBOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 97%
0%25%50%75%100%2019202020212022April 2019 — 86.91% builtJuly 2019 — 86.91% builtOctober 2019 — 86.98% builtJanuary 2020 — 88.69% builtApril 2020 — 88.69% builtOctober 2020 — 88.69% builtJanuary 2021 — 88.69% builtApril 2021 — 88.69% builtJuly 2021 — 88.69% builtOctober 2021 — 91.69% builtJanuary 2022 — 91.69% builtApril 2022 — 91.69% builtJuly 2022 — 91.69% builtOctober 2022 — 91.69% builtOctober 2022 — 97% built

15 quarterly returns · April 2019 (86.91%) to October 2022 (97%)

86.91%

Initial progress · April 2019

97%

Final progress · October 2022

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2018

    Registration

  2. 2019

    Annual Compliance

  3. 2021

    Annual Compliance

  4. 2023

    Annual Compliance

  5. 2026

    Snapshot reviewed

Full application ledger (6 rows)
  1. Registration — 2018-11-17 12:30:48.000000
  2. Annual Compliance — 2019-10-19 18:47:12
  3. Annual Compliance — 2021-01-30 14:00:20
  4. Annual Compliance — 2021-12-31 13:11:32
  5. Annual Compliance — 2023-11-17 21:08:05
  6. Annual Compliance — 2023-11-17 21:08:05

Quarterly filing history

2019

Q-1 · Q-2 · Q-3 · Q-4

2020

Q-5 · Q-7 · Q-8

—

Q-6

2021

Q-9 · Q-10 · Q-11 · Q-12

2022

Q-13 · X-1 · X-2 · Q-E

15 submitted · 1 missing

Documents on file

39 documents

Missing from this record: Registration certificate, Title clearance certificate, Title report.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/CAA04047/171118 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Pethapur
TP scheme
( Pethapur )
Final / sub plot
-
Authority
Gandhinagar Urban Development Authority
Covered area
959 sq m
Open area
1076 sq m
Land cost
₹0.72 Cr
Estimated cost
₹2.7 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/180606/005512
Parking for sale
0

Escrow account

Bank
HDFC
Branch
GANDHINAGAR
IFSC
HDFC0000190
Account
XXXX-9441
Deposited
₹0.6 Cr
Withdrawn
₹0.19 Cr
Closing
₹0.7 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
AKASH GAJJAR
Site visit
2022-08-31
Form-1 PDF
Open file
  • Block A100%
Phase actual dates (1 block)
  • Block A: excavation — → slab —

Filing PDFs

Project team on record

  • ARVIND C MEHTA · engineer
  • AKASH GAJJAR · architect
How is the paperwork score calculated?50 / 100
  • Delivery standing

    12 / 40

  • Filing discipline

    23 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2022-09-30 elapsed 3 yr ago, progress 97% -> 12/40
  • QPR filings 15/16 -> 23/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: declared completion date elapsed 3 years ago with work still declared incomplete; no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/CAA04047/171118

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.