Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Ongoing

Shalin 6

S.R.No. 1575/1,S.R.No. 371/1/A

ResidentialGroup Housing80 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/6662

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA03453/190918

Shalin 6 — residential developmentGandhinagar · representative residential imagery

Paperwork score

Material gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusOngoing
Quarterly filings16 / 21
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Mukeshbhai Vitthalbhai Patel Proprietor Of Shalin Buildcon
Project type
Residential / Group Housing
Total units
80
Project cost
₹15.95 Cr
Carpet area
5,388.8 sq m
Price band
₹17L – ₹0L
Carpet area per unit
62.6-76.19 sq m
Status
Ongoing
Filing extras — blocks, inventory lines, dates
  • Residential/Group Housing — 80 units · carpet 5,388.76 sq m
  • Block BLOCK A
  • Block BLOCK B
  • Block BLOCK C
  • Declared start 2018-06-01 · completion 2023-11-30
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.2290° N, 72.6180° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

80

Total units

78

Booked (98%)

2

Unsold (2%)

98% booked · 2% unsold

Tower BLOCK A28 units

28 booked (100%) · 0 available (0%)

Tower BLOCK B24 units

23 booked (96%) · 1 available (4%)

Tower BLOCK C28 units

27 booked (96%) · 1 available (4%)

Flat-level inventory (80 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
A-101BLOCK A62.6BOOKED
A-102BLOCK A62.6BOOKED
A-103BLOCK A62.6BOOKED
A-104BLOCK A62.6BOOKED
A-201BLOCK A62.6BOOKED
A-202BLOCK A62.6BOOKED
A-203BLOCK A62.6BOOKED
A-204BLOCK A62.6BOOKED
A-301BLOCK A62.6BOOKED
A-302BLOCK A62.6BOOKED
A-303BLOCK A62.6BOOKED
A-304BLOCK A62.6BOOKED
A-401BLOCK A62.6BOOKED
A-402BLOCK A62.6BOOKED
A-403BLOCK A62.6BOOKED
A-404BLOCK A62.6BOOKED
A-501BLOCK A62.6BOOKED
A-502BLOCK A62.6BOOKED
A-503BLOCK A62.6BOOKED
A-504BLOCK A62.6BOOKED
A-601BLOCK A62.6BOOKED
A-602BLOCK A62.6BOOKED
A-603BLOCK A62.6BOOKED
A-604BLOCK A62.6BOOKED
A-701BLOCK A62.6BOOKED
A-702BLOCK A62.6BOOKED
A-703BLOCK A62.6BOOKED
A-704BLOCK A62.6BOOKED
B-101BLOCK B76.19BOOKED
B-102BLOCK B76.19BOOKED
B-103BLOCK B76.19BOOKED
B-104BLOCK B76.19UNBOOKED
B-201BLOCK B76.19BOOKED
B-202BLOCK B76.19BOOKED
B-203BLOCK B76.19BOOKED
B-204BLOCK B76.19BOOKED
B-301BLOCK B76.19BOOKED
B-302BLOCK B76.19BOOKED
B-303BLOCK B76.19BOOKED
B-304BLOCK B76.19BOOKED
B-401BLOCK B76.19BOOKED
B-402BLOCK B76.19BOOKED
B-403BLOCK B76.19BOOKED
B-404BLOCK B76.19BOOKED
B-501BLOCK B76.19BOOKED
B-502BLOCK B76.19BOOKED
B-503BLOCK B76.19BOOKED
B-504BLOCK B76.19BOOKED
B-601BLOCK B76.19BOOKED
B-602BLOCK B76.19BOOKED
B-603BLOCK B76.19BOOKED
B-604BLOCK B76.19BOOKED
C-101BLOCK C64.55BOOKED
C-102BLOCK C64.55BOOKED
C-103BLOCK C64.55BOOKED
C-104BLOCK C64.55BOOKED
C-201BLOCK C64.55BOOKED
C-202BLOCK C64.55BOOKED
C-203BLOCK C64.55BOOKED
C-204BLOCK C64.55BOOKED
C-301BLOCK C64.55BOOKED
C-302BLOCK C64.55BOOKED
C-303BLOCK C64.55BOOKED
C-304BLOCK C64.55BOOKED
C-401BLOCK C64.55BOOKED
C-402BLOCK C64.55BOOKED
C-403BLOCK C64.55BOOKED
C-404BLOCK C64.55BOOKED
C-501BLOCK C64.55BOOKED
C-502BLOCK C64.55BOOKED
C-503BLOCK C64.55BOOKED
C-504BLOCK C64.55BOOKED
C-601BLOCK C64.55BOOKED
C-602BLOCK C64.55BOOKED
C-603BLOCK C64.55BOOKED
C-604BLOCK C64.55BOOKED
C-701BLOCK C64.55BOOKED
C-702BLOCK C64.55BOOKED
C-703BLOCK C64.55UNBOOKED
C-704BLOCK C64.55BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 87.25%
0%25%50%75%100%20192020202120222023February 2019 — 9.56% builtMay 2019 — 19.12% builtAugust 2019 — 26.35% builtNovember 2019 — 33.26% builtFebruary 2020 — 36.74% builtAugust 2020 — 42.62% builtNovember 2020 — 47% builtFebruary 2021 — 52.88% builtMay 2021 — 60.52% builtAugust 2021 — 66.23% builtNovember 2021 — 81.34% builtFebruary 2022 — 85.48% builtMay 2022 — 85.48% builtAugust 2022 — 87.25% builtNovember 2022 — 87.25% builtDecember 2023 — 87.25% built

16 quarterly returns · February 2019 (9.56%) to December 2023 (87.25%)

9.56%

Initial progress · February 2019

87.25%

Final progress · December 2023

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2018

    Registration

  2. 2019

    Annual Compliance

  3. 2021

    Annual Compliance

  4. 2023

    Annual Compliance

  5. Undated

    Annual Compliance

  6. 2026

    Snapshot reviewed

Full application ledger (7 rows)
  1. Registration — 2018-09-19 14:24:48.000000
  2. Annual Compliance — 2019-10-24 12:55:22
  3. Annual Compliance — 2021-01-27 11:27:52
  4. Annual Compliance — 2023-11-17 21:08:21
  5. Annual Compliance — 2023-11-17 21:08:21
  6. Annual Compliance — undated
  7. Annual Compliance — undated

Quarterly filing history

2019

Q-1 · Q-2 · Q-3 · Q-4

2020

Q-5 · Q-7 · Q-8

—

Q-6 · Q-17 · Q-18 · X-1 · X-2

2021

Q-9 · Q-10 · Q-11 · Q-12

2022

Q-13 · Q-14 · Q-15 · Q-16

2023

Q-E

16 submitted · 5 missing

Documents on file

39 documents

Missing from this record: Registration certificate, Title clearance certificate, Title report.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA03453/190918 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Gandhinagar
TP scheme
Vavol
Final / sub plot
-
Authority
Gandhinagar Urban Development Authority
Covered area
1007.87 sq m
Open area
1686.13 sq m
Land cost
₹1.6 Cr
Estimated cost
₹14.34 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/180714/005750
Covered parking
7 · 2289.12 sq m
Parking for sale
0

Escrow account

Bank
Kalupur Commercial Co-operative Bank Ltd.
Branch
K.B.Pharmacy Campus,Gandhinagar
IFSC
KCCB0GNR038
Account
XXXX-0007
Deposited
₹3.49 Cr
Withdrawn
₹3.71 Cr
Closing
₹0.04 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
MANISH MEHTA
Site visit
2022-12-15
Form-1 PDF
Open file
  • Block BLOCK A85%
  • Block BLOCK B85%
  • Block BLOCK C85%
Phase actual dates (3 blocks)
  • Block BLOCK A: excavation — → slab —
  • Block BLOCK B: excavation — → slab —
  • Block BLOCK C: excavation — → slab —

Filing PDFs

Project team on record

  • HIMANSHU A. PATEL · engineer
  • MANISH P. MEHTA · architect
How is the paperwork score calculated?46 / 100
  • Delivery standing

    12 / 40

  • Filing discipline

    19 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2023-11-30 elapsed 2 yr ago, progress 87.25% -> 12/40
  • QPR filings 16/21 -> 19/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: declared completion date elapsed 2 years ago with work still declared incomplete; QPR filing rate 76.2% is below 90%; no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA03453/190918

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.